Engineering and codes

Lowest anticipated service temperature: when cold weather changes seismic welding

Most seismic welds live in heated buildings. The ones that do not, such as parking decks, canopies and cold storage, need a Lowest Anticipated Service Temperature on the drawings. Here is how LAST changes filler metal testing.

· 7 min read · World Steel USA engineering team

Steel loses toughness as it gets colder, and so does weld metal. Most seismic frames sit inside heated buildings, where that is not a concern. But many do not: open parking structures, stadium canopies, pipe racks, unheated warehouses, cold storage and buildings in Alaska, the northern Rockies and the high desert. For those, AWS D1.8 asks the Engineer to set a Lowest Anticipated Service Temperature (LAST), and the welding requirements change. This article explains what LAST is, when it applies and how a fabricator responds.

What LAST means

Clause 3 defines LAST as the lowest daily minimum temperature, or other suitable temperature, set by the Engineer of Record. The definition was changed in the 2021 edition to match AISC 341.

Two words in that definition carry weight:

  • Daily minimum. LAST is not the record low for the area. It is based on daily minimum temperatures that the steel will realistically see.
  • Suitable. The commentary notes that insulation and exposure may allow a calculated LAST warmer than the outdoor temperature. A frame inside an insulated but unheated building, for example, may never get as cold as the air outside.

When the drawings need a LAST

Clause 1.4.1, item 11, asks the Engineer to show LAST on the contract documents if the structure is not enclosed and maintained at 10 °C (50 °F) or higher. The commentary adds that most welded connections in buildings are in temperature-controlled settings, so most projects need no LAST at all.

Typical cases where LAST is needed:

Structure Why it may be cold in service
Open parking structures The frame is exposed to outdoor air
Canopies, porte-cocheres and covered walkways Fully outdoors
Pipe racks and equipment support frames Outdoors at industrial sites
Unheated warehouses and agricultural buildings Enclosed but not heated
Cold storage and freezer buildings Steel inside the insulated envelope can run well below freezing
Buildings under construction for long periods Heat may not be on before the building is finished, a question for the Engineer

The seismic states overlap with cold climates more than people expect. Alaska, Utah, Idaho, Montana, Nevada's high desert and the inland Pacific Northwest all combine meaningful seismic design categories with hard winters. Our Alaska and Utah solutions pages cover those markets.

How LAST changes demand critical welds

For Demand Critical welds, the standard test in Table 6.3 is 54 J (40 ft·lbf) at 21 °C (70 °F) for 70 and 80 ksi filler metals and at 10 °C (50 °F) for 90 ksi filler metals. Those temperatures assume a LAST of 10 °C. When LAST is lower, Clause 6.2.2 moves the test temperature down:

  • 70 and 80 ksi filler metals: test at no more than 11 °C (20 °F) above LAST
  • 90 ksi filler metals: test at LAST

The commentary explains the 11 °C shift. Charpy tests are fast impact tests, while seismic loading, though rapid, is slower. For 70 and 80 ksi weld metals that difference in loading rate lets the test run slightly warmer than service. For 90 ksi weld metals the effect is smaller, so no shift is allowed.

The commentary gives an example. If LAST is -15 °C (5 °F), the test temperature is no higher than -5 °C (25 °F) for 70 or 80 ksi filler metal, and -15 °C for 90 ksi filler metal.

These rules apply whether the WPS is prequalified or qualified by test.

Exemptions that disappear

Two shortcuts in D1.8 depend on LAST being 10 °C or warmer:

  1. Table 6.4 exemption from heat input envelope testing. E7018 and E7018-1 SMAW electrodes, E7018-C3L and E8018-C3, and ER70S and ER80S-Ni solid GMAW wires are normally exempt from Annex A. Below 10 °C LAST, they are not (Clause 6.2.2).
  2. Exemption from production lot testing. Under Clause 6.3.4, the same products are normally exempt from lot testing when the certificate shows 27 J at -18 °C. Below 10 °C LAST, the supporting tests must be run at no more than 11 °C above LAST for 70 and 80 ksi products, or at LAST for 90 ksi.

So a cold LAST does not just change a number on a test report. It can turn a simple E7018 job into one that needs envelope data at a low temperature for every product used on Demand Critical welds.

The intermix test follows LAST too

When self-shielded flux cored wire is combined with another process in one joint, Annex B requires an intermix Charpy test. For Demand Critical welds, the 54 J test is run at 21 °C, or at LAST plus 11 °C when LAST is below 10 °C. See FCAW-S intermix testing.

What the fabricator does with a LAST

When a LAST appears on the drawings, the shop's job changes in four ways:

  • Filler metal selection. Products are chosen for their low-temperature Charpy performance, not only their classification. A wire classified for -29 °C or -40 °C gives margin.
  • Data collection. Envelope and lot data must be at the right temperature. Manufacturers often publish results at several temperatures; if not, the shop arranges testing with the manufacturer or an accredited lab.
  • WPS review. Heat input limits come from the low-temperature envelope, which may be narrower than the standard one.
  • Base metal. LAST also informs base metal toughness requirements under AISC 341 and the project specification, typically shown by Charpy results on the mill certificates.

Questions to ask the Engineer early

Because LAST can change filler metal and testing, it is worth settling early. Useful questions for the design team:

  1. Is the structure enclosed and kept at 10 °C or warmer in service? If yes, D1.8 needs no LAST.
  2. If not, what LAST applies to the SFRS, and does it differ for parts of the frame, such as an exposed canopy attached to a heated building?
  3. Does the specification call for weld or base metal Charpy testing beyond D1.8 and AISC 341?
  4. For cold storage, is LAST taken as the room temperature inside the insulated envelope?

Getting these answers before bid matters for schedule as much as cost. Low-temperature envelope data may already exist from the filler metal manufacturer, but if it does not, a new Annex A test takes several weeks once plates are welded, machined and tested. Knowing the LAST at the start lets the shop pick a product that already has the data, instead of waiting on a lab while the steel sits.

Our article on freezer and cooler building structure covers other cold storage design points.

Why toughness falls in the cold

Carbon steel and its weld metal have a ductile-to-brittle transition. Above it, a crack has to tear its way through the metal, absorbing a lot of energy. Below it, the same crack can run fast with little warning. The Charpy V-notch test measures that energy at a chosen temperature, which is why every toughness value in D1.8 comes with a temperature attached.

For a seismic weld, the risk is the combination of three things at once: a cold structure, a sharp notch such as a weld root or the edge of left-in-place backing, and the very high strain rates and stresses of an earthquake. The Northridge fractures happened in buildings that were not especially cold, so toughness margin at normal temperatures was already shown to matter. At low service temperatures the margin shrinks further, and the code responds by testing colder.

Shop welding is not service

One point often confuses people. LAST is about the temperature of the finished structure in service, not the temperature in the fabrication shop or on the day of erection. Shop and field welding temperatures are controlled by preheat and interpass rules in D1.1 and D1.8, and gas-shielded field welding by the wind limits in Clause 6.6.3. A frame welded in a warm shop in Vietnam and erected in summer still needs the low-temperature filler metal if it will stand in a freezer or an Alaskan winter. Conversely, a cold welding day does not create a LAST for a building that will be heated.

A cold storage example

Consider a seismic cold storage building in the Pacific Northwest where the freezer rooms run at -25 °C. The steel moment frames that resist seismic load are inside the insulated envelope. The Engineer sets LAST at -25 °C for that frame. For Demand Critical welds with E70 filler metal, the 54 J envelope test temperature becomes -14 °C or colder. The common E7018 and solid wire exemptions no longer apply, so the fabricator needs Annex A data at that temperature, or must qualify its WPSs by test at that temperature. The office block next door, heated and enclosed, needs no LAST at all, so its frames follow the standard rules. The example is a simplified illustration; the Engineer sets the actual values.

How World Steel handles cold service

World Steel has fabricated cold storage projects such as the New Era cold storage facility, and we treat a LAST on the drawings as a trigger for a filler metal review before ordering. Each Demand Critical weld type is matched with a product and with test data at the right temperature, and plate can be supplied with EN 10204 3.1 certificates including Charpy results on request. Testing is done at ISO/IEC 17025 laboratories or a laboratory the customer names. Our shop welding procedures and welders are qualified to AWS D1.8, and the filler metal records sit in our IAS AC472-accredited quality system.

For more on toughness, read seismic filler metal toughness and our page on cold storage facilities.

Quick answers

What is LAST?

The Lowest Anticipated Service Temperature: the lowest daily minimum temperature, or another suitable temperature, set by the Engineer of Record for the steel structure.

When must the Engineer give a LAST?

When the structure is not enclosed and kept at 10 °C (50 °F) or warmer. Heated, enclosed buildings do not need one under AWS D1.8.

How does LAST change the Charpy test?

For demand critical welds with 70 or 80 ksi filler metal, the 54 J test is run no more than 11 °C (20 °F) above LAST. For 90 ksi filler metal it is run at LAST.

Do the E7018 and solid wire exemptions still apply?

No. The Table 6.4 exemptions from heat input envelope testing and from production lot testing only apply when LAST is 10 °C or warmer.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AWS D1.8 seismic fabrication series

Twenty in-depth articles that follow a seismic weld from the drawings to the last test report. Each one explains a part of AWS D1.8:2025 in plain terms and lists the checks a general contractor can ask the fabricator about.

Drawings and scope

What the code covers, which welds are Demand Critical, and the data the drawings must carry.

Procedures and welders

The WPS, the restricted access welder test and the bottom flange sequence.

Details and Protected Zones

Access holes, backing, weld tabs, k-area details, Protected Zones and repairs.

Inspection and testing

Who inspects what, inspector qualifications, and UT and MT done the D1.8 way.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.