Skip to content
Seeking US contractor partners IAS AC472 ACCREDITED ★ METAL BUILDINGS ★ AC472 IAS AC472 accreditedIAS AC472
World Steel USA
Welded H-beams with stiff flanges and webs being assembled in the World Steel plant

Engineering and codes

Width-to-thickness ratio limits for seismic steel members: Table D1.1 explained

A seismic member can only yield through many cycles if its flanges and webs are stocky enough not to buckle first. AISC 341-22 Table D1.1 sets those width-to-thickness limits for moderately and highly ductile members, and the 2022 edition revised the equations for webs and box walls.

· 7 min read · World Steel USA engineering team

Steel fails in seismic frames in a handful of ways, and one of the earliest is local buckling. A beam flange that is wide and thin may yield nicely the first time an earthquake bends it, then ripple and fold on the next cycle, losing strength just when the frame needs it most. To prevent that, AISC 341 limits the width-to-thickness ratio of every flange, web and wall in the members chosen to yield. Those limits live in Section D1.1 and Table D1.1 of AISC 341-22, which the 2022 edition updated. This article explains the logic, the two ductility classes, what changed and how the limits shape member selection.

Why slenderness controls ductility

A steel plate element, such as a flange of an I-beam, behaves like a thin column under compression. If it is slender, it buckles at a low strain. If it is stocky, it can be squeezed well past yield and into strain hardening before it buckles. In a beam bent back and forth by an earthquake, one flange is always in compression, so the flange's slenderness decides how much plastic rotation the beam can deliver before it loses strength.

AISC 360 already classifies sections as compact, noncompact or slender for ordinary design. Compact sections can reach their plastic moment, but that is not enough for seismic design, which asks a member to hold its strength through many large cycles. AISC 341 therefore sets stricter limits than AISC 360's compact limit.

Two ductility classes

Section D1.1 divides members of the seismic force-resisting system (SFRS) into two classes, and each system chapter says which class its members must meet:

  • Moderately ductile members, limited by λmd, are expected to undergo moderate inelastic rotation or strain, on the order of what an intermediate moment frame or the beams of a braced frame experience.
  • Highly ductile members, limited by λhd, are expected to undergo large inelastic rotation or strain, such as special moment frame beams reaching story drift angles of 0.04 radians, or braces in special concentrically braced frames that buckle and yield repeatedly.

As a general guide, the "special" systems ask for highly ductile members where the yielding happens, and the "intermediate" systems ask for moderately ductile ones. The system chapters in E, F, G and H give the exact assignment member by member.

How the limits are written

Table D1.1 expresses each limit as a coefficient times a material term, usually √(E/(Ry Fy)), where E is the modulus of elasticity, Fy the specified minimum yield stress and Ry the ratio of expected to specified yield stress from Table A3.1. Using Ry Fy rather than Fy means that a steel expected to be stronger gets a slightly stricter limit, because it will strain more before reaching its plastic moment.

For the flanges of rolled or built-up I-shaped sections, which is the most common check, the limits are:

  • Highly ductile: b/t ≤ 0.32 √(E/(Ry Fy))
  • Moderately ductile: b/t ≤ 0.40 √(E/(Ry Fy))

Here b is half the flange width and t the flange thickness.

A worked example

Take ASTM A992 steel, with Fy = 345 MPa (50 ksi) and Ry = 1.1, so Ry Fy is about 380 MPa (55 ksi). With E = 200,000 MPa (29,000 ksi), √(E/(Ry Fy)) is about 22.9. The highly ductile flange limit is then 0.32 × 22.9 ≈ 7.3, and the moderately ductile limit 0.40 × 22.9 ≈ 9.2.

A rolled beam with flanges 254 mm (10 in.) wide and 17 mm (0.67 in.) thick has b/t = 127/17 ≈ 7.5: fine for a moderately ductile member, just over the highly ductile limit. For a special moment frame beam, the designer would pick a section with a thicker or narrower flange, or build up a section to suit.

Webs: axial load matters

For webs, the limits depend on how much axial load the member carries. A web under bending alone can be relatively slender, but as axial compression rises, more of the web is in compression and the limit tightens. Table D1.1 expresses this through the ratio of required axial strength to axial yield strength, often written Ca.

AISC 341-22 revised the equations for webs of rolled or built-up I-shapes and channels used as beams or columns, and for the webs and walls of box sections. The changes reflect newer research on how columns under high axial load behave during large drifts, and they make the transition between low and high axial load smoother. For deep columns in moment frames, which are common in US practice because they help control drift, the web limit is often what governs the section choice.

Hollow structural sections and design thickness

For hollow structural sections (HSS), both rectangular and round, Table D1.1 gives limits on the wall slenderness, b/t or D/t. These matter most for HSS braces in special concentrically braced frames, where local buckling of the wall at the brace's mid-length plastic hinge is a classic way braces fracture.

The 2022 edition clarifies when the design wall thickness must be used instead of the nominal thickness in these checks. HSS made by electric-resistance welding to some specifications are produced with walls thinner than nominal, and AISC 360 defines a design thickness that accounts for it. Using the right thickness can change whether a tube meets a highly ductile limit, and therefore whether it can be used as an SCBF brace at all.

Other elements in the table

Table D1.1 also covers:

  • Flanges and legs of angles, tees and channels, used as braces or in built-up members.
  • Stems of tees.
  • Webs of built-up box sections and their stiffened elements.
  • Plates in composite members, such as the walls of concrete-filled tubes and steel plates in composite walls, where concrete restrains inward buckling and the limits differ.
  • Elements of links in eccentrically braced frames, where flange limits depend on link length.

How the limits shape design and fabrication

Width-to-thickness limits look like a pure design issue, but they ripple through procurement and fabrication:

  1. Section availability. Not every rolled section meets the highly ductile limits, especially lighter shapes with wide flanges. The available list narrows quickly for SMF beams and columns.
  2. Built-up members. When no rolled section fits, the designer turns to a built-up section, choosing flange and web plates that satisfy the limits directly. Heavy box columns and cruciform columns in tall moment frames are usually built up for exactly this reason.
  3. Grade substitutions. Because Ry Fy appears in the limit, swapping to a stronger grade can push a section over the line. Any grade change in the SFRS needs the engineer's check.
  4. HSS sourcing. For SCBF braces, the tube specification (for example ASTM A500 or A1085) affects the design thickness and therefore whether the brace complies.
  5. Plate tolerances. In built-up members, the actual plate thickness at the lower tolerance limit can matter for elements close to the limit. Good shops check plate thickness at intake.

A quick map by system

The table below is a simplified guide to where each ductility class typically applies. The system chapters of AISC 341-22 govern, and some members have exceptions or alternatives.

System Members where yielding is expected Usual ductility class
Special moment frame (SMF) Beams, and columns that may hinge Highly ductile
Intermediate moment frame (IMF) Beams and columns Moderately ductile
Special concentrically braced frame (SCBF) Braces, and columns of the braced bay Highly ductile
SCBF beams Beams of the braced bay Moderately ductile
Eccentrically braced frame (EBF) Links Depends on link type and length
Buckling-restrained braced frame (BRBF) Beams and columns around the brace Moderately ductile
Steel plate shear wall (SPSW) Boundary elements Highly ductile

Ordinary systems, such as ordinary moment frames and ordinary concentrically braced frames, have fewer width-to-thickness requirements, because they are designed for higher forces and expected to yield less. Even there, some members, for example OCBF braces, must still meet specific limits.

What happens when a section is close to the limit

Sections that sit right at the boundary deserve attention. A flange ratio of 7.2 against a limit of 7.3 passes on paper, but mill tolerances on flange thickness, a later substitution or a change of grade can tip it over. Experienced designers leave a small margin for highly ductile members, and fabricators flag sections that are within a few percent of the limit when they review the drawings, so the Engineer of Record can confirm them before steel is ordered.

Checklist for reviewing member selection

  • Is each SFRS member's ductility class, moderately or highly ductile, shown on the drawings?
  • Do flange and web ratios meet Table D1.1 for that class, using Ry Fy for the specified grade?
  • For columns with high axial load, has the web limit been checked with the revised 2022 equations?
  • For HSS braces, has the design wall thickness been used?
  • For built-up members, are plate thicknesses specified so that the limits are met with tolerance?

How World Steel works with Table D1.1

World Steel designs and fabricates seismic steel for US projects in its IAS AC472-accredited plant in Vietnam. Our engineers check every member of the SFRS against Table D1.1 for the ductility class its system requires and show that class on the shop drawings. When a rolled section will not meet the limit, we propose a built-up alternative: welded plate girders, welded box columns and cruciform columns are proportioned plate by plate, cut on laser machines that handle steel up to 100 mm thick and welded by welders qualified to AWS D1.8.

Plate thickness and grade are verified against the EN 10204 3.1 certificate at intake, and every member can be followed in PEB Studio. Our design optimization service often finds the lightest section that still meets the ductility limit, saving tonnage without losing toughness. The Engineer of Record reviews and approves the member selection.

The next article covers two more Chapter D topics that keep a yielding member stable: beam stability bracing and the layout of protected zones.

Quick answers

What is a highly ductile member?

A member whose flanges and webs meet the stricter λhd limits of Table D1.1, so it can sustain large inelastic rotations or strains. Special moment frame beams and columns and special concentrically braced frame braces are typical examples.

What is the flange limit for a highly ductile I-shape?

For flanges of rolled or built-up I-shapes the highly ductile limit is 0.32 √(E/(Ry Fy)). For ASTM A992 steel that works out to a flange half-width to thickness ratio of about 7.3.

What changed in Table D1.1 in 2022?

AISC 341-22 adjusted the limits throughout the table and revised the equations for webs of I-shapes and channels and for the webs and walls of box sections, and clarified when the design wall thickness of HSS must be used.

Can a built-up section be proportioned to meet Table D1.1?

Yes. Built-up members let the designer choose flange and web thicknesses directly, which makes it easier to meet highly ductile limits on heavy beams and columns.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AISC 341-22 seismic design series

Twenty in-depth articles on the 2022 Seismic Provisions for Structural Steel Buildings: what each chapter asks of the design, the drawings, the shop and the inspector, and how World Steel engineers and fabricates seismic steel to it for US projects.

Chapter D
Members and connections

Ductile sections, bracing, protected zones, joints, splices and bases.

Chapter E
Moment frames

OMF, IMF, STMF, SMF and the cantilever column systems.

Chapter F
Braced frames and walls

Concentric and eccentric bracing, buckling-restrained braces, plate walls.

Chapters G–H
Composite systems

Steel and concrete working together, including the new CC-PSW/CF.

Chapters I–K
Fabrication, QA and testing

Shop and site rules, quality control and assurance, cyclic tests.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.