Engineering and codes

Mill building geotechnical investigation: borings, depths and the report

Heavy cranes put large, repeated loads into the ground, and a few millimetres of settlement can throw a runway out of line. AIST TR-13 gives a full guide to the site investigation. Here is what it asks for, and what the steel designer needs from it.

· updated November 23, 2026 · 7 min read · World Steel USA engineering team

A crane runway is only as straight as the ground under it. A column that settles 20 mm more than its neighbor tilts the girder, opens the rail gauge and makes the crane crab along the runway. That is why AIST Technical Report No. 13 (2021), the guide for the design and construction of mill buildings, opens its technical content with soil, not steel. Section 2.0, Appendix A (the Geotechnical Investigation and Foundation manual) and Appendix B (a model specification for borings) together form a complete brief for the site investigation.

This article walks through that brief: what the investigation should establish, how borings are laid out and how deep they go, which field tests matter, and what the Project Geotechnical Report should contain. It closes with the part that matters to the steel package, because the structure we design and fabricate rests on the numbers in that report.

What the investigation has to answer

TR-13 Section 2.1 lists nine things the surface and subsurface exploration should determine once a site has been judged feasible:

  • foundation design criteria, based on the load magnitudes the foundation designer provides;
  • earthwork design criteria;
  • lateral soil pressures for walls;
  • subgrade properties for floor slabs on grade;
  • recommendations for special or complex soil problems;
  • the water table, including its seasonal swing;
  • the electrical and chemical properties of the soil, for the durability of anything buried;
  • the site class for seismic design;
  • environmental issues for disposing of excavated material.

Two of these are easy to miss on an ordinary building. Soil chemistry matters in a steel plant because buried concrete and steel piles can sit in aggressive ground or near stray electrical currents. The seismic site class matters because it drives the design spectrum in ASCE 7, which in turn sizes the bracing and the crane columns.

TR-13 asks that a geotechnical engineer plan and coordinate the work, following Appendix A, and that the results go into one document: the Project Geotechnical Report. Where the owner already holds reliable data that meets Appendix A, only the missing parts need to be done.

Three stages of exploration

Appendix A describes the investigation in three stages, each narrowing the picture.

Preliminary exploration (A 1.1). A desk study before any drilling: geological maps and survey publications, aerial photographs (available at 1:20,000 and 1:40,000 for most of the United States), records from earlier work on or near the site, and a walk-over to read surface features. Aerial photos are useful on unfamiliar sites, but TR-13 warns that reading them takes real experience.

General exploration (A 1.2). Geophysical surveys can cover a large area quickly. Seismic refraction measures how fast waves travel through the strata; resistivity and potential-drop methods read differences in electrical conductivity. TR-13 is clear about the limit: these methods find the boundaries between layers, but they do not identify the soil. Test borings and test pits do that.

Detailed investigation (A 1.3). Once the geotechnical engineer has the general picture, the detailed investigation measures the properties the foundation design needs: density, moisture, gradation, permeability, compressibility and shear strength. Where bedrock is reached, cores give the rock quality designation (RQD), classification and compressive strength. A preconstruction survey of neighboring structures is also recommended, so any later movement can be measured against a known starting point.

Laying out the borings

Appendix A gives practical rules for boring layout, which it calls a guide rather than a rule book. Converted to metric first:

Site or structure Suggested boring layout
Large site, uniform ground About 150 m (500 ft) spacing, closed up where conditions vary
New site of large extent Preliminary borings spaced so each group of four encloses about 10% of the area
Soft, compressible strata 30 to 60 m (100 to 200 ft) at likely building locations
Large building, closely spaced footings About 30 m (100 ft) each way, plus pits and exterior walls
Large low-load warehouse At least four borings, plus interior ones to define the profile
Isolated rigid foundation, 230 to 930 m² (2,500 to 10,000 sq ft) At least three around the perimeter
Isolated rigid foundation under 230 m² (2,500 sq ft) At least two, at opposite corners

A mill building with heavy crane columns at 12 to 15 m bays usually falls in the "closely spaced footings" row. Machinery pits, scale pits and deep process foundations get their own borings. Inclined borings are used where a surface obstruction blocks a vertical hole or where buried channels, cavities or faults need to be found. On karst ground, close-spaced rotary or wash borings without sampling may be needed to map cavities in limestone.

How deep to drill

TR-13 Table A1.1 ties boring depth to the structure. For both large buildings with closely spaced footings and isolated rigid foundations, borings should reach the depth where the foundation adds less than 10% of the average applied pressure, and generally at least 9 m (30 ft) below the lowest foundation, unless rock comes first.

The general rules in A 1.2.5.4.1 add common sense:

  • go through every unsuitable layer: loose fill, peat, organic soil, loose sand and potentially expansive fill such as steelmaking slag;
  • in thick, compressible clay, go deep enough that consolidation below will not move the surface noticeably;
  • where a stiff layer appears near the surface, take several borings deeper to prove nothing weaker lies underneath;
  • where rock character matters, penetrate 3 m (10 ft) into rock, with at least one boring 12 m (40 ft) in, and in limestone go through any strata suspected of solution channels.

The depth plan should stay flexible. TR-13 expects it to be adjusted as each boring comes out of the ground.

Field tests and monitoring

Laboratory results depend heavily on how much a sample was disturbed in the drilling, handling and testing. Section A 1.3.1 therefore lists field tests that measure properties in place: cone penetration, vane shear, field load tests, pressuremeter tests and permeability tests.

