Hurricane uplift load path: from roof screw to anchor rod

A steel building on the hurricane coast holds down only as well as its weakest link. This is the hurricane uplift load path, traced from the roof screw to the anchor rod, with what to check at each step.

· updated November 24, 2026 · 5 min read · World Steel USA engineering team

On the Gulf and Atlantic coasts, the question a hurricane asks a steel building is simple: can every part of it be held down? Wind passing over a roof pulls up on it, and that pull has to travel through a chain of parts until it reaches the ground. This article follows the hurricane uplift load path link by link, from the screw in the roof panel to the anchor rod in the footing, and lists what a contractor or reviewer should see on the drawings at each step.

It does one job. How large the wind pressures are, zone by zone, is covered on our high-wind design guide. Which coastal rules apply at your address, from wind-borne debris regions to the Florida High-Velocity Hurricane Zone, is covered on the hurricane coast guide. Here we assume the design pressures are set and approved by your Engineer of Record, and ask whether the building can carry them all the way down.

Why uplift governs on the coast

Most of the year a roof carries gravity: dead load, snow, maintenance traffic, collateral loads. In a hurricane the direction flips. Suction over the roof, plus internal pressure if wind gets inside, pushes the roof up, and the net uplift can exceed the weight of the roof several times over.

ASCE 7 load combinations make this sharper on purpose. For uplift checks the code counts only part of the dead load (0.6D with wind in allowable stress design, 0.9D in strength design), because the weight you rely on to hold the building down might be less than the drawings say. On a light metal building, where the roof weighs little more than its panels and purlins, very little weight is left to resist. Every link has to be connected for tension, not simply resting in place.

Panel to purlin

The chain starts with the panel fasteners or, on standing seam roofs, the concealed clips. Three checks matter here:

  • Pull-over and pull-out. A screw can pull through the panel or out of the purlin. Both capacities are checked, and the lower one governs.
  • Zone spacing. Roof corners and edges see the highest suction, so the fastener pattern tightens there. The pattern must be drawn zone by zone, not as a single note.
  • Clip capacity. For standing seam, the clip and its attachment are often the weak point, not the panel. Ask for the tested capacity of the clip used.

Trims at eaves, rakes and ridge belong to this link too. A loose trim lets wind get under the panel edge and start a peel.

The purlin and its bracing

Under gravity, the top flange of a Z or C purlin is in compression and the roof panel braces it. Under uplift the bottom flange goes into compression, and nothing braces it unless the design adds bridging, flange braces or anti-roll devices. A purlin that is strong enough on paper can still twist and fail if that inner flange is free.

What to look for: bridging lines on the roof framing plan, lap lengths over the frames, and a note on which purlins in edge and corner zones are heavier or more closely spaced.

Purlin to rafter

Each purlin passes its share of uplift into the frame through a clip or a seat and bolts. Under uplift those bolts are in tension or combined tension and shear, and the clip bends. Corner-zone purlins deliver the largest reactions, so their clips may differ from the field. Flange braces from purlin to rafter also need to be present where the rafter's own inside flange goes into compression.

Rafters and columns in reverse bending

A rigid frame designed for snow bends one way; under net uplift it bends the other. The inside flange of the rafter near the knee, normally in tension, can go into compression, and the frame needs flange bracing where the uplift case asks for it. Columns that usually carry compression can see tension. These checks are part of the main frame design in our analysis model, run with every governing combination together, not only the gravity ones.

Walls, doors and internal pressure

Wall girts carry suction on the leeward and side walls and transfer it to the columns. A large overhead door that fails or is left open changes everything above it: the building becomes partially enclosed, internal pressure rises and the roof is pushed up from inside as well as pulled from outside. The door jambs, header and the frames beside them are designed for the reactions of a door rated to the design pressure. The door rating itself comes from its manufacturer.

Base plates, anchor rods and the footing

The last steel link is the column base. Net uplift puts the anchor rods in tension, and on light, long-span buildings this often governs the anchor design, ahead of shear. Check that:

  • the base plate and its welds are designed for the uplift reaction, not just bearing;
  • the anchor rod size, grade and projection on our anchor rod plan match the foundation drawings;
  • the footing has the weight or the anchorage to resist net uplift, a check made by the foundation engineer with our base reactions.

Confirm the anchor rod layout before the concrete is poured. Fixing a mismatch after the pour is slow and costly on any job, and slower still in storm season.

Overhangs, canopies and parapets

Parts that stick out get loaded from both sides at once. A canopy sees suction on top and pressure underneath, so its net uplift is far higher than the wall beside it. Canopy rafters, their connections to the column and the back-span effect on the main frame each need their own check. Parapets and roof screens add a lever arm at the top of the wall.

What to ask for on the drawings

Link What the drawings should show
Panel to purlin Fastener or clip type and spacing for each roof zone
Purlins Sizes and spacing by zone, laps, bridging lines
Purlin to rafter Clip and bolt details, flange braces
Frames Uplift combinations in the calculations, inside-flange bracing
Walls and doors Girt sizes by zone, door jamb and header details, door design pressure
Base and anchors Uplift reactions, base plate details, anchor rod plan

World Steel shows these on its drawings, with shop drawings included at no extra cost, so the crew of the US contractor, our customer, builds what the calculation assumed. Our plant fabricates 2,500 metric tons of structural steel a month, so a distribution center on the coast gets the same zone-by-zone detailing as a small shop.

Where this fits in the wind guides

Read this article with the high-wind design guide, which explains how each roof and wall zone gets its pressure, and the hurricane coast guide, which maps the coastal rules. For Florida projects, the Florida structural steel solutions set covers the state code and the High-Velocity Hurricane Zone. No building is hurricane-proof, and no rating is claimed here; a complete load path is what lets the design do its work.

Quick answers

Where does a hurricane uplift load path usually break first?

At the top: panel fasteners and trims at roof corners and edges, where the suction is highest. Once the envelope opens, wind pressurizes the inside of the building and every link below sees more load.

Why do anchor rods often govern on light coastal buildings?

A metal building is light, so there is little dead load to hold it down. Net uplift after the code takes only part of the dead load can be larger than the shear, which makes tension in the anchor rods and the weight of the footing the deciding checks.

Keep building your steel plan

Go further on USPEB.com

Wind and hurricane guides

One storm, four questions

Each guide answers one part of designing a steel building for strong wind. Start with the question you have now.