Crane girder weld testing: which welds get UT, RT, MT or PT under AIST TR-13

A crane girder weld that would pass in an ordinary building can fail a runway. AIST TR-13 asks for cyclic acceptance criteria and 100% testing on the welds that carry the wheel loads. Here is the scope, weld by weld.

· updated November 22, 2026 · 3 min read · World Steel USA engineering team

Welds are where crane girders crack, so how they are tested matters as much as how they are designed. AIST Technical Report No. 13 (2021), Section 5.16 with its commentary, sets a clear scope: which welds use the stricter cyclic acceptance criteria, and which get 100% non-destructive testing (NDT). This article lays it out, weld by weld.

Static versus cyclic acceptance

AWS D1.1 has two sets of acceptance criteria. Ordinary building welds use the limits for statically loaded structures. Welds that see repeated stress use the stricter limits for cyclically loaded structures, because a small flaw that is harmless under one load grows into a fatigue crack under a million.

TR-13 asks that all crane runway girder welds meet AWS D1.1 for cyclically loaded structures. The commentary to Section 1.5.1 adds that the contract documents should identify which elements take the stricter criteria, so the shop and the inspector both know.

The 100% NDT list

For crane runway girders, TR-13 calls for:

Weld Method Extent
Web and flange splice welds Radiographic (RT) or ultrasonic (UT) 100%
Complete-penetration flange-to-web welds Ultrasonic (UT) 100%
Fillet flange-to-web welds Magnetic particle (MT) or liquid penetrant (PT) 100%
Other girder welds, unless specified Visual by an AWS certified welding inspector All

The design drawings should mark any other welds that need NDT or cyclic criteria.

Backup systems and tiebacks

For backup trusses and other lateral load elements, TR-13 asks the design drawings to say which welds take cyclic acceptance criteria. The commentary helps:

  • Tieback welds see repeated load and take the stricter criteria.
  • Rail clip welds to the top flange do not: the top flange is mainly in compression, so fatigue cracks there do not tend to grow.
  • Backup system welds are judged one by one on whether they see significant repeated load.

Our article on backup bracing and box girders explains those parts.

Rail welds

Crane rail welding is done to AWS D1.1 by qualified welders with qualified procedures, and as a minimum every weld is visually inspected by an AWS certified welding inspector to static criteria. Continuously welded rail joints themselves (flash or thermite) are made and tested to AWS D15.2; see crane rail joints, clips and pads.

Why this scope makes sense

The listed welds are the ones that carry wheel load through the girder: the splices that carry full flange and web stress, and the web-to-flange weld that sees every wheel pass. Testing them 100% costs little against a girder replacement and a shutdown. The weld details themselves are covered in crane girder fatigue details.

Writing it into the contract

TR-13 leaves any inspection it does not list to the contract documents, so the specification should close the gaps. A practical crane girder clause names the acceptance criteria (AWS D1.1 cyclic) for each weld group, the NDT method and extent for splices, web-to-flange welds and tiebacks, the qualification of the NDT technicians, who reviews the reports, and whether third-party or special inspection witnesses the testing at the shop. Stating this at bid stage avoids arguments, and extra cost, once the girders are already welded.

Testing at the plant before shipping

On a mill project World Steel runs the NDT in our plant in Vietnam, before the girders are painted and shipped, so a reject is fixed in the shop and not on a US jobsite:

  • UT, MT and PT by qualified technicians, recorded weld by weld against the girder mark;
  • reports, WPS and welder qualifications in the shop records package for the Engineer of Record and the special inspector;
  • remote inspector access on request, and progress you can follow in PEB Studio.

Our plant is accredited under IAS AC472 and audited twice a year, and our quality program is built around this kind of traceable record. The girders for the Sunpro Steel mill, with cranes up to 150 t, followed this route. See also the AWS D1.1 standard page and our crane design standards page.

Solutions and the Sunpro Steel project

Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package itself. For a factory with bridge cranes, start from manufacturing plants with crane bays. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, is where these TR-13 points were applied at full scale, and our large projects page explains how we run jobs of that size.

Source and limits

This article paraphrases AIST Technical Report No. 13 (2021), Sections 1.5.1 and 5.16 and the commentary. The project specification and the Engineer of Record set the inspection scope on each job.

Quick answers

Which crane girder welds need 100% testing?

Under AIST TR-13: web and flange splice welds by radiography or ultrasonics, complete-penetration flange-to-web welds by ultrasonics, and fillet flange-to-web welds by magnetic particle or liquid penetrant.

What are cyclic acceptance criteria?

The stricter AWS D1.1 acceptance limits for cyclically loaded structures. Small flaws allowed in static work are rejected, because under repeated load they grow into fatigue cracks.

Do rail clip welds need cyclic criteria?

TR-13 says no: the top flange is mainly in compression, so cracks there do not tend to grow. Tieback welds, which see repeated load, do need them.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AIST TR-13 mill building series

Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.

30 articles · 6 parts

Crane classes and loadsSections 1.4–1.5, 3.7, 3.11

Building class, dynamic crane forces, load combinations and the crane data.

Site, soil and foundationsSections 2, 3.13, 4

Soil investigation, foundations under heavy cranes and the floor slab.

Frame, roof and floorsSections 5.2–5.14

Columns, bracing, trusses, girts, equipment floors and connections.

Runway girders and railsSections 3.7.3, 5.8, 5.15

Fatigue details, stiffness, backup bracing, end stops and the rail system.

Shop, testing and serviceSections 1.6, 5.16–5.17, App. C

Weld testing, tolerances, maintenance access, inspection and upgrades.