Skip to content
Seeking US contractor partners IAS AC472 ACCREDITED ★ METAL BUILDINGS ★ AC472 IAS AC472 accreditedIAS AC472
World Steel USA

QC checkpoint: Inspection and Test Plan

Every check written down and signed before the first cut

The Inspection and Test Plan lists each inspection on your job, the standard it follows, the criteria it must meet, the record it leaves and where production stops for your inspector. You review it, we both sign it, and from then on the shop works to it.

Four kinds of point

Where production stops, and where it just tells you

Every line of the plan carries one of these letters. You decide which lines are holds and which are witness points before you sign.

H

Hold point

Work stops until the inspection is done and accepted. If you named an inspector for it, they are notified in advance, and the release is recorded.

W

Witness point

You are notified and may attend in person or by video. If nobody attends at the agreed time, work continues and the result is recorded for you.

R

Review

A document is checked against the specification: mill certificates, welding procedures, qualification records, coating data sheets.

M

Monitor

World Steel QC observes the activity on a sampling basis and records it. No notice is sent.

A typical plan

The matrix behind every World Steel job

Your plan is drafted from your specification, so its lines, references and points will differ. This is the shape it takes, from receiving steel to releasing it for packing.

Contract and specification review

R
Reference
Your project specification and approved drawings
Accepted when
Codes, editions, steel grades, coating and test requirements identified and listed
Record
Specification register
Reference
ASTM grade specification; EN 10204 type 3.1 where specified
Accepted when
Chemistry and mechanical properties within the grade; heat number matches the material
Record
Material log by heat number
Reference
AWS D1.1; AWS D1.8 for seismic welds
Accepted when
WPS prequalified or qualified by PQR for each joint; welders qualified for process and position
Record
Welding procedure register and welder list
Reference
Shop drawings and the WPS
Accepted when
Root opening, bevel, alignment and dimensions as drawn
Record
Dimension Inspection Report
Reference
AWS D1.1 visual acceptance criteria
Accepted when
Size, length, profile and no rejectable discontinuities
Record
Welding Inspection Report
Reference
Your specification; AISC 360 Chapter N; AWS D1.1
Accepted when
Method and extent as specified; acceptance to AWS D1.1
Record
NDT reports
Reference
Shop drawings; AISC 303
Accepted when
Lengths, holes, end plates and straightness within tolerance
Record
Dimension Inspection Report
Reference
AMPP/SSPC grade named in the specification
Accepted when
Cleanliness grade and surface profile achieved; conditions within limits
Record
Coating inspection record
Reference
SSPC-PA 2; coating manufacturer’s data
Accepted when
Dry film thickness of each coat within the specified range
Record
Coating inspection record
Reference
This ITP and the process control tag
Accepted when
Every earlier step signed off; open nonconformances closed
Record
Release record and packing list

H hold · W witness · R review · M monitor. Test methods and extents, NDT included, come from your specification and your Engineer of Record, not from this example.

First page of the World Steel sample Inspection and Test Plan for a PEB warehouse

Sample document

See a real World Steel ITP before you bid

This is the plan format World Steel issues with a quotation, filled in with demonstration data for a pre-engineered warehouse. It follows the job from shop drawing review and incoming material through welding qualification, cutting, fit-up, visual and dimensional checks, NDT, blasting and painting, packing and the manufacturing data record.

  • Document WS-QAC-QITP-0001, revision 00, five A3 pages in English and Vietnamese
  • Separate columns for World Steel, the main contractor, the client or consultant and a third party
  • Hold, witness, review and record points on every line, with the record each check produces

It is a sample. On your project, the inspection items and the inspection rates, NDT extents included, are agreed by both parties and written into your own ITP before fabrication starts.

Inside the sample

Six parts, from drawing approval to the final record

The sample follows the job in the order the work happens. Each part below is a heading in the PDF, and each links to the page that explains how we check it.

Shop drawing

Shop drawings are checked against the approved design drawings, and nothing is cut until the approved set is on record.

Anchor and connection bolts, plate, hot-rolled sections, high-strength bolts, purlins, sheeting, welding consumables and paint, each with its mill certificate reviewed and a visual check, logged on the incoming material inspection report.

Welding procedure specifications and their procedure qualification records, welder qualification records and joint design are reviewed before production welding starts.

Cutting, build-up, fit-up, visual and dimensional inspection, magnetic particle and ultrasonic testing of welds, then blasting and painting to the stated surface preparation and roughness.

Marking, bundling and loading are checked against the packing list before the container is closed.

Manufacturing data record

The reports, certificates and inspection records of the job are gathered into one record that is handed over with the steel.

What every line of the sample carries

  • Inspection activity. what is checked, in English and Vietnamese
  • Reference standard or procedure. the code clause, material standard or World Steel procedure that applies
  • Acceptance criteria. what a pass looks like
  • Inspection frequency. how much is checked, for example every piece or a stated share of welds
  • Inspection record. the World Steel form or certificate the check produces
  • A point for each party. separate columns for World Steel, the main contractor, the client or consultant and a third-party inspector

The full legend used in the sample

H
Hold point
W
Witness point
R
Review point
S
Surveillance
C
Customer-specific requirement
RV
Requires verification
N/A
Not applicable

Inside the document

What a World Steel ITP spells out

Scope and references

The project, the drawing revision, the specification sections and the code editions the plan follows, so an inspector can check every line against its source.

Activities in shop order

From receiving steel to loading the container, each inspection appears once, in the order the work reaches it.

Acceptance criteria

The measurable condition each check must meet, quoted from the standard or the specification, not from habit.

Record for each line

The report or log that proves the check was done: who, when, what was measured and the result.

Who inspects and who attends

World Steel QC for every line; your inspector, special inspector or third-party agency where you mark a hold or witness point.

Notice period

How far ahead we notify hold and witness points, agreed with you so an inspector in the US can plan to attend by video.

Reviewing procedures, qualification records and quality documents
Reviewing procedures, qualification records and quality documents. (IAS AC472 periodic audit, April 2022)

The same discipline is audited from outside: World Steel has held IAS AC472 accreditation since 2019, with plant and office audits twice a year, and AC472 asks for exactly this kind of written inspection program.

From draft to record

How a plan is agreed and then lived

  1. We draft it from your specification

    Our QC team turns the specification, the approved drawings and the code requirements into a draft plan for your job.

  2. You mark it up

    Your project team, inspector or Engineer of Record adds hold and witness points, raises test extents or adds checks of its own.

  3. Both sides sign

    The agreed revision is signed by World Steel and by you before production starts, and it goes into your project records.

  4. Points are called as they come

    As production reaches each hold or witness point, the people named in the plan are notified with the members, the time and the video link.

  5. The plan becomes the record

    Each line fills with report numbers and results, and the completed plan is part of the documents shipped with your steel.

QC and QA

Who checks what at this checkpoint

US practice separates the fabricator’s quality control from the quality assurance carried out for the owner. World Steel runs the QC; your side decides how much QA it adds, and the Engineer of Record sets what is acceptable.

World Steel QC

Quality control: the fabricator

Drafts the plan from your specification, inspects every line of it, calls each hold and witness point in advance and keeps the reports.

Your inspector

Quality assurance: owner, special or third-party inspector

Reviews the draft, chooses which points to hold or witness, and attends in Vietnam, by live video or through remote access to the records.

Your Engineer of Record

Sets the criteria, rules on what changes the design

Sets the test methods and extents in the specification, and confirms any acceptance criteria that differ from the referenced code.

Inspectors can attend in Vietnam, join hold points live on Zoom or Microsoft Teams, or be given remote access to the records on request. The plant itself is audited twice a year under IAS AC472, with periodic plant inspections by Smith-Emery Laboratories.

Questions from US contractors and inspectors

Questions about the Inspection and Test Plan

Ask us anything else about this checkpoint before you award, or during the job through your project manager.

Do we have to write the ITP ourselves?

No. We draft it from your specification and drawings, and you review it. Many US contractors add hold or witness points of their own or ask their special inspector to review it before they sign.

What is the difference between a hold point and a witness point?

At a hold point, work cannot continue until the inspection is done and accepted. At a witness point, you are invited to attend; if nobody attends at the agreed time, the inspection goes ahead and the result is recorded for you.

Can our inspector attend from the US?

Yes. Hold and witness points can be attended live over Zoom or Microsoft Teams, and your inspector can be given remote access to the records on request. Inspectors are also welcome at the plant in Vietnam.

How does the ITP relate to AISC 360 Chapter N?

Chapter N separates the fabricator’s quality control from the owner’s quality assurance, and lists inspection tasks before, during and after welding. The plan sets out how our QC covers those tasks on your job and where your QA inspector steps in.

Does the ITP replace special inspection required by the building code?

No. IBC Chapter 17 decides what special inspection your building needs. IAS AC472 accreditation lets the building official accept our in-plant program in place of in-plant special inspection, but that decision is the building official’s, and field inspections still apply.

Can we see a sample ITP first?

Yes. A sample World Steel ITP for a PEB warehouse is a free download in our download center. It shows the format and the checks, with demonstration data. The inspection items and inspection rates on your job are agreed by both parties for that project.

Who decides the inspection rates, such as how many welds get UT?

Both parties, for each project. Your specification and your Engineer of Record set the minimum, you may ask for more, and the agreed items and rates are written into the project ITP and signed before fabrication starts.

Can the plan change during the job?

Yes, by revision. A change to a test extent, a new hold point or a revised drawing is issued as a new ITP revision, signed again, so the record always shows which version applied to which members.

Send us your specification and we will draft the ITP

Share the specification and drawings for a job you are bidding. Our QC team will return a draft Inspection and Test Plan your inspector can mark up before you award.