It also recommends monitoring during construction: vertical and horizontal ground movement, groundwater levels and pore pressures, and vibration during pile driving or blasting. On a brownfield mill expansion next to a running plant, this monitoring protects the existing crane runways as much as the new ones.

What the owner gives the geotechnical engineer

Appendix A 2.1 lists the minimum data the owner should put in the request for a proposal. For a mill building, the items that most affect the quality of the result are:

  • a description of the proposed facilities with column spacing, structure types and sizes;
  • equipment and foundation loads, including vibratory and cyclic loads;
  • deep pits and excavations;
  • estimates of tolerable total and differential settlement, naming settlement-sensitive structures and equipment;
  • the site history, such as old slag dumps, bulk storage or disposal areas;
  • any earlier borings, load tests and settlement records nearby.

This is where the steel design and the soil investigation first meet. The column reactions, the crane wheel loads and the runway's tolerance for differential settlement are structural information, and they must reach the geotechnical engineer early.

What the Project Geotechnical Report should contain

Appendix A 2.3 lists fourteen groups of recommendations. Those that a crane building depends on most are:

  • an evaluation of foundation alternatives with a specific recommendation for each facility;
  • for spread footings and mats: allowable bearing and toe pressures, foundation sizes and depths, estimated settlement and its rate;
  • for deep foundations: type, size, depth, estimated capacity, and load test requirements;
  • lateral and hydrostatic pressures for pits and retaining walls;
  • groundwater fluctuation, uplift parameters and dewatering effects on neighbors;
  • recommendations for vibratory foundations, and the effect of vibration on existing facilities;
  • protection against aggressive soil chemistry;
  • earthwork and compaction specifications.

Appendix B adds a model specification for the boring contract: locations and survey, number and depth, sequence, logs delivered within days of finishing, protection of utilities and property, and safe drilling practice. It is a useful starting point for the owner's own specification.

Why it matters to the steel

The Sunpro Steel mill is a good example of why the soil and the steel cannot be designed in isolation. With cranes up to 150 t, the crane columns deliver large, repeated vertical loads and moments into the foundations, and the runway tolerances in TR-13 Section 5.17 are measured in millimetres. The commentary to Section 3.13 says it directly: deep foundations are often needed under heavy cranes, and differential settlement can compromise rail alignment and crane function.

On a US mill project, World Steel designs and fabricates the steel structure; the foundations, the soil investigation and all site work belong to the US contractor and the owner's engineers. Our part of the interface is to:

  • give the foundation designer column reactions by load case, including crane, seismic and wind, as soon as the frame is sized;
  • state the base condition we assumed, fixed or pinned, because TR-13 Section 5.3 notes that mill column bases are usually fixed or partly fixed and that fixity depends on the anchorage and the soil;
  • supply anchor bolts, templates and base plates detailed to the foundation drawings;
  • flag the differential settlement the runway can tolerate, so the foundation design can be checked against it.

Our design work follows AISC 360 and ASCE 7, and the US Engineer of Record reviews and seals the design for the project. Our plant is accredited under IAS AC472 and audited twice a year, so the shop side of the column base, from plate flatness to anchor hole layout, is controlled and recorded. For seismic sites, the site class from the report feeds directly into the seismic design category and the bracing we design.

Solutions and the Sunpro Steel project

Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays, and see our US crane design standards page for the code background. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, is where these TR-13 points were applied at full scale. The next article in this series covers foundations under heavy cranes.

Source and limits

This article paraphrases AIST Technical Report No. 13 (2021), Section 2.1, Appendix A (Sections A 1.1 to A 2.3) and Appendix B. It is a guide, not a substitute for a geotechnical engineer's investigation and report. The owner, the geotechnical engineer and the Engineer of Record set the scope on each project.

Quick answers

How far apart should borings be on a mill site?

AIST TR-13 Appendix A gives examples: about 150 m (500 ft) on large, uniform sites, 30 to 60 m (100 to 200 ft) on soft ground, and about 30 m (100 ft) each way under large buildings with closely spaced footings. The geotechnical engineer sets the final layout.

How deep should borings go?

To a depth where the added stress from the foundation falls below 10% of the applied pressure, and generally at least 9 m (30 ft) below the lowest foundation unless rock is found first. Where rock matters, borings go 3 m (10 ft) into it, with one boring 12 m (40 ft) in.

Does World Steel do the soil investigation?

No. The owner and the US contractor engage the geotechnical engineer. World Steel designs and fabricates the steel, and gives the foundation designer the column reactions and base details the report must be checked against.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AIST TR-13 mill building series

Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.

30 articles · 6 parts

Crane classes and loadsSections 1.4–1.5, 3.7, 3.11

Building class, dynamic crane forces, load combinations and the crane data.

Site, soil and foundationsSections 2, 3.13, 4

Soil investigation, foundations under heavy cranes and the floor slab.

Frame, roof and floorsSections 5.2–5.14

Columns, bracing, trusses, girts, equipment floors and connections.

Runway girders and railsSections 3.7.3, 5.8, 5.15

Fatigue details, stiffness, backup bracing, end stops and the rail system.

Shop, testing and serviceSections 1.6, 5.16–5.17, App. C

Weld testing, tolerances, maintenance access, inspection and upgrades.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.