A seismic steel building is designed twice. First, the Engineer of Record designs the structure and shows it on the contract drawings. Then the fabricator's detailers turn that design into fabrication and erection documents, the shop drawings and erection drawings that tell the shop and the field crew exactly what to make and how to assemble it. For ordinary steel, the AISC Code of Standard Practice and AISC 360 govern that second step. For the seismic force-resisting system (SFRS), the AISC 341 provisions add specific items in Section I1. This article explains each one, why it matters and how to review it.
From contract drawings to fabrication documents
Section A4 of AISC 341 lists what the structural design documents must contain for the SFRS: the designation of the SFRS, its members and connections, the system type, demand critical welds, protected zones, the material specifications, and specific items for connections such as continuity plates and doubler plates. A separate article in the chapter-by-chapter series covers Section A4 in depth.
The fabricator's documents start from that information. Section I1.1 requires fabrication documents to show the work to be performed and the items required by AISC 360, the Code of Standard Practice, the building code and Sections A4.1 and A4.2, and, as applicable, five more items:
- Locations of pretensioned bolts.
- Locations of Class A, or higher, faying surfaces.
- Gusset plates designed to accommodate inelastic rotation.
- Weld access hole dimensions, surface profile and finish requirements.
- Nondestructive testing (NDT) where performed by the fabricator.
Section I1.2 requires erection documents to show pretensioned bolt locations and the joints or groups of joints in which a specific assembly order, welding sequence, welding technique or other special precautions are required.
Pretensioned bolts
Bolted joints in the SFRS are designed under Section D2.2, typically as pretensioned joints, with slip-critical faying surfaces where the design requires. The shop drawings must show which bolts are pretensioned, because installation and inspection differ from snug-tight bolts. In the field, the US contractor's crew installs and verifies them using the turn-of-nut method, calibrated wrenches, twist-off bolts or direct tension indicators, and the inspector checks them under Chapter J. Mislabeling a pretensioned joint as snug-tight is a common cause of rework.
Faying surfaces
Slip-critical joints rely on friction between the plies. Their faying surfaces must meet the slip class shown on the design documents, usually Class A or Class B. Paint, galvanizing and mill scale affect the slip coefficient, so the shop drawings must identify where faying surfaces are masked from paint, blasted to a specified profile or coated with a qualified slip-rated primer. On coated or galvanized steel, this is one of the most important coordination points between the coating specification and the seismic design.
Gusset plates that rotate
In special concentrically braced frames (Section F2), braces buckle out of plane in a strong earthquake. Gusset plates at brace ends must accommodate that rotation, usually by leaving a clear distance between the end of the brace and the line of restraint, often twice the gusset thickness, so the plate can bend. Some designs use elliptical clearance patterns. Section I1.1 requires the fabrication documents to identify gussets designed for inelastic rotation, so that the clearance is detailed accurately and not lost to shop convenience, such as welding a stiffener across the hinge line.
Weld access holes
Weld access holes, the cutouts in a beam web that let welders reach the flange groove weld, play a big role in moment connection performance. AWS D1.8 specifies their geometry, and AISC 358 prequalified connections may require a specific profile. Section I1.1 requires the fabrication documents to show their dimensions, surface profile and finish. Rough or notched access holes can start cracks under cyclic loading; the drawings should specify the radius, the surface roughness and any grinding required. Our AWS D1.8 series has an article on weld access holes.
Nondestructive testing by the fabricator
Chapter J assigns NDT of SFRS welds to the quality assurance agency, except where AISC 360 Section N6 permits otherwise. When the fabricator performs NDT, for example as part of its quality control, Section I1.1 requires the fabrication documents to show it. That lets the Engineer of Record, the inspector and the shop agree which welds are tested by whom, and avoids gaps or duplicate testing.
Demand critical welds and protected zones on the drawings
Section A4 requires the design documents to identify demand critical welds and protected zones. The fabrication documents carry them forward. Good practice is to:
- Tag demand critical welds on every detail where they occur, with a clear symbol and a note referencing AWS D1.8.
- Shade or hatch protected zones on member drawings, with dimensions from the column face or the connection reference.
- Show where protected zones will be marked on the steel, if the project requires marking.
- Coordinate shear stud layouts, deck attachments and support clips so none fall within protected zones, as Section I2.1 requires.
Welding procedures and submittals
Section I2.3 requires welding to follow AWS D1.8 and D1.1, with welding procedure specifications approved by the Engineer of Record. Section J3 lists the documents the fabricator submits before fabrication: WPSs, filler metal certificates of conformance, supplemental notch toughness certificates for demand critical welds, intermix test data where FCAW-S is combined with other processes, product data sheets and bolt installation procedures. These travel with the shop drawings, so the reviewer sees the details and the procedures together.
