Mill floor slab on grade: subgrade, joints and the steelmaking slag question

Forklifts, coil cars and stacked product load a mill floor far harder than a warehouse. AIST TR-13 gives a clear method for the slab on grade, and firm warnings about slag and rock fill. Here is what it says, and how the slab meets the steel.

· updated November 23, 2026 · 7 min read · World Steel USA engineering team

In a mill building, the slab on grade is not a simple warehouse floor. It carries coil and slab stacks, forklifts and straddle carriers, rail-mounted transfer cars and sometimes the outriggers of a mobile crane during maintenance. AIST Technical Report No. 13 (2021) treats it in Section 4.6, with a longer commentary to Section 4.6.1 on how to analyze the slab and firm rules in Sections 2.2.5 and 4.6.8 to 4.6.9 about two fill materials common on steel plant sites: steelmaking slag and resistant rock.

This article summarizes that guidance. The slab is concrete work designed and built by others, but it shares column piers, grade walls and loads with the steel structure, so the steel and concrete teams need to plan it together.

Why mill floors are different

A distribution warehouse floor is usually designed around forklift wheels and rack legs, with loads that are well known and fairly uniform. A mill floor sees a wider mix, and TR-13 makes the point in several places. Section 3.4.1 lists recommended minimum floor live loads up to about 48 kPa (1,000 psf) for motor rooms and about 24 kPa (500 psf) for casting and charging floors, and asks the owner, designer and equipment suppliers to add storage, vehicle, bucket and ladle loads where they apply. Section 3.8 adds impact factors for vehicles: 30% of the wheel load for pneumatic tires and 50% for solid rubber tires, which are common on heavy forklifts and slab carriers.

Three loads cause most mill slab problems:

  • Concentrated storage. Coils on the floor, slab stacks and bundled product put very high local pressures on the slab, often next to a column pier or a free edge.
  • Heavy, hard-tired vehicles. Solid tires carry high wheel loads on a small contact area, and the impact allowance makes them heavier still.
  • Repetition. A slab under a transfer aisle sees thousands of wheel passes a day, so fatigue enters the design, which is why TR-13 mentions fatigue explicitly for fiber reinforced sections.

On top of these, mill floors meet heat, spilled scale, oil and water, so durability carries as much weight as strength. The slab is also the surface on which the steel structure is surveyed and set out, so flatness around the column lines matters to the steel crews as well.

Reinforced, unreinforced or fiber: an economic choice

Section 4.6.1 starts by saying the choice between a reinforced and an unreinforced slab section should come from the economy and durability of each system. It then sets the design basis for each:

  • Bar or wire reinforced slabs follow ACI 318.
  • Fiber reinforced slabs follow the fiber manufacturer's requirements, including fatigue.
  • Slabs whose temperature and shrinkage steel is too light to act as tension reinforcement are designed as unreinforced. Their thickness comes from the section modulus and the concrete modulus of rupture.

For unreinforced slabs, TR-13 points to the ACI guide Design of Slabs on Ground for an equation-based method, and to the Portland Cement Association and Corps of Engineers guides for design tables. The commentary notes that the PCA tables assume the load at the center of a panel and adjust for joint efficiency and a fatigue-based safety factor, while the Corps of Engineers method assumes a joint efficiency of 0.75.

What the analysis must capture

The commentary to Section 4.6.1 lists the effects a slab analysis has to include:

  • Nearby local loads. A wheel near a column, a rack leg, a wall or a second wheel adds to the stress under the primary load.
  • Soil stiffness, slab stiffness and two-way action. TR-13 calls these the three greatest factors in how load spreads from slab to subgrade.
  • Shear transfer across control joints. The joint detail must actually deliver the load transfer the analysis assumes.
  • Free edges. A load near the free edge of a floating slab gives the worst stresses. TR-13 suggests thickening the edge, or tying the slab into a grade wall and modeling the wall's stiffness.
  • Moving loads. Load positions should be varied to find the worst case.

A finite element model of the slab on an elastic foundation handles all of this with the fewest assumptions; a beam-on-elastic-foundation calculation is an acceptable simplification. Either way, the subgrade modulus comes from the geotechnical engineer (Section 4.6.2), not from a textbook table.

Subgrade and base course

Section 4.6.3 asks the Project Geotechnical Report to set the depth and degree of compaction for new engineered fill and any special preparation of the in-situ soil. Slabs normally sit on a base course of drainage fill, whose thickness goes on the drawings and whose gradation goes in the earthwork specification.

On vapor retarders, Section 4.6.4 is cautious. A retarder under the slab can make cracking and curling worse during curing, so it should be used only when needed, and then as the geotechnical report recommends. In a mill, where moisture-sensitive finishes are rare outside control rooms and electrical rooms, it is often limited to those areas.

Joints: control, construction and isolation

Control joints (4.6.5) must be shown on the drawings, and construction joints should fall on control joint lines where possible. For slabs without temperature and shrinkage reinforcement, joint spacing follows that ACI guide and the related references TR-13 lists.

Temperature and shrinkage reinforcement (4.6.6) becomes necessary when control joints are spaced further apart than those references recommend. TR-13 recommends the subgrade drag method for sizing it when load demand does not govern, and warns that welded wire fabric needs special care to stay at the right depth in the slab.

Isolation joints (4.6.7) separate the slab from column piers, machine bases and building walls. The commentary notes that older editions called these expansion joints; the 2021 edition uses the correct term. In a crane building, isolating the slab from the column piers matters because the columns move under crane loads and the piers carry concentrated, repeated forces that should not crack the floor.

The steelmaking slag question

Steel plants produce large volumes of slag, and it is tempting to use it as fill. TR-13 is cautious for a good reason: non-granulated steelmaking slag can expand as free lime and magnesia in it hydrate, and that expansion can lift slabs and footings years after construction.

The rules appear in three places:

  • As structural backfill (2.2.5.1): not recommended. Open hearth or basic oxygen furnace slag may be used only after weathering.
  • Under foundations (4.3.1 and 4.4.1): the soils engineer must test it for expansion first.
  • Under slabs on grade (4.6.8): not recommended; if used, it must meet the weathering procedure of 2.2.5.1.

The weathering procedure is simple but slow. The slag is soaked with water, placed in controlled stockpiles no more than about 3 m (10 ft) high, and kept moist for at least six months. If it is crushed further after that, it is stockpiled and kept moist for another six months. Processed iron blast furnace slag, which is accepted as concrete and paving aggregate, does not need this treatment.

Resistant rock fill

Section 2.2.5.2 also warns against using rock that resists compaction as structural backfill, because it is hard to place properly and can lead to large settlements. It can work when it is selected, processed and compacted as Appendix A 3.8 describes, but TR-13 notes that careless use has caused serious foundation settlement. Section 4.6.9 repeats the warning for slab subgrades.

Where the slab meets the steel

The slab is the US contractor's concrete scope, but several steel decisions depend on it:

  • Column base elevation. TR-13 Section 5.9.5 asks that column bases sit above grade. The pier height and the slab level together set the base plate elevation and the column length we fabricate.
  • Isolation at the piers. The pier size must leave room for the isolation joint around the base plate and the anchor bolts.
  • Grade walls and wainscots. Where a concrete grade wall carries the lower part of the wall, the first girt line and the column sheeting details start from its top.
  • Floor loads near columns. Heavy storage beside a crane column is both a slab load and a foundation surcharge; the foundations article explains why that surcharge matters to the runway.
  • Embedded rails. Transfer car rails set in the floor are designed with the floor loads covered in our article on mill floor live loads.

World Steel designs and fabricates the steel structure: frames, crane supporting columns, runway girders, platforms and secondary steel. The slab, foundations and all site work are by the US contractor. We supply base plates, anchor bolts and templates matched to the foundation drawings, and the US Engineer of Record reviews and seals the design. Our plant is accredited under IAS AC472 and audited twice a year.

A practical checklist for the slab package

Pulling the TR-13 points together, a mill slab package should state:

  • the design loads and their positions, including wheel loads, rack legs, stacked product and any rail loads;
  • the subgrade modulus and fill specification from the geotechnical report;
  • the reinforcement system and its design basis;
  • control, construction and isolation joint layouts, with load transfer details;
  • edge thickening or grade wall ties at free edges;
  • whether any slag or rock fill is permitted, and if so the weathering and placement records required.

Solutions and the Sunpro Steel project

Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays, and see industrial floor support structures for elevated floors. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, is where these TR-13 points were applied at full scale.

Source and limits

This article paraphrases AIST Technical Report No. 13 (2021), Sections 2.2.5, 4.3.1, 4.4.1, 4.6 and 5.9.5 and the commentary to Sections 4.6.1 and 4.6.7. Slab and foundation design are by the owner's or US contractor's engineers on each project.

Quick answers

Can steelmaking slag be used under a slab on grade?

AIST TR-13 does not recommend it, because the slag can expand. If it is used, it must first be soaked and kept moist in stockpiles no higher than about 3 m (10 ft) for at least six months, and again after any further crushing.

Why does AIST TR-13 say isolation joint instead of expansion joint?

The 2021 edition corrected the term. A joint that structurally separates the slab from column piers, machine bases and walls is an isolation joint.

Does World Steel design the floor slab?

No. The slab is concrete work by the US contractor and its engineers. World Steel coordinates column base elevations, pier sizes and the steel that meets the floor.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AIST TR-13 mill building series

Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.

30 articles · 6 parts

Crane classes and loadsSections 1.4–1.5, 3.7, 3.11

Building class, dynamic crane forces, load combinations and the crane data.

Site, soil and foundationsSections 2, 3.13, 4

Soil investigation, foundations under heavy cranes and the floor slab.

Frame, roof and floorsSections 5.2–5.14

Columns, bracing, trusses, girts, equipment floors and connections.

Runway girders and railsSections 3.7.3, 5.8, 5.15

Fatigue details, stiffness, backup bracing, end stops and the rail system.

Shop, testing and serviceSections 1.6, 5.16–5.17, App. C

Weld testing, tolerances, maintenance access, inspection and upgrades.