Anchor rods are the first steel on a job and the hardest to change. They are cast into the foundation by the concrete contractor weeks or months before the frame arrives, and a rod in the wrong grade, at the wrong projection or in the wrong place means drilling, epoxy and engineering reviews. Most US projects specify them to ASTM F1554, which replaced the old habit of writing "A36 anchor bolts". This article explains the three F1554 grades and the details that make them fit the base plates when the steel arrives.
The values below are a selection from current editions of ASTM F1554 and the standards it refers to. The editions named in the project specification govern.
What F1554 covers
ASTM F1554 is the standard specification for anchor bolts, steel, 36, 55 and 105 ksi yield strength. It covers straight rods, bent rods (hooked) and headed rods, threaded at the projecting end, for anchoring structural supports to concrete foundations. Diameters run from about 12.7 to 102 mm (1/2 to 4 in) in standard inch sizes; drawings show them in mm with the inch size beside them, for example 25 mm (1 in).
F1554 sets strength, chemistry, thread, marking and test requirements specific to anchor rods, which a general bar specification such as A36 does not.
Three grades
| Grade | Minimum yield | Tensile strength | End color |
|---|---|---|---|
| 36 | 250 MPa (36 ksi) | 400 to 550 MPa (58 to 80 ksi) | Blue |
| 55 | 380 MPa (55 ksi) | 517 to 655 MPa (75 to 95 ksi) | Yellow |
| 105 | 725 MPa (105 ksi) | 862 to 1,030 MPa (125 to 150 ksi) | Red |
- Grade 36 is the default for most building columns, where anchor rods mainly locate the column and resist shear and modest uplift.
- Grade 55 is used where uplift or moment is higher, such as in moment-resisting bases, tall frames in high wind or crane columns.
- Grade 105 is a heat-treated alloy grade for very high tension, such as industrial equipment, tall towers or heavy moment bases.
The color code on the projecting end lets the inspector and the erector confirm the grade after the rod is cast in. Rods should also be stamped with the grade and manufacturer's mark where the specification calls for it.
Weldability
Field fixes of anchor rods sometimes involve welding: extending a short rod, adding a plate washer or repairing a bent thread. The grade decides whether that is allowed.
- Grade 36 is weldable.
- Grade 55 is weldable only when ordered with Supplementary Requirement S1, which limits the carbon equivalent. Without S1, its chemistry may make welding unsafe. Ordering S1 by default for Grade 55 is a cheap insurance.
- Grade 105 should not be welded. Heat changes its heat-treated properties.
Galvanizing
Anchor rods are often hot-dip galvanized, especially for exposed or coastal sites. F1554 allows galvanizing, typically to ASTM F2329 for the rod, with nuts overtapped to fit the zinc. Grade 105, because of its strength, needs care with galvanizing and the engineer may prefer another protection. The nuts and washers must have a matching coating.
Nuts and washers
| Rod grade | Usual nut | Washer |
|---|---|---|
| 36 | ASTM A563 Grade A heavy hex | Plate washer or F436 |
| 55 | ASTM A563 Grade A or DH heavy hex | Plate washer or F436 |
| 105 | ASTM A563 Grade DH heavy hex | F436 hardened |
Galvanized rods take galvanized, overtapped nuts. For most columns, the washer under the nut is a thick plate washer, because the hole in the base plate is oversized; see below.
Base plate holes and plate washers
Anchor rods are never set perfectly. To let the column fit, base plate holes are oversized relative to the rod. AISC Design Guide 1, on base plate and anchor rod design, gives recommended hole sizes for each rod diameter, much larger than standard bolt holes, with a thick plate washer over each hole to carry the load. The plate washer is usually field-welded to the base plate where it must transfer shear.
Three details keep this working:
- Use the recommended oversized holes, so normal placement tolerances can be absorbed.
- Show plate washer sizes and thicknesses on the drawings, and whether they are welded.
- Set the anchor rod projection to allow for leveling nuts or shims, grout, the base plate, the plate washer, the nut and full thread engagement.
Four rods and erection stability
OSHA's steel erection standard, 29 CFR 1926 Subpart R, requires in Section 1926.755 that most columns be anchored by at least four anchor rods. The rule exists so that a column standing alone on its foundation is stable during erection before it is connected and braced. It also sets requirements for repairing or modifying anchor rods in the field, which must be approved by the project structural engineer of record. The design may require more rods; it should never show fewer for a column covered by the rule.
Who does what
Anchor rods cross the line between the foundation and the steel. Typical practice:
- The Engineer of Record designs the rods and shows grade, diameter, embedment and projection.
- The steel fabricator details the anchor rod plan and setting drawings, and can supply the rods, nuts, washers and setting templates with the steel package.
- The concrete contractor sets the rods in the foundation, to the setting drawings and tolerances.
- The steel contractor surveys the rods before erection and reports anything out of tolerance.
The steel erection support guide explains what the steel package includes for the US contractor's field team.
Ordering anchor rods: what to write
- ASTM F1554 and the grade (36, 55 or 105).
- For Grade 55, Supplementary Requirement S1 if welding might be needed.
- Diameter, length, thread length and form: straight, hooked or headed.
- Coating: plain or hot-dip galvanized, with matching nuts.
- Nuts (A563 grade) and washers: plate washer sizes and F436 washers.
- Templates, if the fabricator supplies them.
Checking anchor rods on arrival
Before rods go to the concrete crew, check:
- The color code and marking match the grade on the drawings.
- The certificate shows the grade, heat, tensile and yield results.
- Thread length and projection allow the nut stack on the drawings.
- Coating and nuts match.
Common anchor rod problems on site
Anchor rod issues are among the most common causes of delays at the start of steel erection. Most come from a handful of causes:
- Wrong projection. Rods too short to take the full nut, or too long for the leveling detail. A clear projection dimension on the setting drawing, measured from top of concrete, prevents most of them.
- Rods out of position. Templates that move during the pour, or rods set without a template. Oversized holes absorb small errors; larger errors need the engineer's fix.
- Damaged threads. Threads hit by equipment or filled with concrete. Thread protectors or tape during the pour keep them clean.
- Wrong grade. A Grade 36 rod set where Grade 55 was specified. The color code on the projecting end lets the steel contractor check before erection.
- Rods bent to fit. Bending a rod to line up with the base plate can damage it and changes its capacity. Field bending or repair needs the engineer's approval and, under OSHA Subpart R, the structural engineer of record's approval for modifications.
A survey of all anchor rods before the steel arrives, compared with the anchor rod plan, gives time to fix problems without stopping erection.
Embedment and concrete design
The rod grade sets the strength of the steel, but anchor capacity in tension often depends on the concrete: breakout, pullout and side-face blowout under ACI 318 Chapter 17. That design belongs to the Engineer of Record. A higher rod grade does not help if the concrete governs, which is one reason Grade 36 remains common.
Anchor rods and moment bases
Columns with fixed bases, crane columns and tall frames in high wind or seismic zones use anchor rods for real tension and moment. Three details change for them:
- Grade. Grade 55 or 105 may be needed for the tension.
- Embedment. Longer embedment, headed rods or a plate at the bottom of the rod spread the load into the concrete, and the concrete design may add reinforcement around the rods.
- Pretension. Some designs pretension anchor rods to limit base rotation. That requires a grade, a nut and a procedure suited to pretension, and is set by the Engineer of Record.
For these bases, the anchor rod plan, the base plate detail and the foundation reinforcement should be reviewed together, before the concrete contractor builds the cages.
How World Steel supplies anchor rods
World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam. Anchor rods, nuts, plate washers and setting templates can be shipped ahead of the main steel, so they reach your foundation crew first. They are ordered to the F1554 grade on your drawings, mainly from Vietnamese suppliers, with other sources in Asia when a grade or size calls for it, and every lot is color coded and travels with its certificate, EN 10204 3.1 when your specification asks for one.
The anchor rod plan and setting drawings come with our shop drawings at no extra cost. Check tests, when your inspector asks for them, run at an ILAC-recognized ISO/IEC 17025 laboratory or the laboratory you name. Our anchor bolts page shows the forms we supply, and all grades are on the structural steel materials page. Next in the series: A653 and A1011 sheet for cold-formed framing.
Quick answers
What are the grades of ASTM F1554?
Three, named by minimum yield: Grade 36 at 250 MPa (36 ksi), Grade 55 at 380 MPa (55 ksi) and Grade 105 at 725 MPa (105 ksi), each with a tensile strength range.
What do the colors on F1554 anchor rods mean?
The projecting end is painted to show the grade: blue for Grade 36, yellow for Grade 55 and red for Grade 105, so the grade can be checked after the rod is cast in.
Can F1554 anchor rods be welded?
Grade 36 is weldable. Grade 55 is weldable when ordered with Supplementary Requirement S1, which limits the carbon equivalent. Grade 105 should not be welded.
How many anchor rods does a column need?
OSHA Subpart R, 29 CFR 1926.755, requires at least four anchor rods for most columns, so a column is stable during erection before it is guyed or braced. The design may require more.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors