Steel backing is a strip of steel held under the root of a groove weld. It lets the welder fill a wide-open root from one side without the weld metal falling through. It is fast and reliable, and on most structural steel it stays in place forever without any harm. In a seismic moment connection, though, the edge of that strip where it touches the column flange forms a thin unfused gap: a ready-made crack sitting right at the most stressed point of the weld. AWS D1.8 Clauses 6.13 to 6.15 deal with that problem. This article explains when weld backing removal is required, how the root is treated afterwards, and the rules for backing that stays.
What Northridge revealed
The D1.8 commentary on Clause 6.13 summarizes the findings after the 1994 Northridge earthquake:
- Left-in-place steel backing created a notch effect at the root of the beam flange to column flange weld. Even with sound fusion in the root, the natural unfused plane between one edge of the backing and the column flange concentrated stress.
- Backing also hid root flaws from ultrasonic testing. Those hidden flaws could be much worse notches than the backing itself.
- The effect was more severe at the bottom flange than at the top flange. With backing under both flanges, the bottom flange notch sits at the point of maximum stress in the groove weld, while the top flange notch sits at a lower-stress point. Removing top flange backing also means working through an access hole, which is hard to do well.
The result is a joint-by-joint approach rather than a blanket rule.
Who decides where backing comes off
Clause 1.4.1 asks the Engineer to show three things on the contract documents:
- where backing must be removed (item 6)
- where reinforcing fillet welds are required (item 7)
- where fillet welds are required at left-in-place backing (item 8)
The commentary is direct: removing backing and tabs from every connection is costly and unnecessary. Removal can be impractical, as at column splices, or impossible, as at the inside corners of small box sections. Some AISC connection qualifications were tested with backing left in place, so removal is not justified there. AISC 341 and AISC 358 set the requirements, and the Engineer transfers them to the drawings.
A frequent pattern: Table C-1.1
The commentary includes a table of frequently used practice. It is guidance, and the governing documents for each project control, but it shows the typical pattern:
| Location | Weld tabs | Steel backing |
|---|---|---|
| Moment frame, top flange to column flange | Remove | Stays, with fillet weld to the column (not to the beam) |
| Moment frame, bottom flange to column flange | Remove | Remove |
| Continuity plates | Near the k-area: not recommended; near flange tips: remove | Stays, with fillet weld to the column |
| Concentrically braced frames, brace connections | Stay | Stays |
| Eccentrically braced frames, link to column | Remove | Same as moment frames |
| Eccentrically braced frames, brace to link | Remove | Remove |
| Other EBF brace connections | Stay | Stays |
| Column splices | Remove | Stays |
How backing is removed
Clause 6.13 lists the methods: air carbon arc gouging, plasma arc gouging, grinding, chipping or other thermal cutting. The process must be controlled to minimize errant gouging, meaning the operator must not cut into the beam flange or column face around the backing.
Then:
- Backgouge to sound metal. After backing removal, steel or non-steel, the weld root is backgouged until sound weld metal is reached. The commentary explains this is how root flaws are found and removed.
- Back weld. The backgouged joint is restored by welding, following the repair welding rules of Clause 6.19.2.
- Treat small notches. Notches and gouges no deeper than 1.5 mm (1/16 in) left after back welding are ground smooth under Clause 6.19.1. Deeper ones are repaired by welding under Clause 6.19.2.
The same backgouge-to-sound-metal rule applies when non-fusible backing, such as ceramic or copper, is used.
Reinforcing fillet welds
Clause 6.14 covers the fillet weld added where backing has been removed, when the contract documents call for it:
- minimum size 8 mm (5/16 in)
- the leg on the beam flange side must put the fillet's toe on base metal, not on the back weld, unless both the back weld and the base metal are ground smooth after backing removal, in which case the fillet need not extend to base metal
The commentary explains the purpose. The intersection of the column face with the beam bottom flange is an area of very high demand, and a T-joint meeting at nearly 90° concentrates stress at the weld root and face. An 8 mm fillet on the column face smooths that corner. Because the horizontal leg may need to be longer to cover the whole root area, the finished fillet often has unequal legs, with the longer leg along the beam flange.
Reinforcing fillets are not needed on most groove welds in T- or corner joints, and they cannot be used on butt joints such as column splices.
Backing that stays
Where backing is allowed to remain, Clause 6.15 sets two rules at beam flange to column flange joints:
- Fillet weld to the column. When the contract documents call for a fillet weld between the left-in-place backing and the column, it is at least 8 mm (5/16 in). The commentary explains that this fillet seals the natural unfused plane between backing and column, which significantly reduces the stress concentration.
- No weld to the beam flange. Backing must not be welded to the underside of the beam flange, and tack welds are not allowed there either. Welding the backing to the beam pulls more stress into the backing and makes the notch at the column worse, whether the weld is continuous or a single tack.
Tack welds that hold backing
Clause 6.12.3 controls how backing is held in place inside a Protected Zone:
- Tack welds between backing and the beam flange outside the weld joint are prohibited.
- Tack welds holding steel backing for groove welds should be placed inside the weld joint when practicable, so the later passes consume them.
- The exception: steel backing may be tack welded to the column for beam flange to column flange welds.
If a tack or fillet weld is put between backing and beam flange by mistake, Clause 6.18.4 sets the fix: remove the weld so it no longer joins backing to flange, grind the flange surface flush and defect-free, and repair any gouge or notch under Clause 6.18.5. Our article on protected zone fabrication rules covers the other Protected Zone limits.
Ultrasonic testing near backing
Left-in-place backing creates reflections that can be mistaken for flaws, and real flaws can be mistaken for backing reflections. Clause 7.10.4 says joints are not rejected on the basis of the indication rating of geometric reflectors caused by left-in-place backing, and the commentary points to D1.1 guidance for interpreting them. The UT procedure for joints with backing is qualified on mockups that prove the root can be covered.
Shop or field
Most beam-to-column moment connections are welded in the field, so backing removal, backgouging and reinforcing fillets at those joints are the erector's work and the US contractor's scope. On shop-welded column trees, continuity plates and built-up members, they are shop work. In both cases the shop drawings should show the backing disposition of every joint type, so nobody guesses on site.
Common backing mistakes
The same errors turn up on seismic jobs again and again, and most of them are cheap to prevent:
- Tacking backing to the beam flange. A quick tack on the underside of the flange feels harmless, but it is exactly what Clause 6.15 prohibits, and removing it later means grinding inside the Protected Zone.
- Gouging into the base metal. An air carbon arc operator who chases the backing too hard can cut into the column face or the beam flange, leaving a notch worse than the backing itself.
- Stopping short of sound metal. Backgouging only until the backing is gone, without reaching sound weld metal, leaves the root flaws that removal was meant to find.
- Fillet toe on the back weld. A reinforcing fillet whose toe lands on an unground back weld puts a new stress raiser in the same high-demand corner.
- Removing backing that was meant to stay. Removal at a joint that was qualified with backing in place adds work and risk without any benefit.
Questions a general contractor can ask
- Which joints have backing removed, which keep it, and where is that shown on the shop drawings?
- Which joints need a reinforcing fillet, and what size and leg orientation are detailed?
- How are backing tacks placed inside Protected Zones?
- How is backgouging to sound metal confirmed, and who records it?
How World Steel handles backing
World Steel shows the backing, reinforcing fillet and weld tab treatment of every seismic joint type on the shop drawings, taken from the contract documents, and raises an RFI when a connection is unclear. In the shop, backing in Protected Zones is tacked inside the joint or to the column, never to the beam flange, and where backing is removed our welders backgouge to sound metal, back weld and add the specified fillet. Our shop welding procedures and welders are qualified to AWS D1.8, and these steps are recorded in our IAS AC472-accredited quality system and checked at the weld inspection and NDT checkpoint.
For the matching rules on weld tabs, read weld tab removal and end dams.
Quick answers
Does AWS D1.8 require all steel backing to be removed?
No. Backing is removed only where the contract documents require it, usually at beam bottom flange to column joints of moment connections. The commentary says removing it everywhere is costly and unnecessary.
What happens after backing is removed?
The root is backgouged to sound metal and back welded. Notches up to 1.5 mm deep are ground smooth; deeper ones are repaired by welding.
How big is a reinforcing fillet weld?
At least 8 mm (5/16 in), with its toe on base metal unless the back weld and base metal are ground smooth.
Can left-in-place backing be welded to the beam flange?
No. At beam flange to column flange joints, backing may be fillet welded to the column, at least 8 mm, but never welded or tacked to the underside of the beam flange.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors