QC checkpoint: weld inspection and NDT

Every weld looked at, the critical ones looked into

Every weld on your steel is visually inspected against AWS D1.1 before the member moves on. Where your specification calls for it, ultrasonic, magnetic particle or dye penetrant testing goes further, into the weld or across its surface, and every result is written into your records.

Visual inspection

Looked at three times, not once

AWS D1.1 visual acceptance applies to every weld. AISC 360 Chapter N breaks the work into tasks before, during and after welding, and our QC covers all three on your job.

Before welding

  • WPS at the workstation and followed
  • Welder qualified for the process and position
  • Joint preparation and fit-up accepted
  • Consumables certified and stored dry

During welding

  • Current, voltage and travel speed within the WPS
  • Preheat and interpass temperature where required
  • Each pass cleaned before the next
  • No welding over cracked tacks or in wet, windy conditions

After welding

  • Size, length and location as drawn
  • No cracks, full fusion, craters filled
  • Profile, undercut and porosity within limits
  • Arc strikes removed; tabs and backing removed where required
Welder looking over the stiffeners and end plate of a heavy column
Column stiffeners and end plate under inspection at World Steel, Vietnam.
Two welders operating a submerged-arc welding station on a member
Submerged-arc welding of web-to-flange seams in the Vietnam plant.

Nondestructive testing

Four methods, four different questions

Each method sees something the others miss. Your specification names which ones apply to which welds.

VT

Visual testing

Finds: Surface cracks, lack of fusion at the toes, undercut, porosity, size and profile

Used for: Every weld, by QC, as the first and widest screen

Limits: Sees only the surface; cannot see into the root of a finished groove weld

MT

Magnetic particle

Finds: Cracks at or just below the surface, in fillet and groove welds

Used for: Fillet welds, weld toes and repairs where the specification calls for it

Limits: Steel must be magnetic; does not reach deep inside thick welds

PT

Dye penetrant

Finds: Fine cracks and porosity open to the surface

Used for: Small areas, edges, access holes and repairs

Limits: Finds only flaws that break the surface

UT

Ultrasonic testing

Finds: Lack of fusion, slag and cracks inside the weld volume

Used for: Complete-joint-penetration groove welds, usually 8 mm (5/16 in) thick and over

Limits: Needs a qualified technician and a scanning surface; acceptance per AWS D1.1

QC and QA testing

Who tests what, and why it is written down

What the code requires, and from whom

AISC 360 Section N5.5 sets a minimum of ultrasonic testing for complete-joint-penetration groove welds under transverse tension, scaled by the building’s risk category, and assigns it to quality assurance: the inspection agency working for the owner.

What your specification adds

Many specifications also ask the fabricator to test as part of its quality control, sometimes by method and percentage. We carry out the testing your specification assigns to us and record it in the ITP.

How QA tests our welds

Your agency can test in our plant in Vietnam at the hold points in the plan, with members made available in the order they want them, or test on arrival. Either way, our visual and NDT records travel with the steel.

When a weld fails

The repair loop, closed on record

Marked

A rejected weld is marked on the member in yellow paint marker and logged on the punch list with a photo.

Repaired to a procedure

The defect is removed and rewelded under a WPS by a qualified welder. Repairs that would change the design go to your Engineer of Record first.

Inspected again

The repair is inspected by the same method that found the defect, and the punch list item is closed with a photo.

Recorded

The original result, the repair and the re-inspection all stay in the Welding Inspection Report.

QC and QA

Who checks what at this checkpoint

US practice separates the fabricator’s quality control from the quality assurance carried out for the owner. World Steel runs the QC; your side decides how much QA it adds, and the Engineer of Record sets what is acceptable.

World Steel QC

Quality control: the fabricator

Visually inspects every weld before, during and after welding, performs the NDT the specification assigns to the fabricator, and records results and repairs.

Your inspector

Quality assurance: owner, special or third-party inspector

Performs the testing assigned to QA, either at hold points in our plant, live alongside our QC by video, or on arrival, and reviews our inspection records.

Your Engineer of Record

Sets the criteria, rules on what changes the design

Sets the NDT methods, extents and acceptance level in the specification, marks the welds that need testing, and rules on repairs that touch the design.

Inspectors can attend in Vietnam, join hold points live on Zoom or Microsoft Teams, or be given remote access to the records on request. The plant itself is audited twice a year under IAS AC472, with periodic plant inspections by Smith-Emery Laboratories.

Questions from US contractors and inspectors

Questions about weld inspection and testing

Ask us anything else about this checkpoint before you award, or during the job through your project manager.

Do you inspect every weld?

Yes, visually, against the AWS D1.1 acceptance criteria. Welders check their own work first, foremen check weld size and appearance, and QC inspects and records each weld before the member moves on.

How much of our steel will be ultrasonically tested?

As much as your specification requires. AISC 360 sets a code minimum for certain full-penetration welds based on risk category, and your Engineer of Record can ask for more. We do not apply a fixed percentage of our own.

Who performs the NDT, you or our inspection agency?

Both can. AISC 360 assigns its minimum ultrasonic testing to the owner’s quality assurance. Testing your specification assigns to the fabricator is carried out under our QC. The ITP shows who tests what.

What acceptance criteria do you use?

AWS D1.1, for the loading the weld was designed for, unless your specification sets different criteria. Seismic welds also follow AWS D1.8 where it applies.

Can our agency test the welds in Vietnam?

Yes. Agencies can test at hold points in our plant, where members are easier to reach and repair than on site, or join our inspections live by video.

What happens when a weld fails?

It is marked, logged with a photo, repaired under a welding procedure, and tested again by the same method. The full history stays in your records.

Tell us which welds your engineer wants tested

Send the specification and the weld schedule. We will show in the ITP which tests our QC performs, where your agency tests, and how the records come back to you.