Pre-engineered metal buildings are optimized systems. Their tapered frames put steel only where the moment diagram needs it, their purlins and girts are cold-formed and lapped for continuity, and their bracing is as light as the loads allow. That efficiency is why they dominate US warehouses, workshops, hangars, agricultural and light industrial buildings. Seismic regions test the optimization, because ductility does not come from minimum steel. This article explains how a metal building system meets ASCE 7 and the AISC 341 provisions in Seismic Design Category C, D and above, and what a contractor should check.
Metal buildings in the code stack
Metal building systems in the US are designed to the IBC and ASCE 7 for loads, AISC 360 for hot-rolled and built-up members, AISI S100 for cold-formed purlins and girts, and AWS D1.1 and D1.3 for welding, following the practice of the MBMA Metal Building Systems Manual. Tapered frames are built-up members, welded from plate in the shop. In seismic regions, AISC 341 adds detailing rules for the frames and bracing that form the seismic force-resisting system (SFRS).
Section A1 of AISC 341 points, through its User Note, to the R = 3 route of ASCE 7 Section 14.1.2.2.1: in SDC B and C, a metal building can be designed with the coefficients for steel systems not specifically detailed for seismic resistance and skip AISC 341. In SDC D and above, that route is closed for most buildings, and the frames and bracing must be AISC 341 systems.
The transverse direction: tapered moment frames
Across the building, the lateral system is the tapered frame itself. In seismic terms, it is usually:
- An ordinary moment frame (OMF) under Section E1, with R = 3.5. ASCE 7 limits OMF in SDC D, E and F, but its single-storey exceptions allow OMFs in many light metal buildings: for example, single-storey buildings up to about 20 m (65 ft) in height with roof dead loads below the specified limit, and wall weight limits for the exterior walls.
- An intermediate moment frame (IMF) under Section E2, with R = 4.5, where the building or its loads fall outside the OMF limits, or the designer wants lower forces.
Section E1 sets requirements for OMF connections. Fully restrained moment connections must be designed for a required strength based on the expected beam strength or the maximum force the system can deliver, or be prequalified or tested. End-plate connections common in metal buildings can be designed to meet the requirement, but the bolts, plates and welds are larger than for gravity design. Section E1.6 also sets rules for welds and demand critical welds in OMF connections where complete-joint-penetration groove welds are used.
Tapered members must also meet the width-to-thickness limits of Section D1.1 where the system requires them. Metal building rafters and columns are often slender, with thin webs and narrow flanges, optimized for gravity and wind. In OMF the limits are relatively mild, but IMF requires moderately ductile members, which can force thicker webs or wider flanges near the connections.
The longitudinal direction: bracing
Along the building, metal buildings resist lateral loads with bracing in the roof and walls, or with portal frames where doors leave no room for braces. The common types are:
- Rod or cable bracing, tension-only, light and cheap. ASCE 7 and AISC 341 restrict tension-only systems in seismic design. Section F2.4d does not permit tension-only frames as SCBF. As OCBF, tension-only rod bracing faces slenderness and system limits, and its connections must develop the required strength of the rod.
- Angle or HSS bracing, which works in tension and compression, designed as ordinary concentrically braced frames (Section F1) or special concentrically braced frames (Section F2).
- Portal frames in braced bays where doors or openings prevent diagonal bracing, designed as moment frames.
Brace connections are the critical detail. In OCBF, brace connections must be designed for the expected brace strength in tension, or the maximum force the system can deliver. In SCBF, they must also accommodate brace buckling. Metal building bracing that uses light rods with simple clip connections needs careful checks in seismic regions.
Roof diaphragms and collectors
Metal building roofs are often standing seam panels that do not act as diaphragms, so roof bracing carries the in-plane forces. Through-fastened roofs can provide some diaphragm action. Either way, seismic forces must travel from the roof to the wall bracing. Eave struts and roof bracing act as collectors, and Section B5 requires collectors and their connections to be designed for the overstrength seismic load. In long buildings, eave struts sized for wind may need to grow.
Column bases and anchor rods
Metal building column bases are usually pinned in the transverse direction, carrying shear and uplift through anchor rods and base plates. In braced bays, they also carry uplift and shear from the braces. Section D2.6 of AISC 341 requires SFRS column bases to be designed for the forces the frame and braces can deliver. Anchor rods and their embedment, designed to ACI 318, often need hairpins or shear lugs to transfer large shear forces in seismic regions.
Heavy walls, cranes and mezzanines
Seismic forces in metal buildings rise quickly when the building carries heavy elements:
- Concrete or masonry walls, which add weight and must be anchored to the frame for out-of-plane forces.
- Cranes, whose runway girders and brackets add mass and lateral forces.
- Mezzanines and equipment platforms, which may need their own lateral system.
Each of these can push a building outside the OMF exceptions, and toward IMF or braced frames.
Purlins, girts and the secondary system
Cold-formed purlins and girts are not part of the seismic force-resisting system in most metal buildings, but they are part of the seismic load path. They brace the rafter and column flanges against lateral-torsional buckling, they carry roof and wall cladding loads into the frames, and in through-fastened roofs they connect the diaphragm to the frames. In seismic regions, the flange braces that tie purlins to rafter bottom flanges become more important: AISC 341 stability bracing rules for moment frame beams under Section D1.2 apply where the system requires them, and an IMF rafter needs bracing at closer spacing than a gravity rafter.
Heavy wall systems change the girts too. Insulated metal panels are light, but concrete or masonry walls attached to the frame produce out-of-plane seismic forces that must travel through girts or wall anchors into the columns. Those connections need to be designed for seismic forces, not just wind, and placed where they do not interfere with column flange bracing or protected zones.
Expansions of existing metal buildings
Metal buildings are often expanded: a new bay added to the end, a lean-to on the side, or a second building joined to the first. When the original building was designed under a lower seismic category or an older code, the expansion can trigger a review of the existing structure. Expanding an end wall usually means replacing the end frame with a full interior frame, adding bracing in the new bays and checking whether the original bracing and anchor rods still work for the larger building. Lean-tos attached to existing columns add load to those columns and their bases. A seismic joint between old and new often keeps the design and the permit simpler.
What a contractor should check
Metal building systems are often bought as a package, designed by the supplier's engineers. In seismic regions, the contractor and the Engineer of Record should check:
- The seismic system in each direction and the R value used.
- Whether the ASCE 7 exceptions that allow OMF or OCBF are actually met for height, roof weight and wall weight.
- The connection design basis for end plates and bracing, and whether demand critical welds are identified.
- The column base and anchor rod design for seismic forces, coordinated with the foundation.
- The Chapter J quality control that applies to the SFRS, including inspection of welds on tapered members.
Proof from a metal building specialist
Pre-engineered buildings are where World Steel started, and where our engineering is deepest. We design and fabricate all nine common steel frame systems, from gable clear span and multi-span frames to mono-slope and arched roofs, with web-tapered members welded in our own plant. Our references include warehouses, factories and commercial buildings across Asia, the Pacific and the US, among them the Cost U Less Supermarket and the UR Warehouse on Guam, and in seismic conditions the FPI Barracks on Guam, a seismic-designed steel building delivered in 60 days.
Our plant fabricates 2,500 tonnes a month, holds IAS AC472 accreditation since 2019 and ISO 3834-2 certification from Bureau Veritas, and qualifies welders and procedures to AWS D1.8 where demand critical welds occur. We design metal buildings to the MBMA Metal Building Systems Manual practice and AISC 341-22 where it applies, so a contractor can buy a metal building package and a conventional steel package from one plant.
A checklist for seismic metal buildings
- Confirm the Seismic Design Category and the system in each direction.
- Check OMF and OCBF exceptions against the real roof and wall weights.
- Avoid tension-only bracing where AISC 341 does not permit it.
- Check eave struts and roof bracing as collectors for the overstrength load.
- Coordinate cranes, mezzanines and heavy walls with the lateral design.
How World Steel supports metal building projects
World Steel designs and fabricates structural steel for US contractors in its own plant in Vietnam, the first and only IAS AC472 accredited fabricator in the country. For pre-engineered metal buildings in seismic regions we design to AISC 360, AISC 341-22 where it applies and MBMA practice, and prepare the calculation report and shop drawings at no extra cost.
Frames, bracing, purlins, girts and cladding ship as one package, packed in erection order, and every piece can be tracked in PEB Studio. The Engineer of Record approves the design and the US contractor, our customer, carries out the site work. The next article looks at retrofit: adding new steel frames to existing buildings.
Quick answers
Can pre-engineered metal buildings be used in high seismic regions?
Yes. Metal buildings are common in SDC D and above, using tapered moment frames as ordinary or intermediate moment frames within ASCE 7 limits, and braced frames in the longitudinal direction, detailed to AISC 341 where it applies.
Which seismic system does a tapered frame represent?
Usually an ordinary moment frame under AISC 341 Section E1, with R = 3.5, or an intermediate moment frame under Section E2 where the limits require it. In SDC B and C the R = 3 route without AISC 341 detailing is also possible.
Are rod-braced metal buildings allowed in seismic regions?
Rod and cable tension-only bracing is common in low categories. In SDC D and above, ASCE 7 and AISC 341 restrict tension-only systems; ordinary concentrically braced frames with rods are allowed only within specific limits, and special concentrically braced frames cannot be tension-only.
What changes in the connections of a seismic metal building?
End-plate moment connections must meet the requirements of the system, bolted bracing connections must develop the required brace strength, and column bases must be designed for the forces the frame can deliver.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- Seismic steel structuresSDC D to F framing we fabricate for US jobs
- Seismic regionsWhere seismic design governs in the US
- California seismic designThe everyday AISC 341 market
- Accredited testing labsILAC ISO/IEC 17025 testing on every project
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors