Design step: approval drawings

Approval drawings that close comments instead of collecting them

After the contract is signed, the anchor rod plan, column reactions, framing plans and elevations are issued for approval with the Design Report. Every comment from your team is logged, answered in writing, clouded on the sheet and reissued under a new revision until the set is approved.

Sheet by sheet

What an approval set contains

A typical World Steel approval set for a US steel building. Each sheet is there for a reader on your team, and the Design Report with the calculations travels with it.

SheetWhat you check on itWho checks it
Cover sheet and general notes Design criteria quoted from the design basis, material grades, bolt and coating specifications, and the list of sheets in this revision. Engineer of Record
Anchor rod plan Rod diameters, grades and projections, rod patterns at each column and their dimensions to the gridlines. Foundation engineer and contractor
Column reaction tables Unfactored reactions by load case at every column base, vertical, horizontal and uplift, in kN with kips alongside. Foundation engineer
Roof framing plan Frame lines, purlin spacing, roof bracing bays, openings for rooftop units and skylights. Engineer of Record and MEP engineers
Frame cross-sections Member depths, haunches, clear heights under the rafter and at the eave, and the connection types at knees and ridge. Architect and Engineer of Record
Sidewall and endwall elevations Girt layout, bracing bays, door and window openings with their framing, and wainscot or base details. Architect
Bracing and wind column details Rod or portal bracing, wind columns and how they tie into the roof bracing and the foundations. Engineer of Record
Crane, mezzanine and canopy sections Runway elevations and brackets, mezzanine framing and canopy connections, where they are part of the job. Engineer of Record and equipment suppliers
Envelope layout and typical details Sheeting direction, trim and gutter profiles, flashings and closures, when the envelope is in our scope. Architect and roofing consultant

Anchor rods first

Why the anchor rod plan leaves before everything else

On a steel job shipped from overseas, the foundations are designed, dug and poured while the steel is being fabricated. If the anchor rod plan waits for the whole set to be approved, either the concrete waits for the drawings or the steel waits for the concrete.

So the anchor rod plan and the reaction tables are the first sheets we push to approval. Reactions are given unfactored, by load case, in kN with kips alongside, so your foundation engineer can build their own combinations. Rod grade, diameter and projection are fixed here and never change quietly afterwards.

The comment register

How a comment travels from your stamp to a closed item

Logged

Each comment is entered against its sheet and revision, in the reviewer’s own words.

Answered

Our engineer answers in writing: accepted, clarified with a reason, or raised as a change with its effect on steel and schedule.

Clouded

The change is drawn, clouded on the sheet and marked with a delta, so nobody hunts for what moved.

Reissued

The sheet goes out under the next revision letter, with the register attached.

Closed

Once your reviewer accepts the answer, the item is closed and stays on record.

Mark-ups we see on US jobs

Six comments that come back most often

Most changes at approval have nothing to do with the structure itself. They come from other trades settling their own designs, and the drawings have to follow.

Overhead door sizes change

A dock door grows by 600 mm (2 ft) to suit a different trailer, and the framed opening, girts and bracing bay have to move with it.

A rooftop unit is added or moved

The mechanical engineer settles the unit after approval drawings go out. Purlins, framed openings and sometimes the rafter are rechecked for its weight.

Gutters and downspouts relocate

Downspout positions move to suit the site drainage, and they must miss columns, bracing and doors.

Clear height is raised

Racking or a crane needs more height under the rafter. The frames, wall bracing and sometimes the foundations change.

A masonry or concrete wainscot is added

Girts are lowered or removed at the base and the drift limit is tightened for the brittle wall below.

Bracing clashes with an opening

An X-braced bay sits where the owner wants a door. A portal frame or a different bay solves it without losing the load path.

What an approval releases

One approved revision, four things start moving

Foundation design and anchor rods

The approved anchor rod plan and reactions let your foundation engineer finish the footings and your contractor set rods while the steel is still in production.

Your permit set

With the Design Report, the approved drawings become the structural steel part of your permit package, once your Engineer of Record has reviewed and sealed them.

Tekla modeling

The approved revision is what our detailers model in Tekla Structures. Nothing is detailed from a superseded sheet.

Plate and coil orders

Material is ordered against the approved design and logged by heat number when it reaches the plant.

Approved, approved as noted, revise and resubmit: what each review stamp means on our side is set out in shop drawing coordination.

Who owns this step

Clear lines between our scope and yours

World Steel designs and fabricates the steel structure. Approval, the PE seal, the permit and the erection stay with the US contractor and the Engineer of Record they appoint.

World Steel

Designs, details and fabricates the steel in Vietnam

Issues the approval set and the Design Report, logs every comment, answers it in writing, clouds the change and reissues the set under a new revision.

Your Engineer of Record

Reviews, approves and seals for your permit

Reviews the set against the design basis and the rest of the design, returns one consolidated mark-up, and approves the final revision before sealing it for the permit.

The US contractor, our customer

Submits, builds the foundations and erects

Coordinates the architect, foundation engineer and trades, sends their comments in one round, and releases the anchor rod plan to the site.

Questions from US contractors

Questions about approval drawings

Who approves the approval drawings?

Your Engineer of Record, with your architect and the rest of your design team commenting through the US contractor. World Steel prepares the drawings and the calculations; the approval and the PE seal stay on your side.

Can we approve the anchor rod plan before the rest of the set?

Yes, and we recommend it. Foundations are designed and poured while steel is in production, so an early approved anchor rod plan keeps the site and the plant moving together.

How do you keep track of comments?

Every comment goes into a register with the sheet, the comment, our answer and its status. The answer is clouded on the sheet and the revision letter changes, so your team can see exactly what moved.

Can you send DWG files as well as PDFs?

Yes. The approval set is issued as PDF for review and can be exported to DWG for teams that overlay it on their own drawings.

What if the column reactions change after the foundations are designed?

We tell you before reissuing, show the old and new values side by side, and flag whether the change is within or outside what the foundation design already covers.

When does fabrication start?

Only after the set is approved and the shop drawings that follow are released for fabrication in writing. No steel is cut against an unapproved revision.