Release rules
Four rules no schedule can bend
They come from our fabrication method statement and apply to every member of every job, large or small.
A missing signature stops the member
If any earlier line on the tag is unsigned, the member is put on hold and checked with the people responsible for that station. Work on it cannot continue.
Three people sign each station
The worker who did the job, the foreman who checked it and the QC inspector who accepted it, each with a date, so every step has a name behind it.
On hold is visible
A member waiting on a decision carries an on-hold sticker, so it cannot be picked up by mistake and sent to packing.
Accepted is visible too
After the final inspection is accepted, QC attaches the acceptance sticker that releases the member for packing and delivery.
Nonconformance
Found, reported, decided, closed
Found
An inspector finds a defect at any checkpoint, or a member arrives at a station with a step missing.
Reported
A nonconformance report records the member, the requirement, what was found and photos.
Dispositioned
Repair, remake or use as is. Anything that would change the design, or accept steel outside the specification, goes to your Engineer of Record.
Closed
The repair is re-inspected and the report closed. Only then can the member be released.
Before the doors close
The last check happens at the container
- Members counted and checked against the packing list and the erection sequence they ship in
- Coating and edges looked over for handling damage, which is touched up before loading
- Bundles, dunnage and lashings checked by QC before the goods go into the container
- