AISC 341 seismic steel

Seismic steel for industrial plants, pipe racks and nonbuilding structures

Pipe racks, equipment structures, conveyor galleries and process buildings are not ordinary buildings, but many of them are still designed to AISC 341. This article explains how ASCE 7 Chapter 15 and AISC 341 work together for industrial steel.

· updated November 30, 2026 · 7 min read · World Steel USA engineering team

An industrial plant is a collection of very different structures: a process building, a pipe rack that runs across the site, equipment frames for reactors and heat exchangers, conveyor galleries, silo supports, stacks and platforms. Some of them are buildings in the code sense; many are nonbuilding structures. In seismic regions, a large share of them are still designed to the AISC 341 provisions. This article explains how ASCE 7 and AISC 341 divide the work, and what an industrial steel package needs in a seismic region.

Buildings, nonbuilding structures and "other structures"

ASCE 7 splits structures into two families for seismic design:

  • Buildings, designed under ASCE 7 Chapter 12 with the systems and coefficients of Table 12.2-1.
  • Nonbuilding structures, designed under ASCE 7 Chapter 15. Within this family, ASCE 7 separates nonbuilding structures similar to buildings, such as pipe racks, steel storage racks, electrical transmission structures and equipment support frames, from nonbuilding structures not similar to buildings, such as tanks, silos, stacks and cooling towers.

AISC 341 Section A1 applies the provisions to the seismic force-resisting systems of buildings and of other structures, which it defines as structures designed, fabricated and erected in a manner similar to buildings, with building-like vertical and lateral force-resisting elements. A pipe rack with braced frames and moment frames is exactly that kind of structure.

ASCE 7 Table 15.4-1 lists seismic coefficients for nonbuilding structures similar to buildings. For many systems, it offers a choice:

  • Use the same systems and R values as buildings, such as special concentrically braced frames with R = 6 or special moment frames with R = 8, with AISC 341 detailing for the matching system.
  • Use lower R values with relaxed detailing, often with height limits that are less restrictive than for buildings, for systems such as ordinary braced frames and ordinary moment frames, and in some cases for systems with no seismic detailing at all.

That flexibility is one of the main design decisions in an industrial plant. A pipe rack in SDC D can be designed with a lower R and simpler connections, at the cost of higher forces, or with a higher R and AISC 341 detailing, at the cost of capacity-designed connections and inspection. As in buildings, the answer depends on whether seismic or other loads govern, on the rack's height and mass, and on how much detailing the fabricator handles routinely.

Pipe racks

Pipe racks are the backbone of a process plant: long frames, often several tiers high, carrying piping, cable trays and sometimes air coolers on top. Typical seismic design features:

  • Transverse moment frames, often ordinary moment frames under Section E1 of AISC 341, or intermediate frames where required, so that piping can pass through without bracing.
  • Longitudinal braced bays at intervals, usually ordinary or special concentrically braced frames under Sections F1 and F2, with longitudinal struts that act as collectors.
  • Heavy and variable mass, because operating piping, contents and air coolers can dominate the seismic weight.
  • Thermal and anchor loads from piping that combine with seismic forces.

The detailing follows the system: OMF connections under Section E1.6, brace connections designed for the expected brace strength in SCBF, and protected zones where the system requires them. Piping supports and clips must not be welded into protected zones, which is easy to forget when piping designers add supports late.

Our pipe racks page describes how World Steel fabricates and ships rack modules.

Equipment structures and process buildings

Equipment structures support reactors, drums, exchangers and compressors on multi-level steel frames. They often combine:

  • Braced frames for stiffness, important for vibrating equipment.
  • Large concentrated masses, sometimes several hundred tonnes on one level, which ASCE 7 requires to be modeled realistically.
  • Openings for maintenance access and equipment removal, which limit where braces can go.

Process buildings with cranes and heavy floors are often designed as buildings under ASCE 7 Chapter 12, using AISC 341 systems. The mill building seismic article in our AIST TR-13 series covers crane mass and the nonbuilding route for steel mills.

Conveyor galleries, silos and stacks

Conveyor galleries and transfer towers in mining, cement, grain and bulk handling plants combine long trusses and tall towers. The towers are usually braced frames designed to AISC 341 where the chosen R value requires it, and the gallery supports must accommodate differential movement between towers. Silos, tanks and stacks are nonbuilding structures not similar to buildings, designed under ASCE 7 Chapter 15 and their own industry standards, but their steel support frames and skirts often follow AISC 341 or AISC 360 rules for the support structure.

Importance and function after the earthquake

Many industrial structures carry a higher importance factor because of what they contain or what they do: hazardous materials, fuel, power generation, water treatment or emergency services. ASCE 7 assigns Risk Category III or IV accordingly, and plant owners often add their own requirement that critical systems stay functional. That leads to stiffer systems, more braced bays, and supplemental inspection of critical connections.

Materials, coatings and fireproofing

Industrial steel in coastal and chemical environments is often hot-dip galvanized or protected by a high-performance paint system chosen for ISO 12944 C4, C5 or CX. Petrochemical plants add fireproofing: cementitious or intumescent systems on structural steel to resist hydrocarbon fires. Both interact with seismic detailing:

  • Galvanized faying surfaces in slip-critical joints must be prepared to achieve the specified slip class.
  • Fireproofing must be applied around protected zones and connections without attachments welded into them.
  • Bolted field connections are preferred for galvanized and fireproofed steel, to avoid field welding through coatings.

