Moving loads in mill buildings: rail cars, ladle cars, forklifts and tracked vehicles

Locomotives, ladle cars, slab carriers and tracked loaders all run inside a mill. AIST TR-13 Section 3.8 sorts them into two groups and gives the impact factors for each. Here is how those rules shape floors, platforms and the steel that carries them.

· updated November 23, 2026 · 7 min read · World Steel USA engineering team

A steel plant moves heavy things all day, and not only with overhead cranes. Locomotives bring in scrap and take out product, ladle and tundish cars shuttle between the furnace and the caster, slab carriers and heavy forklifts run along the aisles, and tracked loaders work in the scrap bay. Each of these puts large, moving, impact-amplified loads into floors, platforms, trench covers and the steel that frames them. AIST Technical Report No. 13 (2021) deals with them in Section 3.8, Moving Loads, with short commentary that is worth reading alongside it.

This article explains the two groups TR-13 uses, the impact factors for each, and what they mean for the structure. Crane runway loads, which TR-13 treats separately in Section 3.7, are covered in our article on crane side thrust, impact and traction.

Two kinds of moving load

TR-13 sorts moving loads into two groups:

  • Limited-access vehicles run on tracks: locomotives, railroad cars and machinery operated on rails, such as ladle cars, coil cars and transfer cars.
  • Unlimited-access vehicles are everything not tied to rails: rubber-tired trucks and forklifts, straddle carriers and tracked machines.

The difference matters because rail vehicles follow a known path with known wheel spacing, while free vehicles can reach any point the floor allows, so the designer must find the critical position for every member.

Standard railway equipment

Section 3.8.1.1 is short: unless otherwise specified, floors that carry railroad tracks are designed to the Manual for Railway Engineering published by AREMA, the American Railway Engineering and Maintenance-of-Way Association. That manual sets the design train, impact and longitudinal forces used for railway bridges and structures, so a floor or trench cover carrying standard gauge track is designed much like a short railway bridge.

In practice this applies where a rail spur runs into a scrap bay or a shipping bay. The structural elements that carry the track, such as pit covers, trench crossings and any elevated track support, must be checked for the AREMA loading, and their connections and bearings detailed for the braking and traction forces.

Non-standard rail-mounted equipment

Section 3.8.1.2 covers the rail equipment that is not standard railway rolling stock but is common in mills: ladle cars, tundish cars, coil and slab transfer cars and other floor-operated machines on rails. For these, TR-13 asks:

  • the owner to designate the maximum wheel loads, impact and lateral forces;
  • a vertical impact of not less than 25%;
  • the height above the rail at which lateral traction forces are applied.

The commentary adds that the building designer must get the loading and design criteria from the process engineer and the equipment provider, and that the loads must include both vertical and lateral components. A ladle car carrying a full ladle of liquid steel is one of the heaviest wheel loads in the plant, and its rails often run on a steel or concrete structure over a pit or across a platform.

The height of the lateral force matters because a traction or braking force applied well above the rail creates an overturning moment on the rail support. On a steel girder carrying a transfer car rail, that moment must be resisted by the girder in torsion or by bracing, much as crane side thrust is.

Rubber-tired and tracked vehicles

Section 3.8.2 covers unlimited-access vehicles with solid rubber tires, pneumatic tires or tracks. TR-13 asks that the vehicles be placed in the critical position for each member, and that the loading arrangement be the one that gives the worst single wheel or wheel combination for the member being checked. Wheel loads and spacing come from the owner, or from the AASHTO Standard Specification for Highway Bridges, or both.

On top of the static wheel loads, TR-13 adds these impact allowances:

Vehicle Impact added to the static load
Pneumatic-tired vehicles 30% of the wheel load
Solid-rubber-tired vehicles 50% of the wheel load
Tracked vehicles with air hammer attachments 25% of the track load
Tracked vehicles used for lifting, scraping or digging 100% of the track load

For solid-tired vehicles, the tire contact length and width and the load spread come from the owner or AASHTO, and a longitudinal force is applied as AASHTO or the owner requires. For tracked vehicles, TR-13 asks the owner to give load data, show where the machines will work and describe how they will be operated.

The 100% figure for digging and lifting machines reflects how hard those machines can hit the floor when they drop a bucket or swing a load. The 50% figure for solid tires reflects the stiffness of the tire: with almost no cushioning, every joint, bump or scrap piece on the floor becomes a hammer blow.

Where these loads meet the steel

Most moving loads run on slabs on grade, which our mill floor slab article covers. But many reach the steel structure directly:

  • Elevated operating floors where forklifts or carts deliver refractory, spares or product, often at 24 kPa (500 psf) uniform load plus the vehicle wheels.
  • Trench and pit covers in steel plate or grating, where a forklift or ladle car crosses a cable trench or a scale pit.
  • Transfer car runways on steel girders, where the car runs over a pit, a lower floor or a basement.
  • Loading platforms and dock levelers at shipping bays, covered on our loading platforms page.
  • Bridges between buildings that carry vehicles across a road or a rail line.

For each, the design checks include bending and shear in the girders for the worst wheel position, local bearing and web crippling under concentrated wheels, plate and grating capacity under a single tire, fatigue where traffic is frequent, and connection forces for braking and traction. Retaining walls and grade walls next to vehicle routes also see surcharge from the traffic, which TR-13 Section 3.12.2 asks the designer to include.

Braking, traction and the longitudinal path

Vertical wheel loads get most of the attention, but moving vehicles also push along their path. A ladle car stopping at the caster, a slab carrier braking at the end of an aisle or a locomotive starting a cut of cars all put longitudinal forces into whatever carries them. TR-13 asks for a longitudinal force from AASHTO or the owner for tired vehicles, and AREMA covers braking and traction for standard rail.

On a steel structure, that force has to travel somewhere. For a transfer car girder, it goes through the rail clips into the girder, then through the girder bearings into a braced bay or a fixed support, and finally into the foundations. If the girder has sliding bearings at both ends, nothing resists it. The same thinking applies to an elevated deck carrying forklifts: the deck must be braced or tied to a stiff element so the braking force does not sway the platform. TR-13 Section 5.5 sets out the same principle for crane traction and bumper forces in the building's longitudinal bracing, and the logic carries over directly.

Fatigue under traffic

Impact factors handle the peak load. Repetition is a separate issue. A transfer car crossing a girder twenty times an hour, every hour, every day, puts several million cycles on that girder over the plant's life. TR-13 Section 5.7 asks that members, connections and welds subject to repeated loads be designed for fatigue to AISC 360, for the calculated number of cycles, and the building class idea in Section 1.4 (see building class and crane cycles) works just as well for a car runway as for a crane runway.

That means the same detailing discipline used on crane girders applies: continuous welds, no unplanned attachments, careful stiffener details and splices placed away from high-stress regions. Our article on crane girder fatigue details covers those details.

Getting the data early

Moving loads are a classic case of data arriving late. The building designer often starts with a guess at the forklift size, and the actual slab carrier or ladle car is chosen months later. Some practical steps help:

  • list every vehicle that will use each floor, with its maximum axle and wheel loads, in the basis of design;
  • for rail equipment, get wheel loads, wheel spacing, rail size, impact and the height of lateral forces from the equipment supplier, as TR-13 asks;
  • show the vehicle loads and their allowed routes on the drawings, and post load limits on platforms;
  • design trench and pit covers for the heaviest vehicle that could cross them, not the one that usually does.

How World Steel applies it

World Steel designs and fabricates the steel structure for US projects: frames, crane runways, platforms, girders and secondary steel. On a mill or heavy plant, the moving loads in this article feed our design of industrial floor support structures, transfer car girders and pit covers, and of welded plate girders for the heaviest spans. We list each vehicle load on the drawings and check fatigue where traffic is frequent.

Our designs follow AISC 360, ASCE 7 and the owner's equipment data, and the US Engineer of Record reviews and seals them. Fabrication is in our plant in Vietnam, accredited under IAS AC472 and audited twice a year. Site work, including setting the girders and rails, is the US contractor's scope.

Solutions and the Sunpro Steel project

Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays, and see our US crane design standards page. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, is where these TR-13 points were applied at full scale.

Source and limits

This article paraphrases AIST Technical Report No. 13 (2021), Sections 3.8, 3.12.2 and 5.7 and the commentary to Sections 3.8.1.1 and 3.8.1.2. Vehicle loads and impact factors are set by the owner, the equipment suppliers and the Engineer of Record on each project.

Quick answers

What impact factor does AIST TR-13 use for forklifts?

30% of the wheel load for pneumatic tires and 50% for solid rubber tires. Tracked vehicles take 25% with air hammer attachments and 100% when used for lifting, scraping or digging.

How are ladle cars and transfer cars treated?

As non-standard rail-mounted equipment. The owner gives the wheel loads, impact and lateral forces, with vertical impact not less than 25%, and the height at which lateral traction acts.

Which standard covers floors under standard railway track?

AIST TR-13 refers floors carrying railroad track to the AREMA Manual for Railway Engineering, unless the project specifies otherwise.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AIST TR-13 mill building series

Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.

30 articles · 6 parts

Crane classes and loadsSections 1.4–1.5, 3.7, 3.11

Building class, dynamic crane forces, load combinations and the crane data.

Site, soil and foundationsSections 2, 3.13, 4

Soil investigation, foundations under heavy cranes and the floor slab.

Frame, roof and floorsSections 5.2–5.14

Columns, bracing, trusses, girts, equipment floors and connections.

Runway girders and railsSections 3.7.3, 5.8, 5.15

Fatigue details, stiffness, backup bracing, end stops and the rail system.

Shop, testing and serviceSections 1.6, 5.16–5.17, App. C

Weld testing, tolerances, maintenance access, inspection and upgrades.