Skip to content
Seeking US contractor partners IAS AC472 ACCREDITED ★ METAL BUILDINGS ★ AC472 IAS AC472 accreditedIAS AC472
World Steel USA
Steel frame with crane runway brackets, showing column seats and girder ends

Quality and certification

Crane column and girder end tolerances: shop limits that keep the rail straight

Normal building tolerances are not enough for a crane runway. AIST TR-13 adds tighter limits for crane columns and girder ends, and splits each one into fabrication or erection, so everyone knows who owns it.

· updated November 22, 2026 · 3 min read · World Steel USA engineering team

Crane problems very often trace back to a rail that is out of line, and a rail is only as straight as the girders and columns under it. AIST Technical Report No. 13 (2021), Section 5.17 and its commentary, adds tighter tolerances for the parts unique to crane runways, and labels each one fabrication or erection so responsibility is clear. Our earlier article on crane runway beam tolerances gives the overview; this one goes into the TR-13 numbers.

Why tighter than normal

The commentary is direct: in crane buildings, mill, shop and site tolerances can stack up until the rail cannot be aligned. TR-13 does not replace the AISC Code of Standard Practice; it supplements it with stricter limits on the items that control rail alignment.

Column base lines and anchor rods (erection)

  • Column base lines are set out as parallel lines with gauge held to about ±3 mm (⅛ in).
  • Anchor rods follow ACI 117 and the AISC Code of Standard Practice.

Base plates (fabrication)

Base plate to column connections are fabricated to AISC 360 Chapter M and finished to the Code of Standard Practice. If contact bearing is not achieved, the welds must carry the full load with fatigue considered. The commentary mentions a maximum gap of about 0.4 mm (1/64 in) over the column section, because some weld types are fatigue-sensitive where bearing is poor.

Crane columns

Fabrication. The column is built to a work line between its bottom and top work points. The work point at the crane girder seat may not vary more than about ±3 mm (⅛ in) from that line. The top of the column section under the girder seat plate is finished and cut square to the column axis within about 0.8 mm per 300 mm (1/32 in per 12 in) of depth or width.

Erection. Columns are plumbed to the Code of Standard Practice, with the top of the girder seat plate within about ±3 mm (⅛ in) of the column line and of its elevation.

Girders: sweep and camber (fabrication)

  • Horizontal sweep: no more than about 6 mm per 15 m (¼ in per 50 ft) of span.
  • Camber: no more than about +6 mm, −0 mm per 15 m (+¼ in, −0 per 50 ft) over the drawing value, and always upward. Rolled beams are set with natural camber up; plate girders get a welding sequence that leaves any camber up.

Girder ends (fabrication and erection)

The girder end bears on the column cap plate and must sit evenly, so TR-13 asks for:

  • a flat bottom flange, perpendicular to the web, with flatness of about ±0.8 mm (1/32 in) in the bearing zone defined on the drawings;
  • web-to-bottom-flange squareness within about 0.4 mm per 300 mm (1/64 in per ft) of flange width;
  • top flange squareness within about 3 mm per 300 mm (⅛ in per ft) of flange width, to seat the rail evenly across joints;
  • at erection, girder centerline within about ±3 mm (⅛ in) of theory at the columns.

The commentary explains why: small gaps that open and close as the crane passes can fatigue the pretensioned seat bolts. It even suggests the designer may choose not to fully tighten those bolts, staking the threads instead.

Girder depths (fabrication and erection)

Girder ends are made to a keep dimension within about ±1.6 mm (1/16 in). On rolled shapes, mill depth variation is made up with shim packs over the full contact area, captured by the seat bolts and supplied by the fabricator. At erection, adjacent girder tops at a column may differ by no more than about 1.6 mm.

Rail alignment and the survey (erection)

The final targets, rail center to center and line and level, are covered in crane rail joints, clips and pads. TR-13 recommends that the contractor provide a rail survey at the end of erection, tied to a stable benchmark, so future surveys can show whether settlement or wear is moving the runway.

How we hold the shop side

World Steel checks the fabrication items on this list at our plant before release: seat work points, cap plate squareness, girder sweep and camber, end flatness and keep depths, with the shim packs marked and shipped with the girders. Results go into the shop records and can be followed in PEB Studio. Erection tolerances and the rail survey are the US contractor's scope. See our crane runway girders, crane supporting columns, the Sunpro Steel mill and the crane design standards page.

Solutions and the Sunpro Steel project

See how this fits a complete job: the crane building system for runways, columns and cranes, manufacturing plants with crane bays for factory layouts, and heavy industrial plants for mills and process plants. All of it was put to work on the Sunpro Steel mill project, a 5,000 t steel production plant designed for overhead cranes up to 150 t.

Source and limits

This article paraphrases AIST Technical Report No. 13 (2021), Section 5.17 and the commentary; values are converted to metric and rounded. Use the report and the project specification for the exact limits.

Quick answers

Why are crane runway tolerances tighter than AISC defaults?

Mill, fabrication and erection tolerances add up. AIST TR-13 tightens the ones that decide rail alignment so the final runway can still meet the rail tolerances that cranes need.

What is a keep dimension on a crane girder?

A fixed depth at the girder ends, held to about ±1.6 mm (±1/16 in), so the rail seats evenly across girder joints. Shim packs make up mill depth tolerance on rolled shapes.

Who is responsible for each tolerance?

TR-13 labels each one as fabrication or erection. The fabricator owns shop limits such as cap plate squareness and girder flatness; the erector owns set-out, plumbness and rail alignment.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AIST TR-13 mill building series

Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.

30 articles · 6 parts

Crane classes and loadsSections 1.4–1.5, 3.7, 3.11

Building class, dynamic crane forces, load combinations and the crane data.

Site, soil and foundationsSections 2, 3.13, 4

Soil investigation, foundations under heavy cranes and the floor slab.

Frame, roof and floorsSections 5.2–5.14

Columns, bracing, trusses, girts, equipment floors and connections.

Runway girders and railsSections 3.7.3, 5.8, 5.15

Fatigue details, stiffness, backup bracing, end stops and the rail system.

Shop, testing and serviceSections 1.6, 5.16–5.17, App. C

Weld testing, tolerances, maintenance access, inspection and upgrades.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.