Continuity plates and stiffeners
Section I2.4 requires corners of continuity plates and stiffeners in the webs of rolled shapes to be detailed to AWS D1.8 clause 4.1, with clips that keep welds away from the column's k-area. The shop drawings must show the clip dimensions. AISC 341-22 also relaxed some continuity plate weld requirements, which the detailer must apply exactly as the design documents state.
Material and piece mark traceability
Seismic fabrication documents also carry the information that makes traceability possible. Each SFRS member's drawing shows its material grade, any supplemental requirements such as Charpy testing for heavy sections under Section A3.4, and its piece mark. In the shop, the piece mark links the member to the heat numbers on the mill certificates, the welders who made its welds, the WPSs used and the inspection reports. Section J6 of AISC 341 requires shop inspection reports to identify the piece mark of the piece inspected, so the drawing's piece mark becomes the key that joins every quality record for that member. A clear, unique piece mark system, consistent between drawings, labels and records, is one of the simplest ways to make a special inspector's job easy.
Revisions and change control
Seismic projects change during detailing: an architect moves an opening, a brace shifts a bay, a beam size changes after a drift check. Each change ripples through connections, protected zones and demand critical welds. Revision clouds, revision logs and a clear record of which drawing revision was used for fabrication protect everyone. The shop must never fabricate SFRS members from superseded drawings, which means document control in the plant has to be as disciplined as in the drawing office.
Reviewing seismic shop drawings
A reviewer checking seismic shop drawings should confirm:
- SFRS members are identified and match the design documents.
- Material grades and any Charpy requirements are shown.
- Pretensioned bolts and faying surfaces are marked.
- Gusset plate clearances for buckling braces are correct.
- Weld access holes match the required geometry and finish.
- Demand critical welds and protected zones are shown everywhere they occur.
- NDT by the fabricator is identified.
- Erection documents flag joints needing special sequence or technique.
From drawings to the model
Most US steel is now detailed in 3D models, such as Tekla Structures, with drawings generated from the model. Seismic attributes, including SFRS member flags, demand critical welds and protected zones, can be stored as model properties, which keeps them consistent across hundreds of drawings and lets the reviewer see them in the model as well. Model sharing in IFC format lets the Engineer of Record and the contractor check clashes and protected zones before fabrication.
Proof from the drawing office
World Steel prepares shop drawings for every project at no extra cost, in Tekla, by an in-house drawing office that works to US standards every day. For seismic projects such as the FPI Barracks on Guam, the same team produced the structural calculation report, the permit drawings and the shop drawings, and the whole job went from the start of design to CIF delivery in 60 days. On large projects such as the 5,000-tonne Sunpro Steel mill and the 2,000-tonne Long Son petrochemical complex, our drawing office issued drawings in phased packages that matched the fabrication and delivery sequence.
Our model attributes carry SFRS flags, demand critical welds and protected zones, so they appear on every sheet and can be checked in the shared model. Our quality system holds IAS AC472 accreditation since 2019 and ISO 3834-2 certification from Bureau Veritas, and the download center includes sample approval drawings and a sample design report so a contractor can see our drawing standard before bidding.
How World Steel supports seismic drawing review
World Steel designs and fabricates structural steel for US contractors in its own plant in Vietnam, the first and only IAS AC472 accredited fabricator in the country. We prepare shop drawings and erection drawings with all Section I1 items, submit WPSs and filler metal data with them, and turn review comments quickly.
Drawing status and fabrication progress can be followed in PEB Studio. The Engineer of Record approves the design and the drawings, and the US contractor, our customer, carries out the site work. The next article explains the approved fabricator route and how it fits AISC 341 Chapter J.
Quick answers
What does AISC 341 call shop drawings?
Fabrication documents. AISC 341-22 Section I1.1 lists what fabrication documents for the seismic force-resisting system must show, and Section I1.2 does the same for erection documents.
What must seismic fabrication documents show?
Besides the items required by AISC 360, the Code of Standard Practice and Section A4, they show pretensioned bolt locations, Class A or higher faying surfaces, gusset plates designed for inelastic rotation, weld access hole dimensions and finish, and NDT performed by the fabricator.
What must seismic erection documents show?
Pretensioned bolt locations and the joints that need a specific assembly order, welding sequence, welding technique or other special precautions.
Who approves seismic shop drawings?
The Engineer of Record, or a designee, reviews them for conformance with the design intent. AISC 341 Section I2.3 also requires the Engineer of Record to approve the welding procedure specifications.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- Seismic steel structuresSDC D to F framing we fabricate for US jobs
- Seismic regionsWhere seismic design governs in the US
- California seismic designThe everyday AISC 341 market
- Accredited testing labsILAC ISO/IEC 17025 testing on every project
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors