A seismic weld is inspected more than once. The fabricator inspects it as part of its own quality system. An independent agency, hired for the owner, inspects it again, and on many projects watches the fabricator's inspectors at work. Ultrasonic testing (UT), magnetic particle testing (MT) and visual inspection are split between them according to a written plan. If either side does not know its tasks, welds get missed or tested twice. AWS D1.8 Clause 7 sets out how that split works and who is qualified to do each part. This article explains seismic weld QC and QA: the Quality Assurance Plan, the inspector qualifications, and the extra checks that seismic frames need beyond normal structural welding.
QC and QA are different jobs
The D1.8 commentary to Clause 7.1 defines the two roles:
- Quality Control (QC) is done by the contractor, which for shop work means the fabricator. It covers inspection and testing of fabrication and erection as AWS D1.1 defines it: personnel control, material control, preheat measurement, monitoring of welding procedures and visual inspection. D1.1 calls this "Contractor's Inspection".
- Quality Assurance (QA) is done by an agency or firm other than the contractor, at the owner's choice and often required by the building code. It monitors how well the contractor runs its QC program, checks that QC tasks are done properly and routinely, and may also perform specific inspection tasks, including NDT. D1.1 calls this "verification inspection".
In US practice, QA on the seismic force-resisting system (SFRS) is usually part of the special inspection required by the International Building Code, carried out by an agency the owner or the Engineer appoints. Our article on special inspection of fabricated steel explains how that works when the shop is outside the United States.
The Quality Assurance Plan
Clause 7.1 says that when the building code or the contract documents require it, the Engineer prepares a Quality Assurance Plan (QAP). The QAP names the specific QC tasks for the contractor and the QA tasks for the QA agency, and each side performs the tasks assigned to it.
Clause 3 defines the QAP as the written description of qualifications, procedures, quality inspections, resources and records used to show that the structure meets the Engineer's quality requirements, the specifications, jurisdictional requirements and the contract documents. The commentary adds that:
- AISC 341 Chapter J sets the minimum QAP requirements for welded SFRS construction
- the requirements may be adjusted for the skill and practices of the parties involved
- the QAP can significantly affect the organization and cost of the work, so it belongs in the contract documents where bidders can see it
Many of the inspections in Clause 7 apply only when the QAP requires them. That makes the QAP the single most important document for a fabricator pricing and planning a seismic job.
A typical split of tasks
AISC 341 Chapter J organizes tasks by stage, before, during and after welding, and assigns each to QC and QA as observe (spot checks on a random basis) or perform (every item). A simplified picture of how this usually looks for Demand Critical welds:
| Stage | Typical QC tasks | Typical QA tasks |
|---|---|---|
| Before welding | WPS available, filler metal certified and controlled, fit-up, backing, access holes | Observe the same items |
| During welding | Preheat and interpass, WPS settings, welder ID, cleaning between passes | Observe welding |
| After welding | Visual inspection of every weld, tab and backing removal, repairs | Visual inspection, UT and MT of Demand Critical welds, k-area MT |
| Records | Welder qualifications, WPSs, filler metal lot data, inspection reports | Review and verify |
The actual split always comes from the project QAP. Our article on the demand critical weld fabrication checklist lists the shop steps in order.
Who may inspect: Clause 7.2
Clause 7.2 sets four groups of qualifications.
QA welding inspectors (7.2.1) must be qualified as one of:
- Welding Inspector (WI) or Senior Welding Inspector (SWI) under AWS B5.1; Associate Welding Inspectors may work under the direct supervision of a WI who is on site and available
- Certified Welding Inspector (CWI) or Senior CWI under AWS QC1; Certified Associate Welding Inspectors may work under the direct supervision of a CWI who is on site and available
- Level 2 or Level 3 Welding Inspector certified by the Canadian Welding Bureau under CSA W178.2; Level 1 inspectors may work under the direct supervision of a Level 2 inspector on site
The commentary adds that the inspector should be familiar with both D1.8 and D1.1.
QA NDT personnel (7.2.2) are qualified under their employer's written practice, which must meet or exceed ASNT SNT-TC-1A or CP-189.
QC welding inspectors (7.2.3) must be at least Associate Welding Inspectors under AWS B5.1, or otherwise qualified under AWS D1.1 Clause 8.1.4, to the satisfaction of the contractor's QC program.
UT technicians for QA (7.2.4) must be Level II or Level III certified by their employer, or ASNT Level III by examination, and in addition certified by their employer to Annex F, a practical flaw detection test on weld mockups. Our article on ultrasonic and magnetic particle testing explains Annex F.
The QA agency's written practice
Clause 7.3 requires the QA agency to work to a written practice that describes:
- the training, experience and examination required to qualify and certify its inspectors
- how inspectors are selected and assigned
- its inspection procedures, including general inspection, material control and visual welding inspection
- how it decides whether the structure meets the codes, standards and specifications
The commentary points to ASTM E329, the specification for agencies that test or inspect construction materials, as the model.
