Earthquake forces start as inertia. Every kilogram of roof, floor, wall and equipment wants to stay still while the ground moves, and that inertia has to be collected and carried down to the foundation through a continuous load path. Frames get the attention, but much of the path lies in the horizontal elements: diaphragms, chords and collectors. AISC 341-22 Chapter B, General Design Requirements, sets how that path is designed, how the overstrength factor is applied and which elements must stay elastic while the frames yield. This article explains Chapter B and its clarified Section B5.
What Chapter B contains
Chapter B is short but it frames everything that follows:
- Section B1, General Seismic Design Requirements, ties the required strength and the system type to ASCE 7.
- Section B2, Loads and Load Combinations, applies the ASCE 7 combinations, including those with overstrength, and introduces the capacity-limited seismic load.
- Section B3, Design Basis, sets how required strength and available strength are determined, by LRFD or ASD.
- Section B4, System Type, requires the system to be one of those designated in ASCE 7 and detailed to the matching chapter of AISC 341.
- Section B5, Diaphragms, Chords and Collectors, covers the horizontal load path, including truss diaphragms.
Three levels of seismic force
A seismic steel design works with three different levels of earthquake force, and confusing them is the most common source of error.
The design seismic force
ASCE 7 divides the elastic force by the response modification coefficient R. For a special moment frame, R is 8, so the frame is designed for about one eighth of the elastic force. This design seismic load effect, E, is what the analysis model carries and what most members are sized for.
The overstrength seismic load
The real frame will be much stronger than that design force: members are larger than required, steel is stronger than its grade, and redundant load paths share the load. ASCE 7 estimates that reserve with the overstrength factor, Ω0, given for each system: for example 3 for special moment frames, 2 for special concentrically braced frames, 2.5 for buckling-restrained braced frames in many configurations. The overstrength seismic load, Emh = Ω0 QE, is used for elements whose failure would interrupt the load path and that must not yield: collectors, certain column checks, transfer elements and their connections.
The capacity-limited seismic load
AISC 341 adds a third level that is often more precise: the capacity-limited horizontal seismic load effect, Ecl. It is the force an element receives when the members designed to yield next to it reach their expected strength, based on Ry Fy and strain hardening. Section B2 allows Ecl to replace the overstrength load where the standard permits, which is common for brace connections, link-adjacent beams and columns in braced frames. When the yielding mechanism is clear, Ecl is a real upper bound and often smaller than Ω0 QE.
Load combinations
Section B2 points to the ASCE 7 combinations: the basic strength design combinations with E, and the combinations with overstrength found in ASCE 7 Section 2.3.6 and 12.4.3. In practice, the steel designer runs three families:
- Basic combinations with the design seismic load, for most members of the seismic force-resisting system (SFRS).
- Overstrength combinations, for collectors, columns in some systems and elements AISC 341 or ASCE 7 designate.
- Capacity-design checks, where the force comes from the expected strength of the yielding member rather than from the analysis.
The vertical seismic effect, Ev, which adds or subtracts a fraction of the dead load, is included in all of them.
Section B5: diaphragms, chords and collectors
The 2022 edition clarified Section B5 so that the horizontal load path has the same clarity as the frames. Four elements are involved.
Diaphragms
A diaphragm is the horizontal element, floor slab, steel deck, or braced roof plane, that collects inertia forces and spans between vertical frames like a deep horizontal beam. In steel buildings it can be a concrete slab on metal deck, a bare steel deck designed to AISI S310, or a horizontal truss of rods and angles in a metal building roof. Diaphragm design forces come from ASCE 7 Section 12.10; ASCE 7-22 also offers an alternative diaphragm design method in Section 12.10.3 that accounts for diaphragm flexibility and ductility.
Chords
Chords are the flanges of that deep horizontal beam. They run along the diaphragm edges, perpendicular to the load, and carry tension and compression from diaphragm bending. In a steel building the perimeter beams, edge angles or eave struts often serve as chords, and their splices must carry the chord force.
Collectors
Collectors, also called drag struts, gather diaphragm shear and deliver it to the vertical frames, which rarely run the full width of the building. A braced bay in the middle of a long wall, for example, needs a collector beam on each side to drag the roof shear into it. Because a collector failure would cut the load path just when the frame is yielding, ASCE 7 Section 12.10.2.1 requires collectors and their connections in Seismic Design Category C and above to be designed with the overstrength load, and AISC 341 Section B5 adds the steel-specific rules.
