Columns are the spine of a seismic steel frame. In most systems they are meant to stay elastic while beams, braces or links yield around them, because a column that yields or fails can bring down every floor above it. Two places along a column carry special risk. The splice, where one column shaft is joined to the next, usually every two or three storeys, interrupts the steel exactly where the building relies on continuity. The base, where the steel meets the concrete foundation, has to pass the entire seismic shear, and in moment frames a large moment, into a different material. AISC 341-22 deals with both in Section D2: seismic column splices in D2.5 and column bases in D2.6. This article explains both.
Why columns get special treatment
Section D1.4 sets the required strength of columns in the seismic force-resisting system (SFRS). Because columns must not fail while the yielding members do their work, their axial strength is checked for the overstrength load, or for the capacity-limited load from the yielding members, in addition to the normal combinations. The system chapters add more: in special moment frames, the strong-column weak-beam rule makes sure hinges form in the beams rather than the columns.
Splices and bases are where that column strength must be carried across a joint, so they inherit the same high demands.
Section D2.5: column splices
Location
AISC 341 requires column splices to be placed away from beam-to-column connections, in the region of the column where bending is lower. In most cases the splice must be at least the lesser of 1.2 m (4 ft) or half the column clear height from the beam flanges. In practice, splices in multi-storey frames are typically placed about 1.2 m (4 ft) above a floor, which also suits erection: the crew can reach the splice from the floor below.
Required strength
The splice must carry the column's required axial strength, including overstrength or capacity-limited forces, and the shear and moment that act at that location. AISC 341 adds minimums so that a splice in a region of low calculated moment is still robust:
- Welded splices using complete-joint-penetration (CJP) groove welds develop the full strength of the smaller column and are the usual choice in demanding systems.
- Partial-joint-penetration (PJP) groove welds, where permitted, must be designed with a large reserve over the required strength, and are not allowed in some systems or under net tension, because the unfused root acts like a crack.
- Bolted splices with flange and web plates are designed to develop the required strengths, using pretensioned bolts and the hole rules of Section D2.2.
For special moment frames, Section E3.6g goes further: the splice must develop at least the expected flexural strength of the smaller column, and its shear strength must match the column's capacity-based demand. The welds are demand critical.
Transitions and details
When the column above is lighter than the one below, the splice must handle the change in flange and web thickness. CJP welds between plates of different thickness are made with a tapered transition, and weld tabs are removed and the ends ground where AWS D1.8 requires. Erection aids, such as splice plates used to hold the column during erection, are placed and removed so they do not leave notches in the column flanges.
Section D2.6: column bases
Column bases transfer the column forces into the foundation. AISC 341 Section D2.6 sets their required strength in three parts.
Axial strength
The required axial strength of a base is at least the axial force the column must carry, including overstrength or capacity-limited forces. In braced frames, that often means large uplift at one end of a braced bay, resisted by anchor rods embedded deep in the foundation.
Shear strength
The required shear strength is set by the seismic system: for example, the horizontal component of the brace force in a braced frame, or the shear corresponding to the column's capacity in a moment frame. Shear is transferred by one of several mechanisms:
- Shear lugs, plates or short sections welded under the base plate and grouted into a pocket in the concrete.
- Embedment, where the column extends into the foundation or a grade beam.
- Anchor rods in shear, with base plate holes and plate washers detailed so all rods engage, often by welding the washers to the base plate after the rods are set.
- Bearing against a concrete curb or slab edge.
Friction between the base plate and grout is generally not relied on to resist seismic shear, because vertical earthquake motion and uplift can reduce the compression that friction depends on.
Flexural strength
Where the base is fixed, as in many moment frames and in the cantilever column systems, the base must resist the column moment. AISC 341 sets the required flexural strength at the lesser of the column's expected plastic moment, with a margin, or the moment the system can deliver. A fixed base for a heavy moment frame column becomes a substantial assembly: thick base plate, stiffeners, large anchor rods and a deep foundation.
Coordination with concrete design
Anchor rods, shear lugs and embedment are designed under ACI 318 Chapter 17 for anchorage to concrete, with the seismic provisions of that chapter. AISC Design Guide 1, Base Connection Design for Steel Structures, gives the steel-side methods. The foundation designer and the steel designer must work from the same forces, and the anchor rod layout must match on both sets of drawings.
New emphasis in 2022: cantilever column bases
AISC 341-22 expanded the provisions for ordinary and special cantilever column systems (OCCS and SCCS) in Chapter E. In these systems, every bit of lateral resistance comes from columns fixed at the base, so the base is the most critical joint in the structure. The 2022 edition sets specific requirements for the shear and flexural strength of these bases to make sure the columns can yield in a ductile way above them. A later article in this series covers cantilever column systems in full.
A worked example: a four-storey special moment frame
Consider a four-storey office building with special moment frames on each face. Storey heights are 4.2 m (13 ft 9 in.) at the ground floor and 3.8 m (12 ft 6 in.) above. The columns are heavy wide-flange shapes at the base, stepping down to a lighter section for the top two storeys.
A natural shipping and erection scheme is a two-storey column tier: one splice, at the third floor. The splice is placed 1.2 m (4 ft) above the third-floor beam flanges, which satisfies the location rule because half the clear height above the third floor, about 1.5 m, is larger. The upper column is lighter, so the CJP groove welds join flanges of different thickness, with a tapered transition on the thicker flange. The welds are demand critical, the weld tabs are removed and ground, and the splice gets ultrasonic testing under Chapter J. Erection plates bolted to the webs hold the upper shaft in place while the field welds are made by the US contractor's welders, or, if the Engineer of Record selects a bolted splice, flange and web splice plates with pretensioned bolts complete it with no field welding.
At the base, each moment frame column is fixed. The base plate is thick and stiffened, the anchor rods are designed for uplift and moment under ACI 318 Chapter 17, and a shear lug under the plate carries the base shear into a grout pocket. The foundation designer works from the same capacity-based forces as the steel designer.
Fabrication and erection: where things go wrong
- Splices too close to the floor beams, moved to suit shipping lengths without checking the location limit.
- PJP welds substituted for CJP in splices where the system does not allow it.
- Weld tabs left on or not ground at CJP splice welds.
- Base plate holes oversized for anchor rod tolerance without plate washers designed for shear.
- Anchor rod layouts that differ between the steel and foundation drawings, discovered only when the column arrives on site.
- Shear lugs omitted or grout pockets not formed.
Checklist for splices and bases
- Is every splice located within the limits of Section D2.5?
- Are splice welds CJP where the system requires, and identified as demand critical?
- Are thickness transitions and weld tab removal shown?
- Is the base shear path defined: lug, embedment, anchor rods or bearing?
- Are anchor rods, washers and hole sizes detailed for the seismic shear and uplift?
- Do anchor rod layouts match the foundation drawings?
How World Steel fabricates seismic splices and bases
World Steel designs and fabricates seismic columns for US projects in its IAS AC472-accredited plant in Vietnam, including heavy welded box columns and cruciform columns for tall moment frames. Splices are located and designed to Section D2.5, and CJP splice welds are made by welders qualified to AWS D1.8, with weld tabs removed and ends ground where required. Where shipping allows, columns are fabricated in multi-storey lengths so splices fall at the right height, and each splice is shown on the shop drawings and erection drawings with its welding or bolting.
Base plates, shear lugs and stiffeners are fabricated with the columns; see base plates. We supply anchor bolts and setting templates for the US contractor to cast into the foundation, and we check our anchor layout against the foundation drawings before release. The Engineer of Record reviews and approves the splice and base design, and the US contractor completes the field splices and grouting as part of its scope.
The next stage of this series moves to the systems themselves, starting with ordinary, intermediate and special truss moment frames in Chapter E.
Quick answers
Where must a column splice be located in a seismic frame?
AISC 341 generally requires column splices to be located away from beam-to-column connections, at least the lesser of 1.2 m (4 ft) or half the column clear height from the beam flanges, so the splice sits in a region of lower moment.
Are column splice welds demand critical?
In moment frames and several other systems, complete-joint-penetration groove welds in column splices are designated demand critical, so they use notch-tough filler metal, follow AWS D1.8 and receive the testing Chapter J requires.
How is base shear transferred to the foundation?
By shear lugs, embedment of the column, bearing against concrete, or anchor rods designed for shear with suitable hole and washer details, designed to ACI 318 and AISC 341. Friction alone is not relied on to resist the seismic shear in most designs.
Does the fabricator supply the anchor rods?
Base plates are fabricated with the columns. Anchor rods and templates are often supplied by the steel fabricator for the US contractor to set in the foundation, as agreed in the contract.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- Seismic steel structuresSDC D to F framing we fabricate for US jobs
- Seismic regionsWhere seismic design governs in the US
- California seismic designThe everyday AISC 341 market
- Accredited testing labsILAC ISO/IEC 17025 testing on every project
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors