A mill crane runs for decades, and in that time its wheels, rails, conductors and girders all need inspection and repair. That work happens 15 to 30 m above the floor, often next to a crane that is still running in the next bay. AIST Technical Report No. 13 (2021) treats access and fall protection as part of the building design, not an afterthought, in Section 1.6 and its commentary. The commentary puts it simply: safe access is hard to add once a plant is running, so it has to be planned into the first design.
This article sets out what TR-13 asks for, and how it shapes the steel.
Plan it with the owner
The commentary to Section 1.6.1 admits there are too many places in a mill needing safe access to list them all or write prescriptive rules. What it asks for instead is careful planning between the owner and the designer, both for construction and for maintenance. The owner knows how the plant will be maintained; the designer knows where the steel can carry walkways, platforms and anchors. Section 1.6.1 also asks the owner to provide enough information for mounting equipment, piping, conduit and cable trays on the structure.
What Section 1.6.1 asks for
TR-13 lists the main provisions:
- Installation and removal of equipment. Convenient installation, maintenance and removal of equipment, and no part of the structure designed so it cannot be cleaned and painted.
- Walkways, platforms, stairs and ladders for maintaining equipment in places otherwise out of reach. Stairs are preferred over ladders where practicable.
- Fall protection and fall restraint to OSHA or the local authority.
- Repair platforms for changing track and wheels on electric overhead traveling (EOT) cranes.
- Escape walkways for emergency exit from the cabs of hot metal cranes.
- Overhead trolley hoists or lifting beams in the roof at chosen locations, for changing heavy crane parts. Their capacities and the allowed loads at hoisting points go on the final design drawings and are displayed on the structure.
Each of these is a piece of steel that has to be designed, detailed and coordinated with the crane.
Repair platforms and lift beams
A crane repair bay is usually at one end of the runway, or between two buildings. There, a platform at rail level lets crews work on the end trucks, and a lifting beam or monorail above lets them lower a wheel assembly or a gearbox to the floor. TR-13 Section 5.5 recognizes that the building bracing may have to be interrupted to make room for the crane repair facilities, and asks for a special analysis of the affected frame and bracing when it is.
Practical points for the repair bay:
- size the platform for the end truck, the tools and the parts that will be set down there, as a concentrated and uniform live load;
- align the lift beam so a wheel assembly can be lowered clear of the platform and the crane;
- mark the lift beam capacity on the beam and on the drawings, as TR-13 asks;
- check the girder and column for the extra loads from the platform and lift beam.
Runway walkways and the girder top
The most common access along a heavy runway is a walkway at rail level beside the girder. TR-13 mentions this in Section 5.8.2.1: a horizontal backup system on a long girder can also serve as the walkway, and the commentary describes a horizontal plate between the girder top flange and a backup truss that "has the additional function of providing a walkway surface". Our article on backup bracing and box girders covers that system.
A girder walkway needs:
- a continuous walking surface, with toe plates and guardrails where open edges face the floor;
- a safe way up, by stairs or ladders at the ends or at intermediate columns;
- room to pass the columns, which is where the column clearance rule comes in.
The 450 mm column clearance
The commentary to Section 1.6.1 sets one specific dimension. On new buildings, there should be at least about 450 mm (18 in) between the face of the column and the extremities of the crane end truck, to give personnel clearance. TR-13's typical runway clearance diagram shows this dimension.
There is an alternative. Where another route lets people get past without walking between the column and the crane, the 450 mm can be waived, and the gap is then limited so a person cannot pass. What must not happen is a gap that is wide enough to tempt someone in but too narrow to be safe when the crane comes by. Our article on the crane data sheet covers the other clearance dimensions the crane supplier provides.
Fall protection: the loads are structural
Section 1.6.2 is about the structural side of fall protection. Horizontal lifelines (HLL) are tensioned cables that workers clip onto; when someone falls, the cable sags and its tension rises sharply, and that tension pulls sideways on the anchors. TR-13 warns that HLLs can apply relatively large lateral loads that overstress building members, and asks that those loads be included in the building design.
The commentary adds that the building designer, with the owner, must decide where fall protection systems go. Where a proprietary or third-party engineered system is used, the owner gives the designer all of its information. In every case the building designer documents or determines the anchorage loads and provides a proper load path for them.
That load path is often the hard part. An HLL anchored to two columns at the ends of a long girder pulls the columns toward each other in a fall event. A trolley system running on the girder puts its loads into the flange. These are not large in everyday terms, but they arrive at places such as column webs, stiffeners and girder flanges that were not designed for sideways pulls.
What TR-13 asks of the fall protection system
Section 1.6.2 lists criteria for the systems themselves:
- every HLL and fall protection system is designed by a qualified person and meets current criteria for height, sag and so on;
- systems carry tags showing certification date and duration, design drawings, manufacture and installation dates, hardware, allowed users per span and the annual inspection record.
It then lists items to consider when designing the building and setting the fall protection parameters:
- crane maintenance needs;
- number of users per bay;
- life of the system;
- span of the horizontal lifelines;
- location of anchors and guides;
- runway maintenance and operation, such as rail changes, runway repairs and inspections;
- roof maintenance, including monitors and HVAC equipment.
And it names the governing standards: ANSI Z359 for active fall protection, OSHA Subpart M, and the CSA Z259 series in Canada.
TR-13 also recommends a walking surface, such as a thrust plate or deck plate, as often as is feasible. A solid walking surface with a properly designed HLL makes inspection and maintenance of the runway much safer than balancing on a girder flange.
Roofs, monitors and ventilators
TR-13's list of items to consider includes the inspection and maintenance of the roof system and its components, including monitors and HVAC equipment. Mill roofs carry ventilators, fans, fume duct penetrations and skylights that all need regular service, and the roof itself needs inspection after storms and before winter. Safe roof access usually means:
- a fixed stair or caged ladder to the roof at more than one point, so crews are never far from an exit;
- walkways across the roof to each item of equipment, so nobody walks on skylights or thin roof sheeting;
- guardrails or anchor points along roof edges and around openings;
- lifeline or anchor rails along monitor ridges where work happens at height.
Each item adds loads to the roof framing, from the dead weight of walkways to the fall arrest loads at anchors, and the purlins and truss chords that carry them need to be checked. Our article on girts and purlins covers those members.
Access during construction
Section 1.6 and its commentary mention construction as well as maintenance. Steel crews need safe access to bolt girder connections and set rails, and the same walkways and anchor points used later for maintenance can serve them if they are in place early. Site work is the US contractor's scope on a World Steel project, but shop-installed anchor points, walkway brackets and guardrail sockets can make that work safer and faster.
How World Steel applies it
World Steel designs and fabricates crane runways, maintenance walkways, industrial access systems, stairs, guardrails and repair platforms for US projects, and supplies overhead cranes on request with the building. On a crane building, we:
- agree with the owner where repair bays, walkways, lift beams and escape routes go, before the frame is fixed;
- check the 450 mm column clearance against the crane supplier's end truck dimensions, or detail the alternative route;
- design anchors and members for the fall protection loads given by the owner or the system supplier, and show those loads on the drawings;
- weld clips, brackets and anchor plates in the shop, so no unplanned welding is needed on the girders later.
The US Engineer of Record reviews and seals the design. Fabrication is in our plant in Vietnam, accredited under IAS AC472 and audited twice a year. Fitting walkways, lifelines and guardrails on site is the US contractor's scope.
Solutions and the Sunpro Steel project
Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays, and see our US crane design standards page. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, is where these TR-13 points were applied at full scale.
Source and limits
This article paraphrases AIST Technical Report No. 13 (2021), Sections 1.6.1, 1.6.2, 5.5 and 5.8.2.1 and the commentary to Sections 1.6.1, 1.6.2 and 5.8.2.1. Fall protection systems are designed by a qualified person under the governing standards, and the owner and the Engineer of Record set the requirements on each project.
Quick answers
What clearance does AIST TR-13 ask between the column and the crane end truck?
On new buildings, at least about 450 mm (18 in) between the column face and the end truck, for personnel. It can be waived if another route avoids passing between column and crane, and the gap is then limited so nobody can pass.
Do horizontal lifelines affect the building design?
Yes. Horizontal lifelines can put large lateral loads into the members they anchor to. AIST TR-13 asks the designer to find those loads and give them a proper load path.
Which fall protection standards does AIST TR-13 cite?
ANSI Z359 for active fall protection systems, OSHA Subpart M, and the CSA Z259 series in Canada.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- Quality hubInspection, testing and sign-off at the plant
- IAS AC472 accreditationThe first and only AC472 plant in Vietnam
- Accredited testing labsILAC ISO/IEC 17025 testing on every project
- Online factory auditWalk the shop live with our QA team
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors