A steel plant is full of machines that shake: draft fans on the fume system, screens and feeders in the raw material handling, crushers in the scrap and slag yards, compressors, and the mold oscillator under every continuous caster. Each puts a repeating force into the structure that carries it. If the structure is designed only for the machine's weight, it may vibrate badly, crack at its welds or loosen its bolts within months. AIST Technical Report No. 13 (2021) addresses this in Section 3.10.1, Guidelines for Vibratory Loading, and in Section 3.10.2 on conveyors, with related points in Section 5.10 on floor framing and Section 5.13 on connections.
This article explains the approach TR-13 asks for, why resonance is the central issue, and how the steel is detailed to survive millions of cycles.
What TR-13 asks
Section 3.10.1 asks that structures supporting rotating and vibrating equipment be designed with due consideration of:
- the dynamic loads the equipment produces;
- the operating frequency of the equipment;
- the natural frequencies of the supporting structure;
- the potential for dynamic magnification and resonant response.
It asks the equipment supplier to provide the static and dynamic loads and any performance criteria for the equipment. And it asks the designer to consider fatigue from the vibration and the comfort of people working on or near the structure, pointing to AISC Design Guide 11 on floor vibrations.
TR-13 then lists the kinds of equipment that need this treatment, "including but not limited to":
- motors and similar balanced rotating equipment;
- vibrating screen supports;
- pan feeder supports;
- vibratory conveyors;
- gyratory and jaw crushers;
- forced and induced draft fans;
- mold oscillators;
- reciprocating compressors.
Why resonance is the main risk
Every structure has natural frequencies at which it prefers to vibrate. A machine applies a force at its operating frequency, for example a fan running at 1,180 rpm applies an unbalance force about 19.7 times a second. If a natural frequency of the support is close to that, even a small unbalance force is amplified many times. Far from it, the response is small.
The usual design target is therefore frequency separation: keep the important natural frequencies of the support well away from the operating frequency and its main multiples. There are two ways to do it:
- Stiff (over-tuned) support. The structure's natural frequency is well above the operating frequency. This suits slow machines, such as crushers and reciprocating compressors, and is the natural result of heavy steel framing.
- Flexible (under-tuned) support. The structure's natural frequency is well below the operating frequency, often with spring or rubber isolators under the machine. This suits fast machines such as fans, and the startup and shutdown pass through resonance briefly.
Which separation margin to use, and whether isolators are used, is agreed with the equipment supplier. TR-13 does not set a single number; it asks the designer to address the magnification and resonance potential for each case.
The data to get from the supplier
Dynamic design is impossible without good data. The items to request early are:
- the machine weight and the weight of its rotating or moving parts;
- the operating speed or speeds, including variable speed ranges;
- the dynamic force amplitudes, or the unbalance grade and the method to calculate them;
- the direction of the dynamic forces, such as vertical for a screen or horizontal for a crusher;
- startup, shutdown and fault loads, such as a fan blade loss or a motor short circuit torque;
- allowable vibration at the machine feet and any isolator data.
Section 5.10 of TR-13 makes the same point for any equipment floor: loads, load cases and operating frequencies come from the equipment supplier, and so do serviceability limits such as allowable deflection and drift. Our article on equipment floor framing covers those serviceability limits.
Conveyors: belt tension as a structural load
Section 3.10.2 adds a specific rule: conveyor support structures are designed for belt tension forces at the locations the conveyor supplier gives, in addition to dead and live loads. On a long belt conveyor, the take-up, drive and head pulleys carry large horizontal forces from belt tension, and the gallery or trestle at those points must carry them to the ground. Vibratory conveyors, which move material by shaking a pan, fall under the dynamic rules above as well.
Mining and raw material handling plants are full of these structures. Our mining steel structures solution covers conveyor galleries, transfer towers and screen houses where the same principles apply.
Fatigue: the slow failure
Vibration is a fatigue load. A screen running at 15 Hz for 8,000 hours a year applies over 400 million cycles annually. Even small stress ranges, repeated that often, crack poor details. TR-13 Section 5.7 asks that members, connections and welds under repeated loads be designed for fatigue to AISC 360, and Section 3.10.1 names fatigue specifically for vibratory loads.
In practice this means:
- choosing details with good fatigue categories: continuous fillet or groove welds, no intermittent welds, no abrupt changes of section;
- keeping attachments, such as cleats for cables or handrails, away from high-stress areas of the support beams;
- designing for the stress range, not just the peak stress.
Bolts that stay tight
Section 5.13 of TR-13 asks that bolted connections on members under fatigue cyclic loading or vibration be slip-critical connections with pretensioned high-strength bolts, to the RCSC specification. A snug-tight or bearing bolt under vibration works loose, the joint starts to slip and hammer, and the bolt eventually fails. A slip-critical joint holds the plies together by friction, so no slip occurs at service load. Our structural bolts page and the RCSC standard page explain the bolt types and pretension methods.
People on vibrating platforms
TR-13 asks the designer to consider human comfort as well as structural safety. Operators and maintenance staff spend hours on platforms near fans and screens, and perceptible vibration is tiring and worrying even when it is structurally harmless. AISC Design Guide 11 gives acceptance criteria for floor vibration due to human activity, and the same principles help judge machine-induced vibration on walkways and operating floors.
Detailing the support steel
Putting it together, a well-designed vibrating equipment support usually has:
- a stiff, direct load path from the machine feet to the columns, with no long cantilevers or eccentric hangers;
- deep, closely braced beams under the machine, often with a dedicated sub-frame separate from the surrounding floor;
- separation from adjacent floors and walkways where practical, so vibration does not spread;
- continuous welds and slip-critical bolts throughout;
- base plates and anchor rods designed for the dynamic forces, with grout placed properly.
An example: a draft fan on a steel platform
Consider an induced draft fan for a melt shop fume system, set on a steel platform beside the baghouse. The fan and motor run at a fixed speed, and the supplier gives the rotor weight, the balance grade and the operating speed. A typical design sequence is:
- build a model of the platform with the fan, motor and base frame as masses at their real positions;
- find the natural frequencies and mode shapes, paying most attention to modes that move the fan bearings vertically and horizontally;
- compare them with the running speed and twice the running speed, and stiffen the framing until there is a comfortable margin, or choose isolators that move the system well below the running speed;
- apply the unbalance force at the running speed and check the vibration amplitude at the bearings against the supplier's limit;
- check the members and welds for fatigue under the resulting stress range, and the anchor rods and base plates for the dynamic forces.
The answer is often a heavier and more directly braced platform than the static loads alone would need. That extra steel is cheap compared with a fan that has to be shut down for vibration problems.
When the problem appears after startup
Vibration problems usually show up in the first weeks of operation. The warning signs are familiar to plant engineers: handrails buzzing, grating rattling, bolts loosening, paint cracking at weld toes, and operators avoiding a platform. The first step is to measure: frequency and amplitude at the machine and at several points on the structure. If the problem is resonance, the fix is to change the structure's frequency, by adding bracing or stiffeners, or to change the machine's, by changing its speed or adding isolation. Simply adding mass rarely solves it and can make it worse.
Design records make this diagnosis much faster. A design report that states the natural frequencies calculated for each support lets the plant engineer compare the measured frequency with the predicted one immediately, rather than starting from scratch.
How World Steel applies it
World Steel designs and fabricates machinery support frames, mechanical equipment support steel and equipment platforms for US projects. On a mill or plant with vibrating equipment, our engineers:
- collect the dynamic data from the equipment supplier through the US contractor;
- model the support with the machine mass and check natural frequencies against operating speeds;
- check fatigue and specify slip-critical connections where TR-13 Section 5.13 asks for them;
- record the frequency results and assumptions in the design report for the Engineer of Record.
The US Engineer of Record reviews and seals the design. Fabrication is in our plant in Vietnam, accredited under IAS AC472 and audited twice a year, and welds on fatigue-rated supports are inspected to the project's requirements before shipping. Setting and grouting the machines and supports on site is the US contractor's scope.
Solutions and the Sunpro Steel project
Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays. The Sunpro Steel mill project, about 5,000 t with 150 t cranes and a continuous caster area, shows the scale at which these TR-13 points apply.
Source and limits
This article paraphrases AIST Technical Report No. 13 (2021), Sections 3.10.1, 3.10.2, 5.7, 5.10 and 5.13. The frequency example is illustrative. Dynamic loads and acceptance criteria come from the equipment supplier and the Engineer of Record on each project.
Quick answers
Which equipment does AIST TR-13 list for dynamic design?
Motors and balanced rotating machines, vibrating screens, pan feeders, vibratory conveyors, gyratory and jaw crushers, forced and induced draft fans, mold oscillators and reciprocating compressors, among others.
What is the main check for a vibrating equipment support?
That the natural frequencies of the support stay well away from the operating frequency of the machine, so it does not resonate. Dynamic loads, fatigue and human comfort are checked as well.
Who provides the dynamic loads?
The equipment supplier. AIST TR-13 asks for the static and dynamic loads and any performance criteria, such as allowable vibration, to come from the supplier.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors