In an office building, most connections carry static loads and are designed once. In a mill, cranes run back and forth, machines vibrate and hot processes cycle the temperature, so connections see millions of load reversals. Loose bolts, cracked welds and corroded thin plates are among the most common problems found when old mill buildings are inspected. AIST Technical Report No. 13 (2021) addresses them in three short sections: 5.12 on minimum thickness, 5.13 on connections and 5.14 on bolt and weld spacing. Together with related rules elsewhere in the report, they set a clear standard. This article explains each rule and the reasoning behind it.
Minimum thickness of material
Section 5.12 sets the minimum thickness for all material except secondary members such as purlins and girts:
| Location | Minimum thickness |
|---|---|
| Exterior construction | About 8 mm (5/16 in) |
| Interior construction | About 6 mm (1/4 in) |
For rolled shapes, the controlling thickness is the mean thickness of the flanges, whatever the web thickness. Metal exposed to marked corrosive action must be protected as the owner specifies.
Why a minimum at all? Mill steel loses thickness over time to corrosion, abrasion and heat scaling. A 4 mm gusset plate that loses 1 mm has lost a quarter of its capacity; an 8 mm plate losing the same has lost an eighth. The minimum gives every primary part a margin against the environment and against handling damage. It also helps welding: very thin plates distort easily and are harder to weld well.
In practice, this rule mostly affects gusset plates, connection plates, stiffeners and bracing members, where a designer working only from strength calculations might choose something thinner.
Connections: welded or pretensioned bolted
Section 5.13 starts with a simple rule: new shop and field connections should be welded or bolted, and every bolted structural connection is made with pretensioned high-strength bolts. Snug-tight bolts, which are common in ordinary buildings, are not used for structural connections in a mill.
It then sets the bolt type by loading:
- Members under fatigue cyclic loading or vibration: slip-critical high-strength bolted connections, to the RCSC Specification for Structural Joints Using High-Strength Bolts.
- Other connections: pretensioned high-strength bolts in bearing-type connections may be used where the drawings say so.
The difference matters under repeated load. In a bearing joint, the bolts pass load by bearing against the hole walls, and under reversing loads the plates can slip back and forth by the hole clearance. That slip hammers the bolts and the holes, loosens the nuts and eventually fails the joint. In a slip-critical joint, the bolt pretension clamps the plates so tightly that friction carries the load, and no slip occurs at service loads. Faying surfaces must be prepared and coated to give the friction coefficient the design assumes.
Slip-critical joints are typical for crane girder connections, crane column splices, bracing that carries crane traction and bumper forces, and supports for vibrating equipment. Our article on vibrating equipment supports covers the last of these.
Nothing attached that is not on the drawings
Section 5.13 also states that appurtenant material must not be attached to structural members unless it is added to the drawings as a revision and approved by a qualified engineer. Section 5.8.9 says the same for crane runway girders, adding that the restriction should be noted clearly on the design drawings.
This is not bureaucracy. A small clip welded to the tension flange of a crane girder to hold a cable tray creates a fatigue detail of a much lower category than the plain flange. Under millions of crane passes, a crack can start at the toe of that weld and grow into the girder. Our article on crane girder fatigue details explains why. The same applies to holes drilled for hangers and to field welds made without a procedure.
Spacing of bolts and welds
Section 5.14 says bolted and welded details generally follow AISC 360, with one specific addition for crane runway girders connected to a horizontal diaphragm plate, the plate that ties the girder top flange to a backup truss or a parallel member:
- if bolted, the bolt spacing is no greater than needed for full shear transfer, and no greater than AISC's limit for intermittent attachment in compression members, whichever is less;
- if welded, the weld is continuous top and bottom.
The horizontal diaphragm carries the crane side thrust from the girder to the backup system, and it acts as part of the compression flange. Widely spaced bolts or intermittent welds would let the plate buckle between fasteners and would create fatigue-prone stops and starts. Our article on backup bracing and box girders covers the diaphragm and backup system.
Continuous welds elsewhere
TR-13 repeats the preference for continuous welds in several places. Section 5.8.3 asks that welds between stiffeners and web or flange plates of crane girders be continuous, except that Class C and D buildings may use intermittent fillet welds for the intermediate stiffener-to-web connection. Intermittent welds have many starts and stops, and each one is a small notch that fatigue can find. For lower-cycle buildings the risk is acceptable; for Class A and B it is not. See our article on building class and crane cycles for the classes.