Truss diaphragms
Long-span roofs often use a horizontal steel truss instead of deck as the diaphragm. AISC 341 Section B5 covers truss diaphragms that form part of the load path, setting how their members and connections are designed so the truss either stays elastic under the amplified force or, where the standard allows, behaves in a controlled ductile way. Connections of truss diaphragm members are a frequent weak point and get specific attention.
Why collectors and connections fail in earthquakes
Post-earthquake surveys repeatedly find damage not in well-detailed frames but in the elements around them: collector connections that pulled out, chord splices that opened and diaphragm-to-frame attachments that were never designed for the real force. The common thread is an element sized for the design force E in a building whose frames delivered several times that. Chapter B is written to close that gap.
What it means on a typical steel building
- Warehouses and metal buildings. Roof rod and angle bracing forms the diaphragm, eave struts act as chords and collectors, and wall bracing or portal frames are the vertical system. Collector connections at the braced bays are designed for overstrength. See roof bracing and eave struts.
- Multi-storey buildings. A concrete slab on metal deck forms each floor diaphragm, with steel collector beams dragging floor shear into moment or braced frames. Shear studs and the slab-to-beam transfer are part of the path. See composite floor support steel and metal decking.
- Industrial structures. Platforms, pipe racks and equipment floors often use horizontal bracing as truss diaphragms, with heavy equipment loads raising the seismic mass. See industrial floor support structures.
A worked example: the collector at a braced bay
Picture a single-storey warehouse 120 m (394 ft) long with one special concentrically braced bay in the middle of each long wall. The roof diaphragm collects seismic inertia along the full length of the wall, but only the braced bay can resist it. The eave strut on each side of the bay therefore works as a collector: it gathers roof shear along its length and delivers the accumulated force into the braced bay.
That collector force grows from zero at the end wall to its maximum at the bay. Because the building is in Seismic Design Category D, the collector, its splices and its connection to the braced frame are designed for the overstrength load, with Ω0 for the bracing system applied to the collector force. The eave strut that would be a light member under wind alone may become a heavier section near the bay, with a bolted splice and a gusset designed for the amplified force. The braced frame itself is then checked to receive that force. Without the collector design, the roof would tear away from the frame long before the braces did their work.
A checklist for reviewing the load path
Before seismic steel drawings are approved, the following questions are worth asking:
- Is every diaphragm identified, with its type, deck, slab or truss, and its design force?
- Are chords identified, and are their splices designed for the chord force?
- Are collectors identified on the drawings, and are they and their connections designed with the overstrength or capacity-limited load?
- Does every collector actually reach a vertical frame, with a connection designed for its force?
- Are openings, re-entrant corners and offsets in the diaphragm accounted for?
- Are truss diaphragm members and connections designed under Section B5?
How World Steel designs the seismic load path
World Steel designs and fabricates the complete steel structure, including the diaphragm bracing, chords, collectors and their connections, in its IAS AC472-accredited plant in Vietnam. Our engineers run the ASCE 7 basic, overstrength and capacity-design combinations, identify collectors and chords in the model and on the shop drawings, and design their connections for the forces the Engineer of Record approves. Calculations are presented in a design report the Engineer of Record can review line by line; see our design report explainer and structural analysis.
On metal buildings we supply the full secondary system that forms the diaphragm, from purlins and rod bracing to eave struts, and on multi-storey work the collector beams, embed plates and stud layouts that tie the slab into the frames. The US contractor installs the deck and pours the slab as part of its site scope.
The next article looks at analysis: what Chapter C requires and how the new Appendix 1 brings nonlinear response history analysis into AISC 341.
Quick answers
What is the overstrength factor Ω0?
Ω0 is the ASCE 7 factor that estimates how much stronger a seismic system really is than its design force. Multiplying the earthquake effect by Ω0 gives the overstrength seismic load, used for elements that must stay elastic, such as collectors.
What is the capacity-limited seismic load?
It is the AISC 341 term for the force an element receives when the yielding members next to it reach their expected strength. It may be used instead of the overstrength load where it is smaller and can be calculated reliably.
Are collectors part of the seismic force-resisting system?
Collectors deliver diaphragm forces to the vertical frames. In Seismic Design Category C and above, ASCE 7 requires collectors and their connections to be designed with the overstrength load, and AISC 341 Section B5 covers their design.
Does a metal building roof act as a diaphragm?
Yes. Roof deck or rod and angle bracing carries seismic forces to the wall bracing or frames. Eave struts and other members often act as collectors and are designed for the forces the Engineer of Record assigns.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- Seismic steel structuresSDC D to F framing we fabricate for US jobs
- Seismic regionsWhere seismic design governs in the US
- California seismic designThe everyday AISC 341 market
- Accredited testing labsILAC ISO/IEC 17025 testing on every project
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors