Mill floor live loads: AIST TR-13 Table 3.1 for platforms and operating floors

A casting floor, a motor room and a walkway in the same mill can differ twentyfold in design load. AIST TR-13 Table 3.1 gives the starting values. Here they are in metric first, with the rules for reduction, roofs and drawings.

· updated November 23, 2026 · 7 min read · World Steel USA engineering team

Every mill building has elevated floors: casting floors beside the furnace, motor rooms under the mill stands, pulpits, operating platforms, repair decks and kilometres of walkways. Getting their live loads right is basic, but it is also where many arguments start, because the building code values for offices and warehouses do not describe a steel plant. AIST Technical Report No. 13 (2021) fills that gap in Section 3.4 and Table 3.1, with commentary that explains how to use the numbers.

This article sets out Table 3.1 in metric first, explains the rules around it, and covers the roof live load and what the drawings must show. The companion article on moving loads covers rail cars, forklifts and tracked vehicles.

What TR-13 asks of floor live loads

Section 3.4 sets three rules:

  • uniform and concentrated live loads for floors and platforms are listed in the project specification for each category of use, based on the maximum expected process demand;
  • movable uniform and concentrated loads are positioned to produce the worst design effect;
  • occupancy live loads tied only to people may be reduced as the local building code allows.

The commentary to Section 3.4 adds the key limit: reduction is allowed only for live loads of about 4.8 kPa (100 psf) or less that are mainly from human occupancy, consistent with the International Building Code and ASCE 7. Heavier loads from storage, equipment or processes are not reduced. In a mill that means most operating floors are designed for their full live load over their full area.

Table 3.1 in metric first

Section 3.4.1 gives representative uniform live loads for typical mill structures. TR-13 calls them recommended minimums for new buildings, a starting point when the actual equipment is not yet known.

Structure Recommended minimum live load
Ironmaking
Casthouse casting floors 24 kPa (500 psf)
Elevated platforms 9.6 kPa (200 psf)
Blast furnace top platforms 14.4 kPa (300 psf)
Steelmaking
Charging, furnace and casting floors 24 kPa (500 psf)
Furnace and ladle repair platforms 24 kPa (500 psf)
Rolling mill
Motor room floors 48 kPa (1,000 psf)
Oil cellar roofs and other operating floors 24 kPa (500 psf)
Miscellaneous
Boiler house operating floors 12 kPa (250 psf)
Working and storage platforms, heavy storage 12 kPa (250 psf)
Working and storage platforms, light storage 6 kPa (125 psf)
Walkways, access platforms and stairs 4.8 kPa (100 psf)

For comparison, an ordinary office floor is designed for about 2.4 kPa (50 psf). A motor room floor at 48 kPa is twenty times that, which is why mill floor framing looks so heavy to anyone used to commercial buildings.

Minimums, not the design load

TR-13 is careful to say these values are not the end of the matter. Section 3.4.1 asks the design engineer, the owner and the equipment suppliers to set the live loads for each structure while recognizing every likely loading scenario:

  • expected storage, such as spare rolls, refractory, stacked product or scrap boxes;
  • concentrated loads from equipment feet, jacks and maintenance stands;
  • equipment loads themselves where they are treated as live;
  • vehicle loads from process and maintenance traffic;
  • bucket and ladle loads where they apply.

The commentary adds that when the actual equipment is known, the engineer should agree loads, deflection limits and installation tolerances with the owner and the equipment maker. All parties should also agree what the load includes: stacks of product, stored process material, maintenance equipment and so on. A 24 kPa casting floor that will also carry a ladle set down on stands may need a much higher local design load.

Concentrated loads and patterns

A uniform load alone rarely governs a mill platform. Beams under a repair deck are usually controlled by a concentrated load: a ladle on its stand, a gearbox set down for maintenance, a mobile lift's outrigger or a forklift wheel. Section 3.4 asks that movable loads be placed for the worst effect, which in practice means checking:

  • concentrated loads at midspan for bending and near supports for shear and bearing;
  • partial uniform loads arranged in a checkerboard on continuous framing;
  • local plate and grating checks under wheels and feet;
  • connection forces where a concentrated load sits close to a beam end.

The commentary to Section 3.9 adds contingency loads: allowances for maintenance equipment, temporary support of process equipment during repairs and emergency operation, mobile lifts on elevated platforms, and anchor points for temporary fall arrest. These are easy to forget at design stage and expensive to add later.

The roof live load

Section 3.2 sets a roof live load of at least about 0.96 kPa (20 psf), not reducible, applied to all or part of the horizontal projection to give the worst effect. That is the same basic value ASCE 7 uses for ordinary flat and low-slope roofs, but TR-13 does not allow it to be reduced for large tributary areas. The reason is practical: mill roofs carry maintenance traffic, stored roofing materials during repairs and, often, a layer of dust.

Dust is treated as its own load. Section 3.10.4 asks that dust buildup be included in loads from ducts, ventilators and monitors on the roof, and roofs downwind of a melt shop can collect a surprising amount. Our article on utility, duct and pipe loads covers those items in detail.

Platforms and the cranes above them

Many mill platforms sit under crane hooks. When a crane sets a load onto a platform, the platform sees the lifted load plus the crane's handling effects. TR-13 deals with crane runway loads separately in Section 3.7, but the platform design should consider what the crane will set down there. A repair platform where the crane lands motor rotors or roll chocks needs a local design load for that, agreed with the operations team.

What the drawings must show

The commentary to Section 3.4.1 ends with a simple rule: in every case, the assumed loads must be clearly shown on the design drawings. A good mill platform drawing states:

  • the uniform live load for each area, with its use;
  • each concentrated load, its footprint and where it may be placed;
  • any vehicle or rail load, with wheel loads and spacing;
  • contingency and maintenance allowances;
  • whether reduction was used, and where.

Later, when the plant changes how a floor is used, these notes tell the plant engineer what the floor was designed for. TR-13 Section 5.8.9 makes a similar point for crane girders: nothing should be attached that is not on the drawings without an engineer's approval.

Following the load down

A heavy floor load does not stop at the beam under it. A 48 kPa motor room floor over a 10 m by 12 m bay carries close to 5,800 kN of live load alone, and that force runs through the girders, the columns and the base plates into the foundations. Three consequences follow for the structure:

  • Columns and bases. Floor columns in a motor room or under a casting floor often carry more load from the floor than from the roof and cranes combined, and their bases need to be sized for it.
  • Foundations. The geotechnical engineer must see these loads early. The commentary to TR-13 Section 3.13 asks that the foundation designer understand the full magnitude and nature of the loads, and stored material at grade near the foundations adds surcharge on top.
  • Lateral systems. Under ASCE 7, part of the floor live load counts as seismic mass where it represents storage. TR-13 Section 3.6 makes the same point for bins, tanks and racks, whose stored contents are included in the seismic mass. A heavy storage platform therefore also raises the seismic forces in the bracing.

Common mistakes on mill floors

Looking back at platform problems on operating plants, the same causes come up again and again:

  • Designing for the table value only. The Table 3.1 minimum was used, but nobody asked what would be set down on the floor during a reline or a major repair.
  • Changing use without checking. A light storage platform becomes a spare parts store, or a walkway becomes the route for a pallet jack.
  • Ignoring dynamic effects. A platform carries a fan, a pump or a screen, and the floor was designed as if the machine were a static weight. TR-13 Section 3.10.1 asks for the dynamic loads and the frequency check; see our article on vibrating equipment supports.
  • No load signs. Lift beam capacities must be marked on the structure under TR-13 Section 1.6.1, and many plants extend the habit to platform load signs, which helps operators keep within the design.

Each of these is cheaper to solve on the drawing board than after the steel is in place.

How World Steel applies it

World Steel designs and fabricates steel structures for US projects, including heavy equipment platforms, industrial floor support structures, steel platforms, stairs and walkways. On a mill project we:

  • start from TR-13 Table 3.1 and the owner's process data, and list every floor's design loads on the drawings;
  • check the framing for concentrated and moving loads as well as the uniform load, with ASCE 7 combinations;
  • set deflection and vibration limits with the equipment supplier where machines sit on the floor, as our equipment floor framing article explains;
  • detail grating, checker plate and toe plates to the loads they carry.

Our designs follow AISC 360 and the project's load criteria, and the US Engineer of Record reviews and seals them. Fabrication is in our own plant in Vietnam, accredited under IAS AC472 and audited twice a year. Site work, including setting and fixing the platforms, is the US contractor's scope.

Solutions and the Sunpro Steel project

Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays, and see the ASCE 7 standard page for the general load basis. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, has induction furnace and continuous caster platform areas where loads of this kind apply.

Source and limits

This article paraphrases AIST Technical Report No. 13 (2021), Sections 3.2, 3.4, 3.4.1, 3.9 and 3.10.4 and the commentary to Sections 3.4, 3.4.1 and 3.9. Metric values are converted and rounded. The owner, the equipment suppliers and the Engineer of Record set the design loads on each project.

Quick answers

What live load does AIST TR-13 recommend for a casting floor?

About 24 kPa (500 psf) for steelmaking charging, furnace and casting floors and for blast furnace casthouse floors, as a recommended minimum. Actual equipment, ladle and storage loads are added on top where they govern.

Can mill floor live loads be reduced?

Only loads of about 4.8 kPa (100 psf) or less tied mainly to human occupancy, as the local building code allows. Heavier loads from storage, equipment or process cannot be reduced.

What roof live load does AIST TR-13 use?

A non-reducible minimum of about 0.96 kPa (20 psf) on all or part of the horizontal projection, placed to give the worst effect.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AIST TR-13 mill building series

Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.

30 articles · 6 parts

Crane classes and loadsSections 1.4–1.5, 3.7, 3.11

Building class, dynamic crane forces, load combinations and the crane data.

Site, soil and foundationsSections 2, 3.13, 4

Soil investigation, foundations under heavy cranes and the floor slab.

Frame, roof and floorsSections 5.2–5.14

Columns, bracing, trusses, girts, equipment floors and connections.

Runway girders and railsSections 3.7.3, 5.8, 5.15

Fatigue details, stiffness, backup bracing, end stops and the rail system.

Shop, testing and serviceSections 1.6, 5.16–5.17, App. C

Weld testing, tolerances, maintenance access, inspection and upgrades.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.