Sheet by sheet
What an approval set contains
A typical World Steel approval set for a US steel building. Each sheet is there for a reader on your team, and the Design Report with the calculations travels with it.
Anchor rods first
Why the anchor rod plan leaves before everything else
On a steel job shipped from overseas, the foundations are designed, dug and poured while the steel is being fabricated. If the anchor rod plan waits for the whole set to be approved, either the concrete waits for the drawings or the steel waits for the concrete.
So the anchor rod plan and the reaction tables are the first sheets we push to approval. Reactions are given unfactored, by load case, in kN with kips alongside, so your foundation engineer can build their own combinations. Rod grade, diameter and projection are fixed here and never change quietly afterwards.
Photo
The comment register
How a comment travels from your stamp to a closed item
Logged
Each comment is entered against its sheet and revision, in the reviewer’s own words.
Answered
Our engineer answers in writing: accepted, clarified with a reason, or raised as a change with its effect on steel and schedule.
Clouded
The change is drawn, clouded on the sheet and marked with a delta, so nobody hunts for what moved.
Reissued
The sheet goes out under the next revision letter, with the register attached.
Closed
Once your reviewer accepts the answer, the item is closed and stays on record.
Mark-ups we see on US jobs
Six comments that come back most often
Most changes at approval have nothing to do with the structure itself. They come from other trades settling their own designs, and the drawings have to follow.
A dock door grows by 600 mm (2 ft) to suit a different trailer, and the framed opening, girts and bracing bay have to move with it.
The mechanical engineer settles the unit after approval drawings go out. Purlins, framed openings and sometimes the rafter are rechecked for its weight.
Downspout positions move to suit the site drainage, and they must miss columns, bracing and doors.
Racking or a crane needs more height under the rafter. The frames, wall bracing and sometimes the foundations change.
Girts are lowered or removed at the base and the drift limit is tightened for the brittle wall below.
An X-braced bay sits where the owner wants a door. A portal frame or a different bay solves it without losing the load path.
What an approval releases
One approved revision, four things start moving
Foundation design and anchor rods
The approved anchor rod plan and reactions let your foundation engineer finish the footings and your contractor set rods while the steel is still in production.
Your permit set
With the Design Report, the approved drawings become the structural steel part of your permit package, once your Engineer of Record has reviewed and sealed them.
Tekla modeling
The approved revision is what our detailers model in Tekla Structures. Nothing is detailed from a superseded sheet.
Plate and coil orders
Material is ordered against the approved design and logged by heat number when it reaches the plant.
Approved, approved as noted, revise and resubmit: what each review stamp means on our side is set out in shop drawing coordination.
Who owns this step
Clear lines between our scope and yours
World Steel designs and fabricates the steel structure. Approval, the PE seal, the permit and the erection stay with the US contractor and the Engineer of Record they appoint.
World Steel
Designs, details and fabricates the steel in Vietnam
Issues the approval set and the Design Report, logs every comment, answers it in writing, clouds the change and reissues the set under a new revision.
Your Engineer of Record
Reviews, approves and seals for your permit
Reviews the set against the design basis and the rest of the design, returns one consolidated mark-up, and approves the final revision before sealing it for the permit.
The US contractor, our customer
Submits, builds the foundations and erects
Coordinates the architect, foundation engineer and trades, sends their comments in one round, and releases the anchor rod plan to the site.
Questions from US contractors
Questions about approval drawings
Who approves the approval drawings?
Your Engineer of Record, with your architect and the rest of your design team commenting through the US contractor. World Steel prepares the drawings and the calculations; the approval and the PE seal stay on your side.
Can we approve the anchor rod plan before the rest of the set?
Yes, and we recommend it. Foundations are designed and poured while steel is in production, so an early approved anchor rod plan keeps the site and the plant moving together.
How do you keep track of comments?
Every comment goes into a register with the sheet, the comment, our answer and its status. The answer is clouded on the sheet and the revision letter changes, so your team can see exactly what moved.
Can you send DWG files as well as PDFs?
Yes. The approval set is issued as PDF for review and can be exported to DWG for teams that overlay it on their own drawings.
What if the column reactions change after the foundations are designed?
We tell you before reissuing, show the old and new values side by side, and flag whether the change is within or outside what the foundation design already covers.
When does fabrication start?
Only after the set is approved and the shop drawings that follow are released for fabrication in writing. No steel is cut against an unapproved revision.