Ask a structural engineer what decides the cost of a steel building in a seismic region, and the answer will start with the seismic system: the moment frames, braced frames or walls that resist earthquake forces. The system sets the design forces, the drift, the member sizes, the connection work, the welding and the inspection. It also shapes the architecture, because braces and walls take space. The AISC 341 provisions define the steel systems and their detailing; ASCE 7 gives their R values, height limits and permitted categories. This article compares the main options on the factors that matter, so owners, engineers and contractors can have the conversation early.
The options at a glance
ASCE 7 Table 12.2-1 lists the systems with their response modification coefficient R, overstrength factor Ω0 and deflection amplification Cd. The main steel systems in AISC 341-22 are:
- Ordinary moment frame (OMF), Section E1: R = 3.5. Limited in SDC D and above.
- Intermediate moment frame (IMF), Section E2: R = 4.5. Limited in SDC D and above.
- Special moment frame (SMF), Section E3: R = 8, Cd = 5.5. No height limit.
- Special truss moment frame (STMF), Section E4: R = 7.
- Ordinary concentrically braced frame (OCBF), Section F1: R = 3.25.
- Special concentrically braced frame (SCBF), Section F2: R = 6.
- Eccentrically braced frame (EBF), Section F3: R = 8 with moment-resisting link connections.
- Buckling-restrained braced frame (BRBF), Section F4: R = 8.
- Special plate shear wall (SPSW), Section F5: R = 7.
- Composite systems, Chapters G and H, including composite special moment frames and composite plate shear walls.
- Dual systems, combining a special or intermediate moment frame with braced frames or walls.
Higher R means lower design forces, but more demanding detailing.
Height limits and permitted categories
In SDC D, E and F, ASCE 7 limits several systems:
- SCBF, EBF and BRBF are limited to 49 m (160 ft) in SDC D and E and 30 m (100 ft) in SDC F, unless they are part of a dual system or the ASCE 7 exceptions for taller buildings apply.
- SPSW has similar limits.
- SMF has no height limit in any category.
- OMF, IMF and OCBF are heavily restricted in SDC D, E and F, permitted mainly in light single-storey buildings within the ASCE 7 exceptions.
For tall buildings, the limits push toward SMF, dual systems or core walls. For low and mid-rise buildings, the full menu is usually available.
Drift and stiffness
ASCE 7 limits story drift, typically to 2.0 or 2.5 percent of the storey height for ordinary buildings and less for Risk Category III and IV. Calculated drift is the elastic drift multiplied by Cd, divided by the importance factor.
- Braced frames are stiff. Drift rarely governs SCBF or BRBF members in low and mid-rise buildings.
- EBFs are stiff too, though less than concentric braces.
- Moment frames are flexible. SMF members are often sized for drift, not strength, which adds tonnage beyond what strength alone needs.
That is the main reason braced systems usually weigh less than moment frames for the same building.
Steel tonnage and connection work
The steel in a seismic system has two parts: the members and the connections. Rough patterns:
- SMF: heavy beams and columns, sized for drift and the strong-column weak-beam ratio of Section E3.4a; prequalified connections under AISC 358 or tested under Chapter K; demand critical welds; panel zones and continuity plates.
- SCBF: lighter members; brace connections designed for the expected brace strength in tension and compression; gusset plates detailed for brace buckling; beams in V-braced frames designed for the unbalanced load after braces buckle.
- BRBF: braces supplied as proprietary tested assemblies; connections designed for the adjusted brace strength, usually smaller than for SCBF; beams in V-braced frames designed for the imbalance between tension and compression strengths.
- EBF: link beams designed to yield in shear or flexure; link stiffeners and bracing; braces and columns designed for the forces from the yielded and strain-hardened link.
- SPSW: thin web plates yielding in tension fields; heavy boundary columns and beams designed for the web forces.
Columns in every system are designed for forces from the yielding elements, limited by the system, under the capacity-design rules of each section, with splices and bases under Sections D2.5 and D2.6.
Architecture and services
- Moment frames keep floors and façades open, which offices, retail and parking value.
- Concentric braces occupy wall lines; chevron and X patterns block doors and windows.
- EBFs allow doors and corridors through braced bays.
- BRBs have compact connections and fit well in walls.
- Plate walls take wall space but are thin.
Services matter too. Protected zones in all systems forbid attachments without the Engineer of Record's approval, so ducts and pipes near moment frame beam ends or brace connections need coordination.
Procurement and schedule
- SMF connections require more shop welding and inspection, and sometimes field welding, unless bolted prequalified connections are used. AISC 358 also lists proprietary connections, which require licensing. Our AISC 358 series explains how to choose a prequalified moment connection.
- SCBF braces are rolled HSS or wide-flange sections, available from stock; gusset plates are cut in the shop.
- BRBs are proprietary assemblies supplied by specialist manufacturers, qualified by tests under Section K3. Their lead time and coordination with the steel fabricator must be planned early.
- EBF links need careful fabrication, with stiffeners and lateral bracing, but use standard shapes.
Foundations: the hidden cost of each system
The seismic system also decides the foundations. Braced frames concentrate overturning at a few columns, producing large uplift and compression at their bases; moment frames spread it across more columns but with large base moments where columns are fixed. On poor soils, the foundation under a braced frame, with its piles, grade beams or mat, can cost more than the frame itself.
Section D2.6 of AISC 341 requires column bases in the seismic force-resisting system to be designed for the forces the system can deliver, which ties foundation cost to the strength of the yielding elements, not just the analysis forces. Higher R values reduce design forces, but capacity design brings expected brace or beam strengths back into the base design. A fair comparison of systems includes the foundations, the anchor rods and the base plates, not only the steel above them.
Redundancy and the number of frames
ASCE 7 applies a redundancy factor, ρ, of 1.0 or 1.3 to seismic forces in SDC D, E and F, depending on whether losing one brace or one moment connection would reduce the building's strength too much. Buildings with only a few lateral frames per line usually carry ρ = 1.3, which raises design forces by 30 percent. Adding frames to reach ρ = 1.0 often costs less than designing every element for the higher force. The decision interacts with architecture: more frames mean more walls or bays taken by braces, but smaller members and connections in each.
Mixing systems
ASCE 7 lets the engineer use different systems in each direction, each with its own R value and detailing. Many buildings use moment frames in one direction and braced frames in the other. Vertical combinations are also allowed with rules for the transition. Dual systems combine moment frames with braced frames or walls to gain both stiffness and redundancy, which is useful in taller buildings.
A quick decision guide
- Low-rise industrial or warehouse, SDC D: SCBF or OCBF within limits; moment frames where doors and openings demand.
- Mid-rise office or lab, SDC D: SMF perimeter with braced cores, or BRBF throughout.
- Hospital or essential facility: BRBF or SCBF for stiffness; SMF in dual systems.
- Tall building: SMF, dual systems or core walls, often with nonlinear verification under Chapter C and Appendix 1.
- Parking structure: SMF where sides must stay open; braced frames at cores.
- SDC B or C: compare R = 3 with an AISC 341 system, as covered in the moderate-region article.
Proof that one fabricator can deliver every system
A seismic system decision should not be limited by what the fabricator can make. World Steel's plant fabricates all of these systems' members and connections: rolled and built-up beams and columns, welded box columns and cruciform columns for moment frames, gusset plates and brace connections for concentric and eccentric braces, link beams with stiffeners, and BRB frame steel with connections designed to the brace manufacturer's test data. Our laser machines cut and drill plate up to 100 mm thick, and our welders and procedures are qualified to AWS D1.8 for demand critical welds.
At scale, we have delivered single projects of 5,000 tonnes (Sunpro Steel mill), 2,500 tonnes (CPV Food) and 2,000 tonnes (Long Son petrochemical complex and M&D warehouse), and the seismic-designed FPI Barracks on Guam in 60 days. Our engineers prepare concept comparisons at proposal stage, so the system choice is made with real tonnage and real connection counts.
A checklist for the system decision
- Confirm the Seismic Design Category, Risk Category and height.
- List the systems permitted by ASCE 7 for that category and height.
- Compare two or three options on steel tonnage, connection count, drift and architecture.
- Check procurement: BRB suppliers, proprietary connection licenses, built-up columns.
- Decide early, before architectural layouts lock wall and opening positions.
How World Steel supports the decision
World Steel designs and fabricates structural steel for US contractors in its own plant in Vietnam, the first and only IAS AC472 accredited fabricator in the country. We design to AISC 360 and AISC 341-22, use AISC 358 connections where moment frames are chosen, compare system options at proposal stage, and prepare the calculation report and shop drawings at no extra cost.
Every piece can be tracked in PEB Studio. The Engineer of Record approves the design and the US contractor, our customer, carries out the site work. The next article looks at the part of the building that is not in the seismic system but must still follow it: the gravity frame.
Quick answers
Which seismic system uses the least steel?
For most buildings, braced frames use less steel than moment frames, because braces are stiff and drift is easier to control. Buckling-restrained braced frames often give the lightest system where their braces are procured economically.
Which system gives the most open floor plan?
Special moment frames, which have no braces. Eccentrically braced frames allow openings in braced bays, and placing braced frames around cores also keeps most of the floor open.
Are there height limits for steel seismic systems?
Yes, in SDC D, E and F. ASCE 7 limits SCBF, EBF and BRBF to 49 m (160 ft) in SDC D and E and 30 m (100 ft) in SDC F unless they are part of a dual system or the exceptions apply. Special moment frames have no height limit.
Can different systems be used in each direction?
Yes. ASCE 7 allows different systems in the two orthogonal directions, each with its own R value, as long as each direction is designed for its own system.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- Seismic steel structuresSDC D to F framing we fabricate for US jobs
- Seismic regionsWhere seismic design governs in the US
- California seismic designThe everyday AISC 341 market
- Accredited testing labsILAC ISO/IEC 17025 testing on every project
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors