Every crane runway ends in a stop, and sooner or later a crane will reach it faster than intended. The bumper force from that hit travels through the girders, seats and bracing into the foundations, and it is often the largest longitudinal load in the building. AIST Technical Report No. 13 (2021), Section 3.7.3 and its commentary, sets out how to size it.
The rule in the body of the report
TR-13 keeps the main requirement short:
- The stop load is included in the design of the runway girders, their connections and the supporting frame, following a defined load path.
- The maximum design bumper force is agreed with the crane designer and shown on the structural drawings.
- That design force must not exceed the maximum allowable force on the stop.
Picking the energy absorber
The commentary gives three criteria for the bumper, hydraulic or spring:
- The bridge deceleration must not exceed about 4.9 m/s² (16 ft/s²) at 50% of the full-load rated speed, or 50% of the maximum attainable speed.
- The bumper must be able to absorb the energy of an impact at 100% of rated speed.
- The maximum force it generates must stay below the design strength of the runway stop.
Hydraulic bumpers behave non-linearly and springs linearly, so the designer must know which device is used. The force is worked out from conservation of energy: crane kinetic energy against bumper stroke.
The full-speed case is a rare event
The building, stops and connections are designed for the force at 100% of the full-load rated speed. TR-13 explains that this is not normal service but a crane malfunction or serious operator error, so it carries a load factor of 1.0 in LRFD, with a matching reduced factor in the ASD combinations (0.67 on the bumper force). The matching load combinations are covered in crane runway load combinations.
What mass goes into the calculation
For bridge bumpers, the trolley is placed at the end that gives the largest end reaction from bridge and trolley together, and that share of the crane mass is assigned to the bumper. The lifted load is generally left out, because it hangs from the hoist and its inertia does not peak together with the crane's.
Where to mount the bumpers
TR-13 suggests mounting bumpers on the runway end stops, not on the crane. Reasons:
- they can be inspected, maintained and replaced without shutting the crane down;
- any leaking hydraulic fluid collects in one place, where inspectors will see it;
- having bumpers on both the crane and the stop is not recommended.
The height of the bumper above the rail must be agreed with the crane manufacturer so the stop is placed and designed correctly. The bumper supplier should certify performance.
Choosing the bumper saves steel
The commentary makes a point owners often miss: full-speed bumper forces can be very large, and a well-chosen bumper with a longer stroke can cut the peak stop force, and with it the size of the stops, girders, seats and bracing. Choosing the bumper is a structural decision, not only a crane decision.
The load path to the ground
The force must travel somewhere. A typical path runs from the stop into the girder, through the girder cap or rocker plate into the next girder, and so on until it reaches a longitudinal vertical brace, then down to the foundation. Struts can carry it across to the braced line. Our article on mill building bracing and expansion joints covers that side. TR-13 also asks for clearance between the rail ends and the stops for thermal expansion and rail creep.
One supplier for crane and runway
Because World Steel can supply overhead cranes with the building, the bumper choice, the stop force on the drawings and the runway design can be settled together instead of through rounds of RFIs between separate suppliers. The steel is designed to AISC 360 and TR-13 guidance; the US contractor, our customer, handles site work and its Engineer of Record approves the design. See our crane design standards page and the Sunpro Steel mill, designed for cranes up to 150 t.
Solutions and the Sunpro Steel project
See how this fits a complete job: the crane building system for runways, columns and cranes, manufacturing plants with crane bays for factory layouts, and heavy industrial plants for mills and process plants. All of it was put to work on the Sunpro Steel mill project, a 5,000 t steel production plant designed for overhead cranes up to 150 t.
Source and limits
This article paraphrases AIST Technical Report No. 13 (2021), Section 3.7.3 and its commentary. Use the full report and the crane and bumper suppliers' certified data for design.
Quick answers
At what speed are crane end stops designed?
AIST TR-13 designs the building, the end stops and their connections for the force at 100% of the full-load rated speed, treated as a rare malfunction case.
Should bumpers be on the crane or on the stop?
TR-13 suggests mounting them on the runway end stops, so they can be inspected and repaired without taking the crane out of service, and not on both.
Is the lifted load included in the bumper force?
Generally no. The load hangs from the hoist, so its inertia does not peak at the same moment as the crane impact.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors
- Solutions by stateState-by-state steel solutions