Galvanizing inspection, rejection and retest: who checks what under ASTM A123

ASTM A123 gives the galvanizer the job of making the coating comply and the purchaser the right to check it. Galvanizing inspection, rejection and retest follow a clear order in Sections 8 to 10. Here it is, with what it means when the galvanizer is overseas.

· 7 min read · World Steel USA engineering team

ASTM A123 is unusual among coating standards in how plainly it divides the work. The galvanizer is responsible for making the coating comply; the purchaser has the right to check it; and the standard sets out what happens when they disagree. This article walks through galvanizing inspection, rejection, retest and certification in Sections 8 to 10, and what each step looks like when the galvanizing is done overseas, far from the jobsite.

The edition reviewed is ASTM A123/A123M-13. The edition and any inspection requirements in your contract govern.

The tests that are always done

Section 8.1 says the tests in Section 8 are conducted to make sure the coating is furnished as the specification requires. In practice that means two checks on every lot:

  • Thickness, by one of the four methods of Section 8.2, usually a magnetic gauge.
  • Visual inspection of the coating for the finish and appearance requirements of Section 6.

Two more tests are optional. Section 8.1 makes the specifying of adhesion and embrittlement tests a matter of mutual agreement between galvanizer and purchaser. Section 8.3 describes the adhesion test with a stout knife, and Section 8.4 sends embrittlement tests to ASTM A143 and says they are not required unless strong evidence of embrittlement is present.

The galvanizer's inspection program

Section 9.1 puts the responsibility on the galvanizer to ensure compliance with the specification, through an in-plant inspection program designed to keep coating thickness, finish and appearance within its requirements, unless the inspection is performed under Section 9.2.

A credible in-plant program has a few visible signs:

  • written procedures for each stage, from receiving to release,
  • bath control records for the zinc, flux, acid and degreasing tanks,
  • calibrated thickness gauges with verification records,
  • a record of the sample, readings and result for each lot,
  • a nonconformance log with the disposition of each rejected piece.

Those records are what a purchaser's inspector or a reviewer will ask for. The process behind them is described in the hot-dip galvanizing process, step by step.

The purchaser's inspector

Section 9.2 says the purchaser accepts or rejects material by inspection through the galvanizer's inspector, the purchaser's inspector or an independent inspector. The inspector representing the purchaser has access at all times, while the purchaser's work is being performed, to the areas of the galvanizer's facility that concern the application of the coating. The galvanizer must give the inspector all reasonable facilities to be satisfied that the coating is being furnished to the specification.

Three practical choices follow for the purchaser:

Option When it fits What to agree
Accept the galvanizer's inspection Routine work with a trusted chain of records Records to be supplied, certificate under Section 10
Send your own inspector High-value or sensitive work Hold points, notice period, access
Appoint an independent agency Public, bridge or owner-inspected work Scope, sampling plan, reporting

Where inspection happens

Section 9.3 says the material is inspected at the galvanizer's plant before shipment. By agreement, the purchaser may make the tests that govern acceptance in its own laboratory or elsewhere.

For steel galvanized overseas, the place of inspection has real consequences. Inspection at the galvanizer means problems are fixed beside the kettle. Inspection only after delivery means a rejected piece is thousands of kilometers from the bath. The sensible pattern is acceptance at the galvanizer, witnessed in person or remotely, with receiving checks on site for transport damage. The lot rules that make site testing fair are covered in galvanizing lot sampling.

Rejection on visual grounds

When visual inspection under Section 6.2 warrants rejection of a lot, Section 9.4 lets the galvanizer sort the lot and submit it again for acceptance after removing the nonconforming articles and replacing them with conforming ones. Section 9.5 says the sampling plan used on the first inspection is used again for resampling the sorted lot.

By mutual agreement, the galvanizer may also submit the sorted lot without replacing the removed articles. That smaller lot is then treated as a new lot for inspection and acceptance.

Rejection on thickness

Thickness disputes follow the referee method of Section 8.2.5. A new random sample with twice the number of test articles is taken; for large articles it is measured with magnetic gauges calibrated against reference standards, and for small articles the method is agreed. If the lot is still nonconforming, the galvanizer has the right to sort it by testing each article, to regalvanize the nonconforming articles, or to renovate them within the limits of Section 6.2. The measurement side is covered in measuring galvanized coating thickness.

Stripping and regalvanizing

Section 9.6 says materials rejected for reasons other than embrittlement may be stripped and regalvanized, and submitted again for inspection and test, at which point they must meet the specification. Stripping means dissolving the zinc in acid and starting the process again. It is routine for pieces with bare areas beyond the repair limits or thickness below the grade. Embrittled material is excluded because regalvanizing does not restore ductility.

Adhesion: the knife test

Where adhesion testing is agreed, Section 8.3 describes it. The point of a stout knife is applied with considerable pressure, cutting or prying in a way that tends to remove a portion of the coating. Adhesion is inadequate if the coating flakes off as a layer, exposing the base metal ahead of the knife point. Tests at edges or corners, the points of lowest adhesion, are not used, and the removal of small particles by paring or whittling is not a failure.

Certification

Section 10.1 says that when it is specified in the purchase order or contract, the purchaser is furnished certification that samples representing each lot were tested or inspected as the specification directs and the requirements were met. When specified, a report of the test results is also furnished.

Because certification is not automatic, the order should ask for it. A useful certificate names:

  • the purchaser, the project and the order,
  • the specification and edition, for example ASTM A123/A123M-13,
  • the lots covered, by piece mark or tag,
  • the sampling plan and the test methods used,
  • the results, or a reference to the attached report,
  • a signed statement that the requirements were met.

A hold-point plan for overseas galvanizing

For a job where steel is galvanized overseas, a short plan in the inspection and test plan keeps everyone aligned:

  1. Before dipping: receiving check of holes, surface and marking; your inspector may witness.
  2. First lot of each member type: visual and thickness check, witnessed.
  3. Each lot: galvanizer's inspection, records posted within a day.
  4. Repairs: size, method and thickness recorded before release.
  5. Release: certificate and report for the shipment.
  6. On site: receiving check for transport damage, repaired by the US contractor to ASTM A780.

What an inspector should ask for on day one

A purchaser's inspector arriving at a galvanizer, or joining by video, can check the inspection program quickly with a short list of requests:

  1. The written galvanizing procedure and the inspection steps it contains.
  2. The latest zinc bath analysis and the flux and acid control records.
  3. Verification records for the thickness gauges in use, and the reference standards.
  4. The sampling plan and lot definition agreed for the job.
  5. The process tracking sheet for the lot being inspected.
  6. The nonconformance log and how rejected pieces are kept apart.

If those records exist and match what is happening on the floor, most of the inspector's work is confirming results rather than finding problems.

Common sources of inspection disputes

Experience shows that disputes at galvanized steel inspection come from a short list:

  • the wrong edition of A123, so the wrong Table 1 line for plate,
  • a large member treated as one specimen,
  • rejection on a single low reading,
  • gray zinc or roughness from steel chemistry treated as a defect,
  • detailing problems blamed on the galvanizer,
  • transport damage on site treated as a galvanizing failure.

Each of these has a clear answer in the standard, and settling them in the inspection and test plan before work starts is far cheaper than settling them at delivery.

Inspection by video

Remote witnessing has become normal for overseas fabrication, and it suits galvanizing well. A camera at the measuring station shows the gauge reading and the piece mark together, a second view shows the piece being inspected visually, and the inspector can ask for a reading to be repeated or another area to be checked. The session is recorded and archived with the lot records. Section 9.2 does not require the purchaser's inspector to be physically present, only that the inspector has access and the galvanizer gives reasonable facilities.

How World Steel supports your inspection

World Steel fabricates up to 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam, audited twice a year. Galvanizing is arranged in Vietnam with a galvanizer named for the job, under our written galvanizing procedure, with the in-plant inspection program above: process tracking sheets, bath control records, gauge readings per lot and a nonconformance log.

Your inspector, or an independent agency you appoint, can attend the hold points at the galvanizer in person or follow them live by Zoom or Microsoft Teams, with the video archived. The records, the certificate of conformance and the report of test results are posted in PEB Studio by piece mark and bound into the handover file. Repairs are covered in repairing galvanized coatings. See our inspector access page and the standard at a glance on our ASTM A123 page.

Quick answers

Who is responsible for galvanizing inspection under ASTM A123?

The galvanizer, through an in-plant inspection program that keeps coating thickness, finish and appearance within the specification (Section 9.1). The purchaser may accept or reject through the galvanizer's inspector, its own inspector or an independent inspector (Section 9.2).

Where is galvanized steel inspected?

At the galvanizer's plant before shipment, under Section 9.3. By agreement, the purchaser may make the acceptance tests in its own laboratory or elsewhere.

What happens when a galvanized lot is rejected?

For visual rejections the galvanizer may sort the lot, remove nonconforming pieces and resubmit it with the same sampling plan. Rejected pieces, other than for embrittlement, may be stripped, regalvanized and submitted again. Thickness disputes follow the referee method of Section 8.2.5.

Is a galvanizing certificate always supplied?

Only when the purchase order or contract asks for it. Section 10 then requires certification that each lot was tested or inspected and met the specification, and a report of test results when specified.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

ASTM A123 hot-dip galvanizing series

Sixteen in-depth articles that follow a galvanized member from the coating specification, through design for the kettle and the dip itself, to the thickness gauge, the repair rules and the jobsite. Each one explains a part of ASTM A123 in plain terms and lists what to check.

Specify and order

What A123 covers, what goes on the order, and the steel and zinc chemistry behind the coating.

Design for the kettle

Vent and drain holes, distortion, embrittlement and welded assemblies.

Through the kettle

The hot-dip process step by step and the zinc-iron layers it grows.

Thickness and sampling

Coating grades by steel, how the zinc is measured and how a lot is sampled.

Finish, repair and the site

What the finish may show, A780 repairs, inspection and retest, and storage on the way to the job.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.