The crane rail is the part of a runway the crane actually touches, and its joints and fastenings take a beating every pass. AIST Technical Report No. 13 (2021), Section 5.15 and its commentary, gives practical guidance on choosing, joining and fastening crane rails. This article sums it up for owners and contractors.
Choosing the rail
TR-13 lists what drives rail type and size: vertical and side wheel loads, wheel diameter and material, rail length and properties, guide rollers if used, and the duty cycle. Rail size itself follows AIST Technical Report No. 6.
For Class A and B runways, the report recommends head-hardened rails, welded joints and elastomeric rail pads for maximum rail life. The commentary notes that in the US head-hardened crane rails are rolled to ASTM A759 in the CR sections, while ASCE sections are control-cooled only, and European DIN sections rely on alloyed grades for hardness. The project specification should state rail length, composition, hardness and tolerances.
Because most rail failures happen at splices, use the longest practical rail, within transport and handling limits. US crane rail sections come in lengths of roughly 12 to 24 m (39 to 78 ft).
Welded joints
Continuously welded joints remove the bump at each joint and are typically superior to bolted joints. TR-13 asks for:
- flash welding or thermite welding, performed and tested to AWS D15.2;
- joints staggered across the runway;
- finish grinding to match the rail profile, without overheating, leaving a smooth, notch-free surface;
- a slightly convex finished joint, because a concave dip invites repeated wheel impact and early weld failure.
The commentary adds that stick welding a continuous rail is not a sound practice today, and that puddle-arc welding should be kept for emergency repairs only.
Bolted joints
Where bolted joints are used, TR-13 asks for tight-fit joints with a gap of no more than about 1.6 mm (1/16 in), staggered across the runway, clean saw cuts and deburred bolt holes. Bolts are re-tightened after the first 30 and 90 days of operation, then as part of regular runway inspection.
Clips and clamps
Rails are never welded or bolted straight to the girder. They are held with clips or clamps that stop sideways movement but let the rail expand and creep along its length:
- clips go in opposing pairs, no more than about 760 mm (30 in) apart;
- where side loads approach the clip rating and cycles are frequent, close up to 460 to 610 mm (18 to 24 in);
- with elastomeric pads, the rail is locked laterally by clips approved by the pad maker, at no more than about 610 mm (24 in);
- clip type and spacing are shown on the contract documents.
Proprietary clips allow alignment adjustment, which matters a great deal during setting and later maintenance.
Hook bolts
TR-13 restricts hook bolts. They should not be used in Class A or B buildings, for cranes over 20 tons, or on runways longer than about 152 m (500 ft), because they fight the rail's thermal movement and stretch or loosen over time. Where used, they are paired 100 to 150 mm (4 to 6 in) apart at about 610 mm (24 in), drilled in the shop.
Alignment and centering
Rail alignment tolerances, set during erection by the US contractor, are tight: rail centers within about ±6 mm (±¼ in) of the drawing dimension corrected to 20 °C (68 °F), and horizontal and vertical misalignment no more than 6 mm in 15 m (¼ in in 50 ft), 10 mm (3/8 in) total. The rail must be centered on the girder web where possible, never offset more than three quarters of the web thickness. Achieving this starts with the shop tolerances explained in crane column and girder end tolerances. Guide-roller cranes may need tighter values from the crane supplier (see crane impact and side thrust).
Our part
World Steel fabricates the girders with the clip layout, rail centerline and any shop-drilled holes shown on approved shop drawings, and can supply the overhead cranes and rail package with the building. Rail setting, welding and alignment on site are the US contractor's work. See the crane design standards page and the Sunpro Steel mill.
Solutions and the Sunpro Steel project
The rules in this article come together in our crane building system: runway girders, stepped columns, bracing and, on request, the overhead cranes, supplied as one package. For whole facilities, see our solutions for heavy industrial plants and manufacturing plants with crane bays. The reference job is the Sunpro Steel mill project: about 5,000 t of steel and crane bays for cranes up to 150 t, our largest crane building to date.
Source and limits
This article paraphrases AIST Technical Report No. 13 (2021), Sections 5.15 and 5.17.6 and the commentary. Rail and clip suppliers' data and the project specification govern each job.
Quick answers
Are welded or bolted crane rail joints better?
AIST TR-13 regards continuously welded joints, made by flash or thermite welding to AWS D15.2, as typically superior because they remove the impact at each joint. Bolted joints must be tight-fit and re-tightened.
How far apart should crane rail clips be?
In opposing pairs no more than about 760 mm (30 in) apart, and 460 to 610 mm (18 to 24 in) where side loads are high and cycles frequent. With elastomeric pads the maximum drops to about 610 mm (24 in).
Can hook bolts be used?
Not in Class A or B buildings, not for cranes over 20 tons, and preferably not on runways longer than about 152 m (500 ft), because they restrain thermal movement and loosen over time.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- Projects by typeWarehouses, plants, data centers and more
- Industries we serveSteel packages by US industry
- Data center steelHyperscale and colocation framing
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors
- Solutions by stateState-by-state steel solutions