Every number in a crane runway design traces back to the crane. If the crane data is generic, guessed or late, the building is designed around the wrong machine. AIST Technical Report No. 13 (2021), Sections 1.5 and 1.6, spells out what the owner must give the designer, what the drawings must show and how clearances are proved. Use it as a checklist when you buy a crane building.
The crane data the owner must supply
TR-13 makes it the owner's job to pass the following from the crane supplier to the building designer:
- the dimensions on the clearance and wheel load diagrams (the report's Figs. 1.1 to 1.3);
- bridge static wheel loads;
- trolley weight;
- total crane weight;
- bridge and trolley speeds;
- cab clearances;
- bridge bumper forces;
- lifted load;
- location of collectors, conductor bars or festoon systems, with guarding where accessible;
- any lift below floor level;
- cab location and cab floor elevation, with escape platforms, access, stairs and ladders;
- runway rail size, to AIST Technical Report No. 6;
- the type of each crane.
Add the mill building class for each runway (see mill building class A to D), the number of cranes per aisle and whether they can work in tandem, and whether guide rollers are used.
What the design drawings must show
Section 1.5.1 lists the contents of mill building design drawings:
- complete design criteria;
- loads, including crane wheel loads and lateral loads;
- key moments, shears and reactions in girders, beams and columns, and truss forces;
- size and ASTM specification of all material;
- camber where needed;
- column base loads for foundation design: direct load, moment, shear and uplift;
- foundation assumptions: bearing pressure, pile type and capacity;
- typical details showing bolt or weld types, and which welds must meet AWS D1.1 for cyclically loaded structures.
The commentary recommends showing all crane and equipment loads on the drawings so future engineers can assess modifications. Design calculations go with the drawings. Drawings and calculations prepared by anyone other than the owner are sealed by the registered engineer of record, and project record drawings are based on a final survey of runway alignment.
Clearance testing
Before a new or relocated crane goes into service, TR-13 calls for a clearance test with no load and the hook fully up. The crane travels the full runway three times: trolley at one end of the bridge, at the other end, and at the center, checking the clearance diagram each time. For the center pass, allow for roof truss deflection under snow.
Access and maintenance
Section 1.6 asks the designer to plan for the life of the plant:
- repair platforms for crane wheel and track changes;
- escape walkways from cabs on hot-metal cranes;
- trolley hoists or lifting beams in the roof to change heavy crane parts, with their capacities on the drawings and on the structure;
- stairs rather than ladders where practical;
- about 457 mm (18 in) between column faces and the crane end truck for personnel clearance on new buildings;
- fall protection: horizontal lifelines can put large lateral loads on members, so their anchorage forces and load paths are designed into the building, to ANSI Z359 and OSHA Subpart M.
These items are hard to add once a mill is running.
One supplier for crane and structure
The biggest risk in this list is the hand-off between a crane supplier and a separate steel supplier. World Steel can supply the overhead cranes with the building, so the crane data, bumper forces and clearances are fixed by one team, and our design report and drawings carry them through to the Engineer of Record's review and approval. Shop drawings are included at no extra cost. On the Sunpro Steel mill, with cranes up to 150 t, this coordination was the backbone of the design. To start, send your drawings or read our crane design standards page.
Solutions and the Sunpro Steel project
The rules in this article come together in our crane building system: runway girders, stepped columns, bracing and, on request, the overhead cranes, supplied as one package. For whole facilities, see our solutions for heavy industrial plants and manufacturing plants with crane bays. The reference job is the Sunpro Steel mill project: about 5,000 t of steel and crane bays for cranes up to 150 t, our largest crane building to date.
Source and limits
This article paraphrases AIST Technical Report No. 13 (2021), Sections 1.5 and 1.6 and the commentary. Crane suppliers' certified data and the project specification govern each job.
Quick answers
Who provides crane data for the building design?
Under AIST TR-13 the owner is responsible for passing the crane supplier's data to the building designer: dimensions, wheel loads, weights, speeds, bumper forces, rail size and more.
How is a new crane runway clearance-tested?
With no load and the hook fully up, the crane travels the full runway three times: trolley at each end of the bridge and at the center, checking the clearance diagram each time.
What personnel clearance is needed beside the crane?
TR-13 calls for about 457 mm (18 in) between the column faces and the crane end truck on new buildings, unless another means of egress avoids that passage.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US general contractorsHow we support GCs, steel erectors and developers
- Lower cost, lower riskWhere overseas fabrication saves on large jobs
- Section 232 steel importsDuties and paperwork on imported steel
- Landed cost calculatorFreight, duty and fees to your US jobsite
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors