AISC 341 seismic steel

Seismic retrofit with new steel frames: AISC 341, AISC 342 and ASCE 41

Thousands of US buildings, from older concrete and masonry to pre-Northridge steel frames, need seismic strengthening. New steel braced frames and moment frames are among the most common fixes. This article explains how AISC 341, AISC 342 and ASCE 41 work together in a seismic retrofit.

· updated November 30, 2026 · 7 min read · World Steel USA engineering team

The United States has a large inventory of buildings that would not meet today's seismic standards: unreinforced masonry, non-ductile concrete frames, soft-storey wood buildings, tilt-up warehouses with weak roof-to-wall anchorage, and welded steel moment frames built before the 1994 Northridge earthquake revealed brittle connection fractures. Cities such as Los Angeles, San Francisco, Seattle and Portland now require many of them to be strengthened. Seismic retrofit with new steel braced frames and moment frames is one of the most common solutions. This article explains how the AISC 341 provisions, AISC 342 and ASCE 41 work together on a retrofit, and what that means for the steel package.

Why retrofit, and who requires it

Retrofit happens for three main reasons:

  • Mandatory programs. Los Angeles requires retrofit of soft-storey wood buildings and non-ductile concrete buildings; San Francisco has soft-storey and other programs; several cities have unreinforced masonry ordinances; and California's hospital seismic safety law has driven decades of hospital retrofit and replacement.
  • Triggers in the existing building code. The International Existing Building Code (IEBC) can require seismic evaluation and strengthening when a building undergoes a substantial alteration, a change of occupancy to a higher Risk Category, or an addition that changes the lateral load path.
  • Owner decisions. Owners retrofit voluntarily to protect tenants, reduce insurance and lender risk, or meet a performance target for critical operations such as data centers and laboratories.

The standards: evaluate with ASCE 41 and AISC 342, design new steel with AISC 341

A retrofit uses two families of standards:

  • ASCE/SEI 41, Seismic Evaluation and Retrofit of Existing Buildings, sets the performance objectives, the analysis procedures and the acceptance criteria for existing and new components. It allows linear and nonlinear procedures and defines performance levels such as Immediate Occupancy, Life Safety and Collapse Prevention.
  • AISC 342-22, Seismic Provisions for Evaluation and Retrofit of Existing Structural Steel Buildings, gives the steel-specific rules for ASCE 41: material properties of existing steel, modeling and acceptance criteria for members and connections, and retrofit measures. Section A2 of AISC 341-22 lists AISC 342 among its referenced standards.

New steel elements added to resist seismic loads, such as braced frames, moment frames or plate shear walls, are typically designed and detailed to AISC 341 for their system, so that they behave in a predictable, ductile way. Where ASCE 41 is used for the whole building, its acceptance criteria apply to the new elements too, but their detailing follows AISC 341 in practice, and many jurisdictions require it.

Common steel retrofit strategies

The usual steel solutions are:

  • New special concentrically braced frames (Section F2), inserted into bays of existing concrete or steel frames, or along walls of masonry buildings.
  • New buckling-restrained braced frames (Section F4), popular for their high strength and stiffness from few bays. Their connection forces, set by the adjusted brace strength, are lower than those of a conventional brace of the same yield strength, which reduces demand on the existing structure.
  • New eccentrically braced frames (Section F3), where openings must stay clear.
  • New special moment frames (Section E3), for soft-storey wood buildings, where a steel frame at the ground floor opening replaces the missing walls. AISC 358 prequalified connections, including bolted connections, are often used to reduce field welding.
  • Strengthening of existing pre-Northridge steel moment connections, by adding haunches, cover plates or side plates, evaluated under AISC 342.
  • Collectors and drag struts to tie existing diaphragms to new frames, designed for the overstrength load under Section B5 of AISC 341, with their connections to old concrete or timber designed carefully.

Connecting new steel to old structure

The hardest part of a retrofit is the connection between new steel and the existing building. New frames need:

  • Foundations, often new footings or micropiles under each braced frame, because existing foundations rarely have the capacity for the overturning of a new frame.
  • Load transfer from existing diaphragms into the new frames, through collectors, drag struts and anchors into existing concrete, masonry or timber.
  • Connections to existing steel, bolted or welded. Existing steel may be of unknown grade, and welding to it requires weldability checks; AISC 342 gives default material properties and testing requirements for existing steel.

The new steel itself must meet AISC 341 materials rules under Section A3, with expected strength factors used to design the connections and the existing elements that receive the force.

Pre-Northridge steel moment frames

A special case is the steel building that already has a moment frame, built before the 1994 Northridge earthquake. Many of those frames used welded unreinforced flange connections with backing left in place, weld access holes of the older profile and filler metals without notch toughness requirements. Northridge showed that such connections could fracture at low drift. Los Angeles, among other jurisdictions, now requires evaluation and, where needed, retrofit of pre-Northridge steel moment frames.

AISC 342 gives the modeling parameters and acceptance criteria for those existing connections, which are much lower than for modern prequalified connections. Retrofit options include adding welded haunches below the beam flange, cover plates, side plates or new braced frames that reduce the drift the old connections must survive. Each option has a fabrication side: haunches and plates are shop-cut pieces welded in the field, often in tight spaces above ceilings, so precise fabrication and clear field welding procedures are essential. Welding to existing steel of uncertain chemistry needs testing or conservative procedures, and field welds are made to AWS D1.8 where they form part of the seismic force-resisting system.

Tilt-up and masonry buildings

Older tilt-up warehouses and masonry buildings fail first at the wall-to-roof connections: heavy walls pull away from light roofs in strong shaking. Retrofit adds steel straps, ties and continuous cross-ties through the roof diaphragm to keep the walls attached, and sometimes new steel braced frames or moment frames inside the building. The steel quantities are modest, but the number of pieces is large, and they must fit an existing roof structure. Standard, repeated details and clear piece marks keep that work fast.

Field verification and fit

Existing buildings are never exactly as drawn. Columns lean, floors sag, beams are not where the original drawings said, and decades of tenant changes have added walls, ducts and pipes. Retrofit steel must fit that reality:

  • Field verification of dimensions before shop drawings are finalized, often with laser scanning.
  • Adjustable connections, slotted holes, shims and field-drilled holes where AISC 341 allows them and the Engineer of Record approves.
  • Piece sizes that fit through existing doors, elevators and openings, and weights that can be handled without heavy cranes inside an occupied building.
  • Bolted field connections where possible, because field welding in an occupied building brings fire watch, fumes and inspection issues.

Protected zones in new frames still apply. Section I2.1 forbids attachments in them unless the Engineer of Record approves, which matters when new frames sit among existing services.

Phasing and occupied buildings

Many retrofits happen in occupied buildings: tenants stay, hospitals keep operating, schools work around summer. The steel arrives in small lifts, often at night, and is assembled bay by bay. The steel package must be divided into lots that match the work zones, labeled clearly and delivered on a schedule tied to tenant moves.

Quality and inspection

New AISC 341 elements in a retrofit carry the same quality control and assurance requirements of Chapter J as in new buildings: inspection by piece mark in the shop, ultrasonic testing of complete-joint-penetration groove welds in the SFRS, inspection of bolting and of protected zones. Field connections to existing steel may need extra NDT and weldability testing. Retrofit permits often require a special inspector familiar with both new and existing construction.

Proof for retrofit and expansion work

Retrofit steel demands careful drafting and precise fabrication more than tonnage. World Steel's drawing office prepares shop drawings in Tekla from field-verified dimensions at no extra cost, and our laser machines cut and drill plate up to 100 mm thick with the accuracy that bolted retrofit connections need. For complex geometry we trial-fit connections in the shop before shipping, so pieces fit existing structures on the first attempt.

Repeat industrial clients such as Haid Group come back to us because later phases fit earlier ones, and our seismic retrofit and expansion page explains how we support those projects in the US. Our quality system holds IAS AC472 accreditation since 2019 and ISO 3834-2 certification from Bureau Veritas, welders and procedures are qualified to AWS D1.8, and all materials are tested at ILAC-accredited ISO/IEC 17025 laboratories.

A checklist for steel retrofit packages

  • Confirm the evaluation standard (ASCE 41 with AISC 342) and the performance objective.
  • Confirm that new frames are detailed to AISC 341 for their system.
  • Verify field dimensions before shop drawings, and design connections that allow adjustment.
  • Size pieces for access and handling inside the existing building.
  • Divide the package into lots that match the phasing of an occupied building.

How World Steel supports retrofit projects

World Steel designs and fabricates structural steel for US contractors in its own plant in Vietnam, the first and only IAS AC472 accredited fabricator in the country. For retrofits we design new braced frames, moment frames and collectors to AISC 341-22 in coordination with the Engineer of Record's ASCE 41 and AISC 342 evaluation, and prepare the calculation report and shop drawings from field-verified dimensions.

Steel is packed in phase lots, labeled by work zone and tracked in PEB Studio. The Engineer of Record approves the design and the US contractor, our customer, carries out the site work. The next article opens the design decisions part of this series: choosing the seismic force-resisting system.

Quick answers

What is the difference between AISC 341 and AISC 342?

AISC 341 covers the design of new steel seismic systems. AISC 342, Seismic Provisions for Evaluation and Retrofit of Existing Structural Steel Buildings, which AISC 341-22 lists as a referenced standard, covers how to evaluate existing steel members and connections and how to retrofit them, working with ASCE/SEI 41.

When does a retrofit trigger new AISC 341 steel?

When new braced frames, moment frames or walls are added as part of the seismic force-resisting system. New steel elements are usually detailed to AISC 341, while the existing structure is evaluated to ASCE 41 and AISC 342.

Why are buckling-restrained braces common in retrofits?

They give high, predictable strength and stiffness with stable behavior, so fewer braced bays are needed, and their connection forces are lower than those of conventional braces of the same strength, which reduces work on the existing structure.

What makes retrofit steel hard to fabricate?

Existing buildings are never exactly as drawn. Retrofit steel needs field verification of dimensions, connections that allow adjustment, and pieces sized to fit through existing doors and around services.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AISC 341 across the US

Twenty-five in-depth articles on where the Seismic Provisions govern in the United States, what they change for each building type, which design decisions set the tonnage, and how a seismic steel package is bought, fabricated and delivered for a US contractor.

US seismic regionsWhere it governs

The West Coast, Alaska, the islands, the Intermountain West, New Madrid and Charleston.

Design decisionsWhat sets the tonnage

Choosing the system, the gravity frame that must follow it, and piles.

Buying and deliveryFrom order to jobsite

Shop drawings, the approved fabricator, overseas sourcing, lead time and site work.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.