Skip to content
Seeking US contractor partners IAS AC472 ACCREDITED ★ METAL BUILDINGS ★ AC472 IAS AC472 accreditedIAS AC472
World Steel USA
Heavy welded built-up steel girders for a moment frame in the World Steel plant

Engineering and codes

Special moment frame design under AISC 341-22: joints, panel zones and continuity plates

The special moment frame is the most ductile steel moment frame in the US codes and the most demanding to detail. AISC 341-22 Section E3 keeps its core rules and updates continuity plates. Here is what an SMF asks of the designer, the fabricator and the inspector.

· 7 min read · World Steel USA engineering team

The special moment frame (SMF) is the steel system that gave seismic steel design its modern form. After the 1994 Northridge earthquake revealed brittle fractures in welded beam-to-column joints that were expected to be ductile, the US steel industry spent years testing, rethinking and rewriting the rules. The result is the SMF as defined in AISC 341 Section E3 and AISC 358: a frame designed for one of the lowest seismic forces in ASCE 7, R = 8, in exchange for the most demanding detailing of any steel moment frame. AISC 341-22 keeps the core of Section E3 and updates the rules for continuity plates. This article walks through what an SMF requires.

What an SMF is designed to do

Section E3.2 sets the basis of design. An SMF is expected to provide significant inelastic deformation capacity through flexural yielding of the beams and limited yielding of the column panel zones. Columns are designed to be generally stronger than the fully yielded and strain-hardened beams, so plastic hinges form in the beams near the columns, not in the columns themselves. Yielding at the base of the columns, where the frame meets the foundation, is accepted.

The benchmark is a story drift angle of 0.04 radian: 4 percent of the story height. A storey 4 m (13 ft) tall swaying 160 mm (6.3 in.) sideways, and back, and again, while every connection keeps its strength.

Strong column, weak beam

Section E3.4a contains the most famous rule in seismic steel: the moment ratio. At every beam-to-column joint, the sum of the projected plastic moments of the columns above and below must be greater than the sum of the projected expected moments of the beams framing in, ΣMpc/ΣMpb > 1.0.

The column side uses the columns' plastic moment reduced for axial load. The beam side uses the beams' expected flexural strength, based on Ry Fy and strain hardening, projected from the plastic hinge location to the column centerline. If the ratio fails, the designer increases the column, or reduces the beam, or uses a reduced beam section to lower the beam moment.

Exceptions exist, for example for columns with low axial load in single-storey buildings or the top storey, and for a limited share of columns in a storey, but they come with extra checks. The purpose is clear: a frame where columns hinge can form a storey mechanism and collapse; a frame where beams hinge spreads damage over many floors.

Members: highly ductile and well braced

SMF beams and columns must meet the highly ductile width-to-thickness limits of Table D1.1, so flanges and webs do not buckle locally under large cyclic rotations. Beams are braced to the highly ductile spacing of Section D1.2, with special bracing near plastic hinges unless the prequalified connection or test data says otherwise. Section E3.4c requires the beam-to-column connections themselves to be braced, so the column flanges cannot move out of plane at the beam flange levels.

The beam regions that yield are protected zones (Section E3.5c), extending from the column face to a distance set by the connection, for example through the reduced section of a reduced beam section connection.

Connections: proven by test or prequalification

Section E3.6 sets the connection rules.

Conformance demonstration

Every SMF beam-to-column connection must be shown to reach a story drift angle of 0.04 radian with a flexural resistance at the column face of at least 0.80 Mp of the beam. That is demonstrated either by using a connection prequalified under Section K1, which in practice means AISC 358-22, or by cyclic qualification tests under Section K2 on specimens that match the project's members.

AISC 358 includes connections such as:

  • Reduced beam section (RBS), with circular cuts in the beam flanges that move the hinge away from the column face.
  • Bolted unstiffened and stiffened extended end-plate connections.
  • Bolted flange plate connections.
  • Welded unreinforced flange-welded web (WUF-W).
  • Kaiser bolted bracket, ConXtech ConXL, SidePlate, Simpson Strong-Tie Strong Frame and other proprietary connections.

Each comes with limits on beam depth, weight, span-to-depth ratio, flange thickness, materials, continuity plates and welding.

Required shear strength

The connection's required shear strength (Section E3.6d) is a capacity-design force: twice the probable maximum moment at the hinge divided by the distance between hinges, plus the gravity shear. That makes shear tabs and web welds in SMF connections much heavier than gravity design alone would suggest.

Demand-critical welds

Complete-joint-penetration groove welds of beam flanges and webs to columns, column splice welds and column-to-base welds are demand critical. They use filler metal that meets the toughness and heat input envelope requirements of AWS D1.8, with backing removed and reinforced or left in place as the connection and D1.8 permit, weld tabs removed and access holes made to the required profile.

Panel zones

The panel zone is the part of the column web bounded by the beam flanges. It carries large shear when beams on either side bend in the same direction. Section E3.6e sets its required strength from the beams' probable moments and allows limited panel zone yielding, which spreads energy dissipation but must be controlled.

When the column web is too thin, doubler plates are welded to it. AISC 341 sets a minimum thickness for the panel zone, including doublers, roughly the panel's depth plus width divided by 90, so it does not buckle in shear, and sets rules for welding the doublers to the column flanges and to each other. Doublers are a large share of the welding at an SMF joint, so designers often choose a heavier column instead.

Continuity plates: the 2022 update

Continuity plates are horizontal plates in the column, aligned with the beam flanges, that carry the beam flange forces through the column and stiffen the column flanges. Section E3.6f says when they are needed, which depends on the column flange thickness relative to the beam flange, and how thick they must be, with one-sided and two-sided connections treated differently.

AISC 341-22 made two changes:

  1. Width-to-thickness limits for continuity plates were introduced, so the plates themselves do not buckle under the high forces they receive.
  2. Welding requirements were relaxed for continuity plates in some cases. Where the plate force can be developed without a complete-joint-penetration weld to the column flange, less demanding welds are permitted.

For fabricators, the second change matters most. CJP welds of continuity plates to column flanges, with their bevels, backing, back-gouging and ultrasonic testing, are among the slowest operations at an SMF joint. Allowing fillet or partial penetration welds where the force permits shortens shop time and testing at many joints without reducing the plate's ability to do its job. The corner clips that keep welds out of the column k-area still apply.

Column splices

SMF column splices (Section E3.6g) must develop at least the expected flexural strength of the smaller column and the required shear, are located away from the beam connections and use demand-critical CJP welds or an equivalent bolted design. The splices and bases article covers them in detail.

A fabricator's view of an SMF joint

For a shop, an SMF joint is a sequence of controlled operations:

  1. Cut and bevel the beam, including the RBS profile or end-plate, to tolerance.
  2. Prepare the column with continuity plates, clipped at the corners, and doublers where needed.
  3. Make demand-critical welds to qualified procedures, with preheat and heat input controlled.
  4. Remove backing and weld tabs as specified, grind and add reinforcing fillets.
  5. Inspect visually, then ultrasonically test CJP welds and magnetic particle test where Chapter J requires.
  6. Keep protected zones clear and mark them where requested.

Choosing shop-welded, field-bolted details, such as column trees with beam stubs, or bolted AISC 358 connections, moves the demand-critical work into the plant.

Where SMF is the right choice

The SMF is permitted without height limits in every Seismic Design Category, which makes it the default moment frame for mid-rise and high-rise steel buildings in California, the Pacific Northwest, Alaska, Utah and other high-seismic regions. It suits buildings that need open bays without braces, such as offices, hospitals, laboratories and parking structures, and it combines well with braced frames or plate shear walls in dual systems. Its weaknesses are drift and cost: because R is high and Cd is 5.5, drift limits often govern member sizes, and the connections are the most expensive of any moment frame. A careful comparison with an intermediate frame, a braced frame or a dual system is worth doing early.

How World Steel designs and fabricates special moment frames

World Steel designs and fabricates SMF steel for US multi-storey and industrial projects in its own IAS AC472-accredited plant in Vietnam. We design to AISC 341-22 Section E3 with AISC 358 connections, check strong-column weak-beam ratios and panel zones, and choose continuity plate and doubler details that the 2022 rules allow, to save welding where it is safe to do so. Heavy columns are fabricated as welded box columns or cruciform columns when rolled shapes do not fit.

Shop welding procedures and welders are qualified to AWS D1.8; demand-critical welds are inspected and ultrasonically tested as Chapter J and the specification require; and protected zones are shown on the shop drawings and marked on the steel on request. With a plant capacity of 2,500 t of steel a month and real-time tracking in PEB Studio, we supply SMF packages for large projects. The Engineer of Record reviews and approves the design, and the US contractor completes the frame on site.

The next article covers a system that received full provisions in 2022: ordinary and special cantilever column systems.

Quick answers

What drift must a special moment frame connection reach?

An SMF beam-to-column connection must sustain a story drift angle of at least 0.04 radian while keeping a flexural resistance at the column face of at least 80 percent of the beam plastic moment, demonstrated by prequalification or cyclic testing.

What is the strong-column weak-beam rule?

At each beam-to-column joint, the sum of the column plastic moments must exceed the sum of the beam expected moments, so hinges form in the beams rather than the columns, with limited exceptions.

What changed for SMF in AISC 341-22?

The 2022 edition added width-to-thickness limits for continuity plates and relaxed some of the welding requirements for continuity plates, reducing shop work at many joints without weakening them.

Are SMF connections always welded?

No. AISC 358 includes bolted connections such as the extended end-plate and bolted flange plate, and proprietary bolted connections, which avoid field welding of the beam-to-column joint.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AISC 341-22 seismic design series

Twenty in-depth articles on the 2022 Seismic Provisions for Structural Steel Buildings: what each chapter asks of the design, the drawings, the shop and the inspector, and how World Steel engineers and fabricates seismic steel to it for US projects.

Chapter D
Members and connections

Ductile sections, bracing, protected zones, joints, splices and bases.

Chapter E
Moment frames

OMF, IMF, STMF, SMF and the cantilever column systems.

Chapter F
Braced frames and walls

Concentric and eccentric bracing, buckling-restrained braces, plate walls.

Chapters G–H
Composite systems

Steel and concrete working together, including the new CC-PSW/CF.

Chapters I–K
Fabrication, QA and testing

Shop and site rules, quality control and assurance, cyclic tests.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.