Extra checks for seismic frames
Clauses 7.4 to 7.8 add inspections that normal D1.1 work does not require. Most apply when the QAP calls for them:
- k-area MT (7.4). After welding doublers, continuity plates or stiffeners in the k-area, MT of the web within 75 mm (3 in) of the weld, no sooner than 48 hours after welding. See our article on k-area cracking.
- Lamellar tearing UT (7.5). Covered below.
- Copes and access holes (7.6). MT or penetrant testing (PT) of cut surfaces before welding. See our article on weld access holes.
- Access hole repairs in the Protected Zone (7.7). Always inspected by MT or PT.
- Repaired tab removal sites (7.8). MT of the repair and the area next to it, whenever the repair used welding.
Lamellar tearing
Clause 7.5 says that when the QAP requires it, base metal is ultrasonically tested after welding for laminations and lamellar tearing. Any discontinuity within t/4 of the surface next to the fusion line is accepted or rejected on the criteria of AWS D1.1 Table 8.2.
The commentary explains the problem. Lamellar tearing is a separation of the base metal along planes parallel to the rolled surface. It happens when large welds shrink under high restraint and pull on the plate through its thickness, tearing along planes of elongated non-metallic inclusions. The tears have a typical stair-step shape. Susceptibility rises with the density and size of inclusions and their closeness to the surface, and inclusions deeper than t/4 generally do not contribute.
AISC 341 calls for this UT on base metal thicker than 38 mm (1-1/2 in) loaded in the through-thickness direction in T- and corner joints, where the connected material is thicker than 20 mm (3/4 in) and contains CJP groove welds. Typical cases are column flanges behind heavy beam flange welds and continuity plates. The commentary notes that the acceptance table is normally used for weld metal and was chosen deliberately as a conservative test for SFRS base metal. Whether the flaw was a lamination from the mill or a tear caused by welding does not matter; both are judged the same way.
What the fabricator should have ready
A QA inspector arriving at the shop, in person or remotely, will expect to see:
- the approved shop drawings and the project QAP
- WPSs and supporting PQRs or heat input envelope data
- welder qualification records, including Annex D restricted access where needed
- filler metal certificates, lot records and exposure control logs
- mill certificates for SFRS material
- QC inspection reports for each piece, with welder identification
- NDT reports where QC performed NDT
Our article on seismic weld submittals and records lists the documents in detail.
Common gaps between QC and QA
The same problems come up on many seismic projects:
- No QAP at bid time. The fabricator prices normal D1.1 inspection, then learns later that k-area MT, lamellar tearing UT and access hole MT are required.
- Unclear hold points. QA wants to observe fit-up of the first moment connection, but nobody told the shop to wait.
- Late QA visits. Members are painted before QA has seen the welds, so coating has to be removed for inspection.
- Records in pieces. Welder IDs, filler metal lots and NDT reports are kept in separate places and cannot be matched to a piece mark.
- Unqualified UT technicians. A technician without Annex F certification tests Demand Critical welds, and the results have to be repeated.
Agreeing the QAP tasks, hold points and record format at the start of the job prevents almost all of these.
How World Steel supports QC and QA
World Steel runs QC on every seismic member through its own inspection checkpoints, from incoming material to final inspection, and agrees the inspection and test plan with the US contractor for each project. Our shop welding procedures and welders are qualified to AWS D1.8, and all records sit in our IAS AC472-accredited quality system. Materials are tested at ISO/IEC 17025 laboratories or a laboratory the customer names. The owner's QA agency can review records and watch production live through inspector access, or visit the plant in person, so QA tasks in the QAP can be performed without delay to fabrication.
Quick answers
What is the difference between QC and QA on a seismic project?
QC is the contractor's own inspection of materials and workmanship. QA is inspection by an agency other than the contractor, on the owner's behalf, that monitors QC and may repeat some tasks, including NDT.
Who writes the Quality Assurance Plan?
The Engineer, when the building code or contract documents require one. AISC 341 Chapter J sets its minimum content for welded SFRS construction.
How must QA welding inspectors be qualified?
As AWS B5.1 Welding Inspectors or Senior Welding Inspectors, AWS QC1 Certified Welding Inspectors or Senior CWIs, or CWB Level 2 or 3 inspectors under CSA W178.2. Associate levels may work under direct, on-site supervision.
When is base metal checked for lamellar tearing?
When the QAP requires it, by UT after welding. Discontinuities within t/4 of the surface next to the fusion line are judged against AWS D1.1 Table 8.2.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- Quality hubInspection, testing and sign-off at the plant
- Online factory auditWalk the shop live with our QA team
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors
- Solutions by stateState-by-state steel solutions
- Send your drawingsGet a steel package quote from your drawings