Work points and eccentricity
Section 5.4 adds a geometric rule: at each connection of primary members, including bracing, member axes should meet at a common work point unless clearances prevent it, and where they do not, the eccentricity must be included in the design. This keeps forces axial and avoids hidden bending in gussets and members. It is especially important in bracing that carries large crane traction and bumper forces, where a few centimetres of eccentricity creates a large moment.
Welding quality
Connection rules mean little without good welding. TR-13 asks that crane girder welds meet AWS D1.1 criteria for cyclically loaded structures (Section 5.16), and the AISC Code of Standard Practice and AWS D1.1 govern welding generally. In practice, that means qualified welding procedures (WPS backed by PQR), qualified welders, controlled consumables and inspection to a plan. Our WPS and PQR page explains how procedures are qualified, and our article on crane girder weld testing covers the inspection scope.
What inspections of old mills find
TR-13's Appendix C, on inspecting and upgrading existing structures, lists the kinds of damage inspectors look for, and connections feature heavily: loose or missing bolts, cracked welds at girder ends and stiffeners, worn or elongated holes, and corroded plates at bracing joints. Our article on the runway inspection program covers that appendix. Many of these defects trace back to choices made at design and fabrication: bearing bolts where slip-critical joints were needed, intermittent welds on high-cycle members, thin gussets in corrosive bays and unplanned attachments added over the years. Following Sections 5.12 to 5.14 from the start avoids most of them, which is why the rules are short and firm rather than flexible.
Field connections and splices
Mill members are large, and most are shipped in pieces and connected on site. TR-13's rules apply equally to field connections:
- field bolts are pretensioned, and slip-critical where fatigue or vibration applies;
- faying surfaces for slip-critical joints are masked during painting, or coated with a qualified slip-rated primer;
- field welds, where used, need the same qualified procedures and inspection as shop welds;
- splice locations are chosen at low-stress points where possible, especially in crane girders.
On a World Steel project, bolting, welding and all site work are the US contractor's scope. Our part is to design and detail field connections so they can be made reliably on site, with clear bolt lists, pretension method notes and faying surface marks.
A connection checklist for mill drawings
Pulling these rules together, mill building drawings should state:
- bolt grade, size and joint type (pretensioned or slip-critical) for every connection;
- the slip coefficient class and faying surface treatment for slip-critical joints;
- weld sizes and types, with continuous welds where TR-13 requires them;
- minimum plate thicknesses consistent with Section 5.12;
- a clear note that no attachments are allowed without an engineer's approval and a drawing revision.
How World Steel applies it
World Steel designs and fabricates mill frames, crane girders, bracing and connection plates for US projects, and supplies structural bolts with the steel. On a mill building, we:
- specify pretensioned bolts throughout and slip-critical joints on members under fatigue or vibration, to the RCSC specification;
- prepare and mask faying surfaces in the shop, or use slip-rated primers where the coating system allows;
- apply TR-13's minimum thicknesses to gussets, plates and stiffeners;
- weld to qualified procedures by qualified welders, with continuous welds where TR-13 calls for them;
- weld all clips and attachments in the shop from the approved drawings, so nothing needs to be added on the girders later.
The US Engineer of Record reviews and seals the design. Our plant in Vietnam is accredited under IAS AC472 and audited twice a year, and welding, bolting preparation and inspection records are kept for each member. Site work is the US contractor's scope.
Solutions and the Sunpro Steel project
Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays. The Sunpro Steel mill project, about 5,000 t with 150 t cranes and bolted crane column splices, is where these TR-13 points were applied at full scale.
Source and limits
This article paraphrases AIST Technical Report No. 13 (2021), Sections 5.4, 5.8.3, 5.8.9 and 5.12 to 5.16. Connection types and details are set by the Engineer of Record on each project.
Quick answers
Does AIST TR-13 allow snug-tight bolts in mill buildings?
No. All bolted structural connections use pretensioned high-strength bolts, and members under fatigue loading or vibration use slip-critical connections. Pretensioned bearing-type joints may be used elsewhere where the drawings say so.
What is the minimum plate thickness in a mill building?
About 8 mm (5/16 in) for exterior and 6 mm (1/4 in) for interior construction, excluding purlins and girts. For rolled shapes, the mean flange thickness controls.
How should a crane girder connect to a horizontal diaphragm plate?
If bolted, at a spacing no greater than needed for full shear transfer or AISC limits for intermittent attachment of compression members, whichever is less. If welded, the weld is continuous top and bottom.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- Quality hubInspection, testing and sign-off at the plant
- IAS AC472 accreditationThe first and only AC472 plant in Vietnam
- Accredited testing labsILAC ISO/IEC 17025 testing on every project
- Online factory auditWalk the shop live with our QA team
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors