Most of the steel in a mill building is there to carry cranes, and every crane load ends up in a footing, a pile cap or a caisson. If one column settles more than its neighbors, the girder tilts, the rail drops out of line and the crane starts to wear its wheels and the rail. AIST Technical Report No. 13 (2021) handles this in Section 3.13 (loads on building foundations) and Section 4.0 (foundations, floors and walls), with commentary that is blunt about the risk.
The cost of getting it wrong is high. Correcting a settled crane column after the building is in production means shutting down the bay, jacking the girders, re-shimming the seats and re-aligning the rail, and if the cause is still active, doing it again later. Designing the foundation for the runway from the start is far cheaper.
This article goes through what TR-13 asks of the foundation design and construction, and then sets out where the steel structure meets it. On a World Steel project the foundation design and the site work are by others, but the two packages have to agree on loads, base fixity, anchor rods and tolerances.
Loads the foundations must carry
Section 3.13 asks that foundations safely carry every load transmitted to them, within the limits of the Project Geotechnical Report, with due attention to total and differential settlement. The loads to consider include:
- column reactions from the steel frame, for every load combination;
- reactions from grade beams;
- surcharge from equipment and stored material around the foundations.
TR-13 adds that the material storage loads assumed must be shown clearly on the design drawings. The commentary explains why: surcharge from product stacked at grade near the columns is often large in warehouse and shipping bays, and if it is missed it causes differential movement and real trouble with crane rail alignment. A coil yard or slab storage bay inside a crane building is the classic case.
The commentary also states plainly that deep foundations are often needed for buildings that carry heavy cranes, and that the geotechnical engineer must fully understand the size and nature of the loads, including the overhead cranes. Repeated crane loading is not the same as a static warehouse load.
Concrete basics
Section 4.2 keeps the concrete rules short. Design and construction follow ACI 318. The minimum compressive strength is about 21 MPa (3,000 psi) at 28 days unless specified otherwise, and the mix must suit the soil, including water-cement ratio and groundwater quality. Two items concern the steel directly:
Setting anchor rods (4.2.3). Rods should preferably be set with metal templates and without sleeves. If sleeves are used, they must be filled completely when the base plate is grouted, and water must be kept out of them until then.
Grouting base plates (4.2.4). Grout goes in after the columns have been plumbed and aligned. If shim packs are used for leveling and removed once the first grout has cured, the shim space must be filled with more grout. TR-13 points to ACI 351.1R for grouting larger base plates.
On a heavy crane column, a base plate can be 60 mm or more thick and well over a metre long. Grouting it properly matters, because a void under the plate changes how the column carries moment and can let the column rock under crane side thrust.
Soil-bearing foundations
For spread footings, Section 4.3.1 lists what the owner must supply from the geotechnical engineer, through the Project Geotechnical Report:
- allowable bearing pressures;
- earth pressures and safety factors for sliding and overturning;
- estimated total and differential settlements for various footing sizes and depths, and coefficients for lateral movement;
- groundwater conditions;
- minimum footing depth for frost protection;
- the effect of overlapping pressures from existing and new structures, machine foundations, floor loads, walls, surcharges, excavations and vibrating equipment;
- testing of any steelmaking slag fill for expansion;
- concrete durability requirements.
Section 4.3.2 adds that where the groundwater level swings and the soil swells and shrinks with it, footings should go below the zone of influence, or the columns should go on piles or caissons instead. Section 4.3.3 asks that the effect of every new foundation on neighboring and buried structures be checked, which matters when a new bay is added beside a working mill.
Piles and caissons
For deep foundations, Section 4.4.1 asks the geotechnical report to give:
- allowable capacities and uplift, including group effects and minimum spacing;
- allowable total and differential settlement and base rotation;
- lateral resistance and the coefficient for lateral movement;
- the effects of neighboring structures, surcharges, vibrating equipment and negative skin friction;
- the depth to the point of support for checking pile column strength;
- corrosion protection where aggressive ground or electrolytic action is possible.
On that last point, TR-13 adds a specific warning: steel piling should not be used for electrical grounding where electrolytic action is possible. In a plant full of large electrical loads, this is easy to overlook.
Section 4.4.2 asks that pile members be designed for axial load, uplift and bending from gravity and lateral loads, with the lateral restraint the soil provides. Splices must develop the pile's design load in compression, tension, shear and bending (4.4.3), and piles or caissons in tension must be positively anchored to their caps (4.4.4). Crane columns with fixed bases can put large overturning moments into a pile group, so tension piles are not unusual.
Pile driving control
Section 4.4.5 reads like a site checklist:
| Item | TR-13 recommendation |
|---|---|
| Driving | Must not impair the pile; damaged heads cut back to sound material before driving continues |
| Group survey | Survey after driving a group to catch heave or lateral movement; re-drive piles that moved up |
| Plumbness | Within 2.5% of plumb |
| Location | No pile more than about 75 mm (3 in) from its design position |
| Records | Tip and cutoff elevations, location, orientation, resistance per 0.3 m (1 ft), and per 25 mm (1 in) over the last 300 mm (12 in) |
| Load tests | As the geotechnical report requires; at least two satisfactory tests unless the owner says otherwise |
These records go to the owner promptly. They also become part of the history of the runway: if a column later settles, the pile records are the first place to look.
Settlement and the crane runway
TR-13 does not give a single differential settlement limit for foundations; it leaves that to the geotechnical report and the designers. What it does give are the runway tolerances in Section 5.17 and the drift and gauge limits in Section 5.3, and those set the real target. A transverse frame whose two columns settle unequally rotates the girder seat and spreads or closes the rail gauge. A run of columns settling unevenly along the runway puts a dip in the rail.
That is why the foundation designer needs the steel designer's input on how much differential movement the runway can absorb, and why the steel designer needs the geotechnical engineer's settlement estimates. Shimming at the girder seats can absorb some movement after the fact, but it is maintenance, not design.
Time matters as well as size. Settlement on clay can continue for months or years after the building is loaded, so the runway that was surveyed in tolerance at handover may drift out of it later. Where the report predicts long-term consolidation, it helps to agree three things at design stage: how much adjustment the girder seats and rail clips must allow, when the follow-up runway surveys will be made, and who reads them against the original record drawings. Our article on the runway inspection program covers what those later surveys check.
Base fixity: one assumption, two designs
Section 5.3 notes that mill building column bases are usually fixed or partly fixed, and that the degree of fixity depends on the anchorage details, the foundation and the soil. That fixity must be accounted for in both the frame design and the foundation design.
In practice, the steel frame model and the foundation model must use the same assumption. If the steel designer assumes a fixed base to control drift at the crane girder level, the foundation must be stiff enough to deliver that fixity, and the anchor rods and base plate must be detailed for the moment. If the foundation is softer than assumed, drift and rail gauge change. Our article on crane column types covers the column bases themselves.
Where World Steel fits
World Steel designs and fabricates the steel structure; foundations, piling, grouting and all site work are the US contractor's scope. On a crane building, our part of the foundation interface is:
- a column reaction table by load case, issued early and updated when the frame changes;
- a stated base condition, fixed or pinned, agreed with the foundation designer;
- anchor bolts, nuts, washers and steel setting templates, supplied with the steel or ahead of it so they can be cast in on schedule;
- base plates with shear lugs where needed, and anchor hole layouts checked against the template;
- column base details drawn to suit the grout thickness and shim method on the foundation drawings.
The US Engineer of Record reviews and seals the design. Our plant in Vietnam is accredited under IAS AC472 and audited twice a year, and anchor bolt templates and base plates are checked against the same drawing before shipping. On the Sunpro Steel mill, with cranes up to 150 t, the crane supporting columns were laced built-up members with bases sized for fixed-base frame action, so getting this interface right was central to the job.
Solutions and the Sunpro Steel project
Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays. The Sunpro Steel mill project is where these TR-13 points were applied at full scale. Before this stage, see the geotechnical investigation article.
Source and limits
This article paraphrases AIST Technical Report No. 13 (2021), Sections 3.13, 4.1 to 4.4 and 5.3 and the commentary to Section 3.13. Foundation design is by the owner's or US contractor's engineers, who set the criteria on each project.
Quick answers
Why do heavy crane buildings often need deep foundations?
Because differential settlement between columns throws the crane rail out of line. AIST TR-13 notes that deep foundations are often required under heavy cranes, and that stored material near the columns can add surcharge that causes uneven movement.
What pile tolerances does AIST TR-13 give?
Vertical piles within 2.5% of plumb, and no pile more than about 75 mm (3 in) from its design location. Damaged pile heads are cut back to sound material, and at least two satisfactory load tests are recommended unless the owner says otherwise.
Who designs the foundations on a World Steel project?
The owner's or US contractor's engineers. World Steel designs and fabricates the steel and supplies column reactions, base details, anchor bolts and templates for the foundation design.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors
- Solutions by stateState-by-state steel solutions