Modular construction

Industrial projects increasingly use modules: pipe rack modules, equipment modules and process modules built off site, shipped complete and set on foundations. Seismic design applies to the module in its final position, and also to its transport and lifting. Module frames are often braced and bolted, designed to AISC 341 where the final R value requires it. Our process modules page explains how World Steel fabricates turnkey modules.

Anchorage, bases and foundations

Industrial structures are often tall, narrow and heavy at the top, which makes overturning and anchorage central to their seismic design. Equipment structures and pipe rack frames deliver large uplift and shear to anchor rods, and ASCE 7 requires anchorage of nonbuilding structures to be designed for amplified forces where the anchor behavior is not ductile. Section D2.6 of AISC 341 applies to column bases in the seismic force-resisting system, so base plates, anchor rods and shear lugs are designed for the forces the frame can deliver.

In practice, that means thick base plates, large anchor rod groups, shear lugs or embedded plates, and close coordination with the foundation engineer and the civil contractor. Anchor rod layouts are among the first drawings a plant project needs, often weeks before the steel itself, because foundations are poured early. A fabricator that issues anchor rod plans and supplies anchor rods and templates ahead of the main steel keeps the civil works moving.

Brownfield plants and additions

Many industrial projects are additions to operating plants: a new process unit beside an old one, a rack extension, an equipment platform added to an existing structure. Old structures were often designed to earlier codes, with lower seismic forces and no AISC 341 detailing. When new steel connects to old, the Engineer of Record has to decide whether the addition is structurally independent, with its own lateral system and a seismic gap, or whether the existing structure must be evaluated and possibly strengthened under the existing building provisions and AISC 342.

For the fabricator, brownfield work means field verification of existing dimensions, connections designed for field drilling or bolting rather than welding near operating equipment, and packages split into small lifts that fit around live process lines and shutdown windows.

Proof from heavy industrial projects

World Steel's largest projects are industrial. For the Long Son petrochemical complex in southern Vietnam, one of the largest petrochemical projects in Southeast Asia, we fabricated about 2,000 tonnes of structural steel over more than 56,000 m², including steel protected with intumescent and sprayed fire-resistive systems. The Long Son project page shows the structures and photos. For the Sunpro Steel mill, we fabricated 5,000 tonnes of mill buildings, crane runway girders and heavy built-up columns, described on our Sunpro Steel mill page.

Our plant welds built-up box and cruciform columns, cuts and drills plate up to 100 mm thick on laser machines, galvanizes or paints with systems from Jotun, PPG, Carboline, Hempel, Nippon and International Paint, and runs its quality system under IAS AC472 accreditation since 2019 and ISO 3834-2 certification from Bureau Veritas.

A checklist for industrial seismic steel

  • Classify each structure: building, nonbuilding structure similar to buildings, or not similar to buildings.
  • Choose the R value and system for each, and note where AISC 341 detailing follows.
  • Model equipment and operating mass realistically, including piping contents.
  • Coordinate piping supports, cable tray supports and fireproofing with protected zones.
  • Plan modularization, transport and lifting with the seismic design.

How World Steel supports industrial projects

World Steel designs and fabricates structural steel for US contractors in its own plant in Vietnam, the first and only IAS AC472 accredited fabricator in the country. For industrial plants we design to AISC 360 and AISC 341-22 with ASCE 7 Chapter 12 or Chapter 15 as applicable, and prepare the calculation report and shop drawings at no extra cost.

Welders and procedures are qualified to AWS D1.8 where demand critical welds occur, materials are tested at ILAC-accredited laboratories, and every piece can be tracked in PEB Studio. The Engineer of Record approves the design and the US contractor, our customer, carries out the site work. The next article moves to mid-rise office and residential buildings.

Quick answers

What is a nonbuilding structure?

A structure that is not a building but must still resist seismic loads, such as pipe racks, steel storage racks, tanks, silos, stacks, cooling towers, conveyor supports and equipment frames. ASCE 7 Chapter 15 sets their seismic design.

Does AISC 341 apply to pipe racks?

When ASCE 7 Table 15.4-1 assigns the rack an R value that corresponds to an AISC 341 system, such as an ordinary or special braced frame or moment frame with higher R, the steel must follow the matching AISC 341 section. Racks designed with the lower R values for systems not detailed for seismic resistance follow AISC 360 only.

What are building-like nonbuilding structures?

Structures such as pipe racks and equipment structures whose lateral systems look like building frames. AISC 341 Section A1 covers them as other structures designed and fabricated in a manner similar to buildings.

Which loads make industrial steel different?

Heavy and concentrated equipment mass, operating and thermal loads, vibration, blast or impact in some plants, and the need to stay functional after an earthquake when the process is critical.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AISC 341 across the US

Twenty-five in-depth articles on where the Seismic Provisions govern in the United States, what they change for each building type, which design decisions set the tonnage, and how a seismic steel package is bought, fabricated and delivered for a US contractor.

US seismic regionsWhere it governs

The West Coast, Alaska, the islands, the Intermountain West, New Madrid and Charleston.

Design decisionsWhat sets the tonnage

Choosing the system, the gravity frame that must follow it, and piles.

Buying and deliveryFrom order to jobsite

Shop drawings, the approved fabricator, overseas sourcing, lead time and site work.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.