Wind and snow are the most ordinary loads on any building, and AIST Technical Report No. 13 (2021) mostly defers to the local building code and ASCE 7 for them. But it adds a few points that are specific to mill buildings, and it links both loads to the crane runway through limits on frame drift and rail gauge. Those links are what make wind and snow design in a mill different from a warehouse. This article covers Sections 3.2, 3.3 and 3.5, the drift and gauge rules in Section 5.3, and the commentary that explains them.
Roof live load first
Before snow, Section 3.2 sets a roof live load of at least about 0.96 kPa (20 psf) on all or part of the horizontal projection, placed for the worst effect, and not reducible. ASCE 7 lets roof live load drop for large tributary areas; TR-13 does not. On a long-span mill roof with large tributary areas per frame, this is a noticeable difference. The roof live load and the snow load are not added together; the larger governs in the usual combinations.
Snow: follow the code, check everything
Section 3.3 asks that ground and roof snow loads be calculated to the local building code, and lists the effects to evaluate:
- unbalanced snow on pitched and curved roofs;
- drifts at roof steps, parapets, monitors and adjacent buildings;
- sliding snow from higher roofs onto lower ones;
- rain-on-snow surcharge;
- ice dams;
- ponding instability.
Where the local code is silent, the designer uses ASCE 7. None of this is unusual, but mill roofs have more of the features that cause drifts than most buildings: multiple aisles at different heights, roof monitors and ventilators, large ducts and fan housings, and low lean-to bays beside tall crane aisles. Each step in the roof line can collect a drift several times the balanced snow load.
Ponding is worth a special mention. Mill roofs often have long spans and light purlins, and if the roof deflects enough under rain or melt water to hold more water, the load can grow until the members fail. ASCE 7 and AISC 360 both require a ponding check, and TR-13 lists it explicitly.
Wind: the internal pressure question
Section 3.5 asks that buildings meet the wind requirements of the local code, with speed and exposure from the code or ASCE 7, unless the owner sets higher loads. Then it adds the point most specific to mills:
Building configurations and production operations that may create internal pressure conditions consistent with partially enclosed structures shall be accounted for.
In plain terms: if the plant runs with large doors open for rail cars and trucks, or has open wall areas for ventilation over hot processes, the building may behave as partially enclosed in a storm. ASCE 7 then gives much higher internal pressure coefficients, which add to the external pressures on the roof and walls. Designing a mill as "enclosed" because its walls are clad, when in practice the scrap bay doors are always open, is a common and risky shortcut.
Section 3.5 also notes that structures outside the scope of the local code are designed to appropriate national standards. TR-13's example is tall exhaust stacks, which can be excited by vortex shedding. Fume system stacks and tall ducts on mill roofs fall in this group. Section 3.10.4 adds that roof-supported structures such as towers, racks, tanks, monitors, ventilators, stacks and large ducts must be designed for wind as well, and the owner supplies their loads and geometry.
Drift at the crane girder
Here TR-13 ties wind to the runway. Section 5.3 limits frame lateral drift at the top of the crane girders to height/400 from the column base, or about 50 mm (2 in), whichever is less, under each of two load conditions:
- the crane lateral forces in TR-13;
- building wind loads for a wind with an annual probability of exceedance of no more than 10%, which is a 10-year return period.
The 10-year wind is a serviceability event, much lower than the strength design wind in ASCE 7. The idea is that the crane should run normally in the storms that happen every few years. The limits may be exceeded only if it can be shown that the total drift will not harm the durability of the building or the operation of the equipment.
The commentary adds useful judgment. These limits are meant for moderate to high use runways in low to moderate height buildings. In a tall building with a lightly used crane, such as a galvanizing tower, a tighter limit could add steel with little benefit, and the owner may agree a more relaxed criterion for that area. Our article on crane girder deflection and drift limits covers the crane side of this rule.
Rail gauge and frame spread under snow
The second link is through gravity. A transverse moment frame spreads outward at the top of its columns when the roof is loaded, and that spread moves the crane rails apart. Section 5.3 limits the change in rail gauge under gravity loads, from an elastic analysis, to between +25 mm and -12 mm (+1 in and -1/2 in) of the specified gauge.
For this check only, snow loads may be reduced:
| Design snow load | Reduction allowed for the gauge check |
|---|---|
| About 1.44 kPa (30 psf) or less | 50% |
| More than about 1.44 kPa (30 psf) | 25% |
The commentary explains why the rule exists: in northern climates with heavy snow, frame spread can push the runway out of alignment unless the frame is stiff enough. A crane with double-flanged wheels tolerates only a small gauge error before the wheel flanges start to bind on the rail.
There are three ways to control the spread: a stiffer frame (deeper rafters, stiffer columns, fixed bases), a roof truss with a tie at the bottom chord that limits the spread, or rail and girder details that allow some adjustment. Most mill designs use the first two.
The longitudinal direction
Wind also blows along the building. On a long mill, the end walls catch the wind and the roof and wall bracing carry it to the longitudinal braced bays, together with crane traction and bumper forces and any seismic load. TR-13 Section 5.5 recommends placing the vertical bracing roughly midway between expansion joints, with braced sections no more than about 60 m (200 ft) apart, and asks that the drift of this system meet the same criteria as Section 5.3. The end wall framing, often called wind columns or gable posts, spans from the floor or a grade wall to the roof bracing and is designed for the full end wall pressure. On a tall crane aisle these posts can be long and heavy, and they may need a horizontal wind girder at the crane level to shorten their span.
A short checklist for the design basis
Pulling the TR-13 points together, the basis of design for a mill building should record:
- the wind speed, exposure category and enclosure classification, with the openings assumed open in a storm;
- the ground snow load, the roof snow loads and every drift location checked;
- the roof live load, stated as non-reducible;
- the drift limit at the crane girder for crane forces and for the 10-year wind;
- the rail gauge tolerance and the snow reduction used for that check;
- wind and dust loads for roof-mounted monitors, ducts, fans and stacks, with the owner's data.
Writing these down at the start avoids the most common late change on mill projects: discovering during design review that the frames were checked for an enclosed building while the plant expects to run with the big doors open.
Walls and secondary framing
Wind reaches the frames through the cladding, girts and purlins. TR-13 Section 5.11 asks that girts and purlins be designed to their own specifications for the code wind loads, and to consider other effects such as falling ice, bulk material buildup, vehicle impact and heat. Our article on girts and purlins in mill buildings covers them. Large door openings for rail and vehicle access need jamb and header framing designed for the full wind load with the door closed and the internal pressure case with it open.
How World Steel applies it
World Steel designs and fabricates steel buildings for US sites from Florida to Washington, including high-wind and heavy snow regions. On a mill building, our engineers:
- take wind speed, exposure and ground snow from the local code and ASCE 7 for the site;
- agree with the owner which doors and openings may be open in a storm, and design for partially enclosed pressures where needed;
- check roof drifts at every step, monitor and duct, and check ponding on long spans;
- check crane-level drift under crane forces and the 10-year wind, and rail gauge under gravity with TR-13's snow reduction.
Our wind and seismic design page shows how we document these checks. The US Engineer of Record reviews and seals the design. Fabrication is in our plant in Vietnam, accredited under IAS AC472 and audited twice a year. Site work is the US contractor's scope.
Solutions and the Sunpro Steel project
Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays, and see the ASCE 7 page for the load basis. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, is where TR-13's drift and frame guidance was applied at full scale.
Source and limits
This article paraphrases AIST Technical Report No. 13 (2021), Sections 3.2, 3.3, 3.5, 3.10.4, 5.3 and 5.11 and the commentary to Section 5.3, and quotes one sentence of Section 3.5. Wind and snow loads are set by the local building code and the Engineer of Record on each project.
Quick answers
What drift limit does AIST TR-13 set at the crane girder?
Frame drift at the top of the crane girder no more than height/400 or about 50 mm (2 in), whichever is less, under crane lateral forces and, separately, under wind with a 10-year return period.
How much can the crane rail gauge change under gravity loads?
Within +25 mm and -12 mm (+1 in, -1/2 in) of the specified gauge. For this check, snow of about 1.44 kPa (30 psf) or less may be cut by 50%, and heavier snow by 25%.
Why does internal pressure matter in a mill?
Large doors and open sides kept open for production can make the building behave as partially enclosed, which raises the wind pressure on the roof and walls. AIST TR-13 asks that this be accounted for.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors