Special inspection of fabricated steel when the shop is abroad

IBC Chapter 17 does not stop at the US border. Here is how special inspection of fabricated steel is planned when the shop is on the other side of the Pacific.

· updated November 19, 2026 · 3 min read · World Steel USA engineering team

Special inspection is the part of the IBC that makes sure what was designed is what gets built. For structural steel it covers material, welding, bolting and dimensions, and it applies to work in the fabricator's shop as well as on site. When the shop is overseas, the rules are the same; the planning is different.

What the code asks for

IBC Chapter 17 requires a statement of special inspections prepared by the registered design professional, listing what must be inspected and how often. For structural steel this references AISC 360 Chapter N (quality control and quality assurance) and, for seismic systems, AISC 341.

Two parties are involved:

  • Quality control (QC) is the fabricator's own inspection.
  • Quality assurance (QA) is the owner's independent check, done by the special inspector.

The approved fabricator route

IBC Section 1704.2.5 lets the building official reduce QA inspection in the shop when the fabricator is approved: registered and approved to perform the work without special inspection, usually shown by AISC certification or IAS AC472 accreditation. At completion the fabricator submits a certificate of compliance.

For steel fabricated abroad, this route is the most practical, because it relies on the fabricator's audited quality program rather than an inspector in the shop for weeks.

When plant inspection is still required

Some specifications or officials still require QA at the plant, for example for seismic demand-critical welds or for the first articles of a new detail. Plan it like this:

  1. Agree hold points at award: first-article fit-up, welding of critical joints, NDT, final dimensional check and coating.
  2. Book visits early so the inspector's travel matches the shop schedule.
  3. Use live video where accepted: a walk-through with measurements on camera can cover many routine checks between in-person visits.
  4. Share records online, piece by piece, so the inspector reviews before arriving.

What a good fabricator provides

  • Notice of each hold point with enough lead time.
  • Access to members, procedures and personnel.
  • Welding procedure specifications, welder qualifications and NDT technician certifications.
  • Traceable records: which piece, which heat, which welder, which inspector, which result.

At World Steel these records are kept against each member in PEB Studio, so the US inspector can see a member's quality history before and after it is packed.

Site inspection still applies

Shop QA does not cover field welding, bolting or erection. The US contractor, as erector, and the special inspector handle those on site. Make sure the statement of special inspections separates shop and field items clearly, so nothing falls between them.

Who hires the special inspector

The building code expects the owner, or the registered design professional acting for the owner, to engage the special inspector, not the contractor whose work is being inspected. In practice the general contractor often coordinates the schedule, but the inspector reports to the building official and the Engineer of Record. Make that relationship clear in the contract so the inspector's findings reach the right people.

The statement of special inspections

The Engineer of Record prepares a statement of special inspections that lists what must be inspected, how often and by whom. For structural steel it usually covers material identification, welding, high-strength bolting and, for seismic systems, the additional tasks in AISC 341. Read it before you award the steel package: it tells you whether plant inspection is required and how much of the work can rely on the fabricator's accreditation.

Fabricator's certificate of compliance

When the approved fabricator route is used, the fabricator issues a certificate of compliance at the end of the work, stating that the steel was made under its approved quality system and to the approved construction documents. The building official keeps it with the project records. Ask for the format of this certificate at bidding so it is not a surprise at closeout.

Records the inspector will want

Mill certificates, welding procedure specifications, welder qualifications, inspection reports, NDT reports, coating records and nonconformance reports with their resolution. A fabricator that can send all of these as a single organised package, piece by piece, saves the inspector days of chasing paper.

Distance is a planning issue

For a plant overseas, schedule plant visits around hold points that matter most: the first article of each member type, demand-critical welds and final inspection before packing. Use video and online records between visits.

A short checklist

  • Statement of special inspections covers shop items explicitly.
  • Fabricator's approval is confirmed with the building official before award.
  • Hold points and video inspection rules are agreed in writing.
  • Record format is agreed (and ideally online).
  • Certificate of compliance is a contract deliverable.

Quick answers

Do inspectors have to fly to the plant?

Not always. With an approved fabricator the building official may accept the fabricator's audited program plus records. Where plant inspection is still required, some hold points can be witnessed by live video if the inspector and official agree.

Who pays for special inspection?

Under the IBC the owner normally engages the special inspector. The fabricator gives access, notice of hold points and records.

What records should arrive with the steel?

Typically mill certificates, weld and NDT reports, dimensional checks, coating reports and a certificate of compliance from the approved fabricator.