Steel shop drawings: how to get them approved in one round

Shop drawing review is the step most likely to delay a steel package. With the right set-up, most of it can close in a single round.

· updated November 19, 2026 · 3 min read · World Steel USA engineering team

Steel shop drawings turn the design into instructions for the shop and the erector. Every member is drawn, every hole located, every weld specified. They are also the step most likely to delay a steel package, because they pass through several reviewers who each have other work.

What the set contains

  • Erection drawings: plans and elevations with member marks, showing where each piece goes and how it connects.
  • Piece drawings: one per member or assembly, with dimensions, holes, cuts, welds and coatings.
  • Anchor bolt plans: the layout the foundation contractor needs first.
  • Connection calculations, when connection design is delegated.
  • Bills of material and bolt lists.

Who reviews what

Reviewer Looks for
General contractor Coordination with other trades, site constraints, erection sequence
Engineer of Record Conformance with the structural design intent
Architect Geometry and finish of exposed steel
Fabricator Shop practicality, before submitting

Why reviews take several rounds

The usual causes are predictable:

  1. Design changes after detailing started, often from other trades.
  2. Open RFIs answered on the drawings instead of before them.
  3. Missing information: elevations, embed locations, MEP openings.
  4. Unclear connection responsibility.
  5. Slow turnaround, with reviewers working in series instead of in parallel.

How to get to one round

Hold an RFI kick-off. Before detailing, the detailer lists every open question; the team answers them in one meeting.

Release by sequence. Approve anchor bolts first, then the first erection sequence, so fabrication can start while later sequences are reviewed.

Review in the model. A shared 3D model shows clashes and geometry far faster than PDFs. World Steel shares models in PEB Studio so reviewers can rotate, measure and comment on the steel.

Review in parallel. The general contractor and the Engineer of Record review at the same time, then merge comments in one call.

Agree turnaround times. Write review periods into the subcontract, for example five working days per round.

Approval does not move design responsibility

Approval of shop drawings confirms they follow the design intent; it does not transfer design responsibility to the reviewer, and it does not make the fabricator the designer of record. Keep the stamp language standard and clear.

Erection drawings and the erector's needs

Shop drawings describe each piece. Erection drawings show where each piece goes, with piece marks, grid lines, elevations and bolt details. The US contractor, our customer, uses the erection drawings to plan the sequence, crane picks and temporary bracing, so they should be issued early and kept current with every revision.

Revision control

Every resubmittal should show what changed. Clouded revisions, a revision table and a short transmittal note that lists the changes make the second round fast. Without them, reviewers check the whole set again, and each round takes as long as the first.

Keep one log for all submittals: drawing number, revision, date sent, date returned and status. Both the fabricator and the contractor should be able to see the same log. A shared online log avoids long email chains between time zones.

RFIs during detailing

Detailers find gaps in the design drawings: a missing elevation, a connection that clashes with a column, a load that is not stated. Each gap becomes an RFI. Answer RFIs before the shop drawings are submitted, not on the returned set, or the reviewer will send the drawings back with the same questions.

Batch RFIs by area and send them early. A fabricator detailing overnight in Vietnam can turn a morning answer from the US into revised drawings by the next US morning, which is an advantage of working across time zones when the process is set up for it.

Models and drawings together

Many projects now exchange a 3D model alongside the drawings. The model helps reviewers find clashes and check geometry faster than on paper. Agree the model format, such as IFC or Tekla, and which document governs if the model and drawings disagree. In most contracts, the approved drawings govern.

Approval stamps

Use clear review stamps: approved, approved as noted, revise and resubmit, or rejected. "Approved as noted" should mean the fabricator may proceed with the noted changes, without another round.

Included, not extra

At World Steel, shop drawings are included on every project, and nothing is cut until the Engineer of Record has approved them. That makes the approval step the gate for the whole schedule, which is exactly why it deserves the planning above.

Quick answers

Do shop drawings cost extra with World Steel?

No. Shop drawings are included on every World Steel project at no extra cost.

Who approves steel shop drawings?

The general contractor reviews for coordination and the Engineer of Record reviews for conformance with the design. The architect may review exposed steel.

Can review happen in the model instead of PDFs?

Yes, if the team agrees. Reviewing a shared 3D model resolves geometry questions much faster than marked-up sheets.