A crane runway that is strong but flexible still causes trouble: wheels climb the rail, tiebacks crack, seat bolts loosen and the crane skews. AIST Technical Report No. 13 (2021) controls this with serviceability limits on girder deflection, frame drift and rail gauge. These limits often size the members more than strength does. Here is what they are and why they exist.
Vertical deflection of the girder
Section 5.8.7 limits the vertical deflection of a runway girder under one crane, without impact:
| Building class | Vertical limit |
|---|---|
| A and B | span / 1000 |
| C and D | span / 600 |
For a 12 m girder that is 12 mm in Class A or B and 20 mm in Class C or D.
The commentary explains the reason. The real target is end rotation. When a simply supported girder sags, its ends rotate, and the tieback connections at the top flange and the seat bolts at the bottom flange work back and forth every pass. Limiting deflection limits that rotation and the fatigue cracking and bolt failures it causes. The report notes that with spherical-bearing tiebacks and careful seat details some relaxation may be possible, and that multiple cranes and tandem lifts should be considered when the limits are set.
Lateral deflection
The girder's lateral deflection from the side thrust of one crane is limited to span / 400. On longer spans, TR-13 asks the designer to consider torsion from vertical wheel loads acting on a girder that has moved sideways. That is one reason longer girders get a backup bracing system, covered in backup trusses and box girders.
Camber on long girders
Girders over about 23 m (75 ft) are cambered for approximately dead load plus half the live load deflection, without impact (Section 5.8.8). The fabrication tolerance on that camber is tight and must point upward; see our article on crane column and girder end tolerances.
Frame drift at the top of the crane girder
The whole building frame must also stay stiff at runway level. Section 5.3 limits lateral drift at the top of the crane girder to height / 400 or 50 mm (2 in), whichever is less, measured from the column base, for each of two cases checked separately:
- the crane lateral forces in TR-13;
- building wind with a 10% annual probability of being exceeded, a 10-year return wind.
These limits may only be exceeded where it can be shown that the extra drift will not harm the building's durability or crane operation. The commentary notes they are written for moderate to high use runways in low to moderate height buildings; in a tall structure such as a galvanizing tower, the owner may agree a looser limit.
Side thrust follows stiffness
The total crane side thrust is shared between runway columns based on an overall analysis that accounts for their relative stiffness. Column bases in mill buildings are usually fixed or partly fixed, and that fixity must be used consistently in the frame model and the foundation design.
Rail gauge spread under gravity
A portal frame spreads when loaded from above. TR-13 limits the change in crane rail gauge under gravity loads, from an elastic analysis, to +25 mm and −13 mm (+1 in, −½ in) from the specified gauge. For this check only, snow up to about 1.44 kPa (30 psf) may be cut by 50%, and heavier snow by 25%. In heavy snow regions this check can decide the frame size, because a crane with too wide a gauge binds or drops off the rail.
Getting the stiffness for less steel
Stiffness can come from deeper girders, heavier frames, roof-level bracing that shares loads between frames, or a backup girder system. TR-13 leaves the choice to the engineer and the owner, weighing steel weight against fabrication and erection time. At World Steel we run these options early, in the proposal stage, and show the tonnage of each. See our crane design standards page, the crane supporting columns and the built-up crane runway girders we fabricate. At the Sunpro Steel mill, with 150 t cranes, stiffness rather than strength set many of the main members.
Solutions and the Sunpro Steel project
Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package itself. For a factory with bridge cranes, start from manufacturing plants with crane bays. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, is where these TR-13 points were applied at full scale, and our large projects page explains how we run jobs of that size.
Source and limits
This article paraphrases AIST Technical Report No. 13 (2021), Sections 5.3 and 5.8 and the commentary. The project specification and the Engineer of Record set the limits used on each job.
Quick answers
What is the vertical deflection limit for a mill crane girder?
Under AIST TR-13, span/1000 for Class A and B buildings and span/600 for Class C and D, from one crane without impact.
What drift is allowed at the crane runway?
Frame drift at the top of the crane girder is limited to height/400 or 50 mm (2 in), whichever is less, under crane lateral forces and under a 10-year wind, each checked separately.
When must a crane girder be cambered?
TR-13 calls for camber on girders longer than about 23 m (75 ft), for roughly dead load plus half the live load deflection, without impact.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors
- Solutions by stateState-by-state steel solutions