A rolled wide-flange column looks uniform, but it is not. Near the junction of the web and the flange there is a narrow band of web steel that may have been heavily cold worked at the mill, and in that band the steel can be harder, stronger and much less tough than the rest of the section. This band is the k-area. Continuity plates, stiffeners and web doublers in a seismic moment frame are welded right into it. AWS D1.8 Clauses 4.1 to 4.3 and Clause 7.4 set out how to detail, weld and inspect those joints so the column does not crack. This article explains where k-area cracking comes from and what the code asks the fabricator to do about it.
What the k-area is
Clause 3 defines the k-area as the region of the web that extends from the tangent point of the web and the flange-web fillet (the AISC k dimension) a distance of 38 mm (1-1/2 in) into the web beyond the k detail dimension. In plain terms: the strip of web just past the rounded fillet where web meets flange.
The commentary to Clause 4.1 explains why that strip matters. To bring rolled shapes within the straightness tolerances of ASTM A6, some mills use rotary straightening, which bends the shape back and forth between rollers. That cold works the web in and near the k-area. The known effects are:
- higher hardness
- higher yield strength and tensile strength
- a higher yield-to-tensile ratio
- lower Charpy V-notch (CVN) toughness
In some recorded cases the toughness fell below 3 J at 21 °C (2 ft·lbf at 70 °F), which is close to glass. Fractures have been found running from cuts, punches and welds in and on shapes in these areas of reduced toughness.
When k-area cracks appear
The commentary is careful on one point. AISC and SAC investigations found that the altered properties do not harm the in-service behavior of uncracked wide-flange shapes. The risk is cracking during fabrication, at stress raisers in highly restrained joints: the ends of continuity plate welds, web doubler welds and thermally cut coped beams. Rare cases have also come from bolt holes and square-cut beam ends with fairly smooth finishes.
The commentary to Clause 7.4 adds the detail that makes these cracks dangerous: they tend to be delayed. Base metal cracking typically shows up 24 to 48 hours after welding, and the cracks generally, though not always, run through the thickness of the web. A joint that looks perfect when the welder walks away can crack the next day.
The first defense: don't weld there
The commentary's first recommendation is simple. Where practical, avoid welding into the k-area. Where it cannot be avoided, it strongly suggests reducing residual stress by:
- increased preheat
- proper weld sequencing
- minimizing weld volume
It also recommends grinding thermally cut surfaces of beam copes and weld access holes smooth. Our article on weld access holes covers that finish in detail.
Corner clips on continuity plates and stiffeners
A continuity plate fits between the column flanges, against the web. If its inside corner were square, the plate's welds would land right in the fillet and the k-area. Clause 4.1 requires the corner to be clipped:
| Rule | Requirement |
|---|---|
| Along the web (4.1.1) | Clip extends at least 38 mm (1-1/2 in) beyond the published k detail dimension |
| Along the flange (4.1.2) | Clip does not exceed 12 mm (1/2 in) beyond the published k1 dimension |
| Weld terminations (4.1.3) | Clip detailed so both the flange weld and the web weld can end properly |
| Curved clips (4.1.4) | Minimum radius 12 mm (1/2 in) |
The long clip along the web keeps the web weld out of the k-area. The short limit along the flange keeps enough plate bearing against the flange to carry the beam flange force. The commentary notes that these clip dimensions have their own minimum radius rule, so the general D1.1 re-entrant corner rule does not apply to them. AISC tables give the k and k1 dimensions for each rolled shape, and the detailer must use the published values for the actual section.
The clip also shapes the welds. With the minimum clip in place, the welds to the clipped plate must be designed for the steel that remains. The commentary suggests holding fillet welds back one to two weld sizes from the clip, and for groove welds, not using weld tabs in the k-area.
Weld tabs at continuity plates
Clause 6.16.4 follows from that. At the end of a continuity plate weld next to the column web-to-flange junction, weld tabs are not used unless the Engineer permits or requires them, and where they are used they are left in place unless the Engineer specifies removal. Removing a tab in that tight corner by gouging or grinding is likely to do more harm than good. The weld ends there may be cascaded instead. At the opposite, outboard end of the plate, tabs can be used normally. Our article on weld tab removal and end dams covers the general tab rules.
Doublers: joint details and mockups
A web doubler is a plate welded to the column web in the panel zone to add shear capacity. Its edges run along the flange fillet, so its welds sit right on the k-area. AISC 341 Section E3.6e.3 shows several ways to join doublers; one common detail combines a J-groove and a bevel along the fillet.
Clause 4.3 lets doublers be welded with a prequalified WPS. Welds at the fillets of rolled shapes using the D1.8 Figure 4.3 details need no testing to qualify the joint geometry, provided the WPS meets the other prequalification rules of D1.1 Clause 5 and the D1.8 requirements are satisfied.
If the production groove angle or root opening is smaller than Figure 4.3 permits, a mockup is required:
- Weld a mockup of the production joint with doubler, web and flange.
- Use the smallest root opening and smallest included angle that production will use.
- Make the mockup doubler at least as thick as the thickest production doubler, though it need not exceed 25 mm (1 in).
- Cut three macroetch sections about 100 mm (4 in) apart (Figure 4.4), polish and etch them so the weld shows clearly.
Clause 4.3.1 sets the acceptance criteria for the macroetch sections, inspected visually:
- no cracks
- thorough fusion between adjacent layers and between weld and base metal
- thorough fusion to the root of the joint, but not necessarily beyond
The fit-up tolerances of Figure 4.3 then apply to the production joints. The commentary also notes the gap that forms when a doubler laps onto the fillet: for plug or slot welded doublers it is limited by the rules for those welds, and for doublers fillet welded at their ends it is limited by fillet weld fit-up rules.
Delayed MT: Clause 7.4
When the QAP requires it, Clause 7.4 calls for magnetic particle testing (MT) of the member web after welding doublers, continuity plates or stiffeners in the k-area:
- the area tested is the k-area base metal within 75 mm (3 in) of the weld
- MT is done no sooner than 48 hours after welding is complete
The 48-hour wait matches the delayed cracking described above. Testing too early can miss a crack that has not yet formed. The commentary adds two good practices for doublers: test both the side of the web opposite the weld and the end of the weld, and where doublers go on both sides of the web, test after welding the first side and before welding the second, so a crack from the first side is not hidden.
MT follows the yoke method and written procedure of Annex G, explained in our article on ultrasonic and magnetic particle testing.
Transitions in thickness and width
Clause 4.2 also sits in this part of the code. When a butt joint in tension has to be tapered, the slope of the transition must not be steeper than 1 in 2-1/2, made by chamfering the thicker part, tapering the wider part, sloping the weld metal, or a mix (Figures 4.1 and 4.2). The commentary notes that tapered transitions are required only where the Engineer specifies them. This matters on column splices and built-up flanges, where plate thickness steps from one size to the next.
Built-up columns avoid the problem
The k-area problem belongs to rolled shapes straightened at the mill. A built-up column, made by welding plates together, has no rolled fillet and no rotary-straightened k-area. Its web-to-flange welds are made under controlled shop conditions with plate of known toughness. That is one reason heavy seismic columns, box columns and cruciform columns are often built up rather than rolled. Built-up sections have their own rules, such as the lamellar tearing checks covered in our article on seismic weld QC and QA inspection, but the rolled k-area concern does not apply.
Shop practice checklist
- Check the rolled section's published k and k1 values and detail clips to Clause 4.1.
- Cut clips mechanically, with curved clips at least 12 mm radius and smooth cut surfaces.
- Use the Figure 4.3 doubler details, or run a macroetch mockup for tighter joints.
- Preheat to the WPS, and consider higher preheat where k-area welding is unavoidable.
- Sequence welds to limit restraint, and keep weld size to what design needs.
- Leave continuity plate tabs at the k-area corner unless the Engineer says otherwise.
- Schedule MT at least 48 hours after welding where the QAP calls for it, testing between sides for double doublers.
How World Steel handles k-area welding
World Steel details continuity plate clips, stiffeners and doubler joints from the published section dimensions and the contract documents, and shows them on the shop drawings for the US contractor's review. Clips are cut on our laser and beam line equipment, so the radii and lengths are repeatable. Our shop welding procedures and welders are qualified to AWS D1.8, and where the QAP requires k-area MT, it is scheduled after the 48-hour wait and recorded with the piece mark in our IAS AC472-accredited quality system. For heavy seismic columns we also fabricate built-up steel columns, including box and cruciform sections, which avoid the rolled k-area altogether.
Quick answers
What is the k-area?
The part of a rolled shape web that runs from the tangent point of the web-to-flange fillet a distance of 38 mm (1-1/2 in) into the web beyond the k detail dimension. Mill straightening can make it harder and less tough.
How big must a continuity plate corner clip be?
Along the web, at least 38 mm (1-1/2 in) beyond the published k detail dimension. Along the flange, no more than 12 mm (1/2 in) beyond the published k1 dimension. Curved clips need at least a 12 mm radius.
When is MT of the k-area done?
When the QAP requires it, after welding doublers, continuity plates or stiffeners in the k-area. It covers the web within 75 mm (3 in) of the weld and is done no sooner than 48 hours after welding.
When does a doubler joint need a mockup?
When the production groove angle or root opening is smaller than the Figure 4.3 detail permits. Three macroetch sections about 100 mm apart must show no cracks and full fusion to the root.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors