Skip to content
Seeking US contractor partners IAS AC472 ACCREDITED ★ METAL BUILDINGS ★ AC472 IAS AC472 accreditedIAS AC472
World Steel USA
Crane bay steel structure at the Sunpro Steel mill during construction

Engineering and codes

Crane side thrust, impact and traction: the dynamic loads on a mill runway

A crane runway is never loaded only by weight. Hoisting, braking, trolley moves and skewing add vertical impact, side thrust and traction. AIST TR-13 gives mill-grade values for each, by crane type.

· updated November 22, 2026 · 4 min read · World Steel USA engineering team

A crane runway sees more than the weight of the crane and its load. Each time the hoist picks up a load, the trolley brakes or the bridge accelerates, the forces on the rail jump for a moment. AIST Technical Report No. 13 (2021) handles these dynamic effects with three allowances: vertical impact, side thrust and traction. This article explains each one and how the report sizes them for mill service.

Where the forces come from

TR-13's commentary to Section 3.7.2 describes crane loads as dynamic: they depend on the mass of the crane and the lifted load, acceleration and braking rates, hoisting speed, and the stiffness and damping of the runway.

  • Vertical impact is the extra vertical wheel load from hoisting and wheel travel over the rail.
  • Side thrust (lateral force) acts across the runway at the rail head. It comes from trolley acceleration and braking, the trolley hitting its stops on the bridge, the crane skewing as it travels, and lifts where the hoist line is not vertical.
  • Traction (longitudinal force) acts along the runway when the bridge accelerates or brakes. Bumper impact at the runway ends is a separate, larger longitudinal case, covered in our article on runway end stops.

Values by crane type

The report's Table 3.2 sets percentages by type of mill crane. Vertical impact is a percentage of the maximum wheel load, side thrust a percentage of the lifted load, and traction a percentage of the maximum load on the driven wheels. Some examples:

Crane Vertical impact Total side thrust Traction
Ladle and mill cranes 25% 40% of lifted load 20%
Magnet cranes, finished product 25% 40% 20%
Magnet cranes, slab, billet and scrap 25% 100% 20%
Clamshell bucket, soaking pit, stripping 25% 100% 20%
Motor room maintenance cranes 20% 30% 20%
Stacker cranes 25% 200% 20%

The full table in TR-13 has a few more rows; use the report for design.

The side thrust floor

Table 3.2 is not the only test. TR-13 sets the total side thrust as the greatest of three values:

  1. the Table 3.2 value for that crane;
  2. 20% of the lifted load plus the trolley weight (40% of lifted load, trolley and rigid arm for stacker cranes);
  3. 10% of the lifted load plus the total crane weight (15% for stacker cranes).

The side thrust is then shared between the two runways in proportion to their lateral stiffness, not simply split 50/50. In a multi-aisle building, a stiff column tower on one side of an aisle will attract more of the thrust than a long-span girder on the other.

Why some cranes get so much more

The commentary explains the high values. Magnet, clamshell, soaking pit and stripping cranes handle scrap, ingots and slabs in operations that are less controlled, where inclined lift lines and skewing are more likely. When a magnet crane handles finished product with a lift beam in a controlled way, the lower 40% value applies. The very high stacker crane values are deliberate, written in after field problems on those runways.

Pendant, radio and automatic cranes

For pendant-operated cranes, TR-13 uses lighter values: 10% of the maximum wheel load for impact, 10% of the lifted load plus crane weight for side thrust, and 20% of the driven wheel load for traction. Radio-controlled and fully autonomous cranes are treated like cab-operated cranes, because they can travel and brake as hard.

Guide rollers change everything

The percentages assume the usual double-flanged wheels. Some cranes, more common in Europe, steer with horizontal guide rollers on one side of the bridge, with flat wheels. Then the whole lateral force goes into one rail, its clips and its girder. TR-13 asks the crane supplier to state whether guide rollers are used, on which side, the rail and fastening to use, any tighter alignment tolerance and any higher lateral force. Our article on crane rails, joints and clips covers the rail side.

What the runway designer needs from the crane supplier

To apply these rules the designer needs the lifted load, trolley and total crane weights, wheel loads and spacing, the crane type and how it is controlled, and whether guide rollers are fitted. Since World Steel can supply the overhead cranes with the building, crane data and runway design can come from one desk, which removes a common source of wrong assumptions. Our crane design standards page shows how these TR-13 values sit next to CMAA and ASCE 7.

On the Sunpro Steel mill, with cranes up to 150 t, these lateral and longitudinal forces governed much of the crane girder top flange, the column brackets and the longitudinal bracing.

Solutions and the Sunpro Steel project

Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package itself. For a factory with bridge cranes, start from manufacturing plants with crane bays. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, is where these TR-13 points were applied at full scale, and our large projects page explains how we run jobs of that size.

Source and limits

This article paraphrases AIST Technical Report No. 13 (2021), Section 3.7.2, Table 3.2 and the commentary. TR-13 is guidance, not a mandatory specification; the project specification and the Engineer of Record set the values used on each job.

Quick answers

What is crane side thrust?

The horizontal force across the runway, at the top of the rail, caused by trolley acceleration and braking, trolley stop impact, crane skewing and lifts where the hoist line is not vertical.

Why does AIST TR-13 give higher values than the building code?

Mill cranes work harder and more roughly than ordinary factory cranes. TR-13 sets deliberately conservative values for reliability and durability, and allows engineering judgment only when an existing runway is assessed.

Are vertical impact and side thrust added together?

No. The 2021 edition stopped combining them, because they come from different crane actions (hoisting versus travel) and their peaks are very unlikely to happen at the same moment.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AIST TR-13 mill building series

Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.

30 articles · 6 parts

Crane classes and loadsSections 1.4–1.5, 3.7, 3.11

Building class, dynamic crane forces, load combinations and the crane data.

Site, soil and foundationsSections 2, 3.13, 4

Soil investigation, foundations under heavy cranes and the floor slab.

Frame, roof and floorsSections 5.2–5.14

Columns, bracing, trusses, girts, equipment floors and connections.

Runway girders and railsSections 3.7.3, 5.8, 5.15

Fatigue details, stiffness, backup bracing, end stops and the rail system.

Shop, testing and serviceSections 1.6, 5.16–5.17, App. C

Weld testing, tolerances, maintenance access, inspection and upgrades.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.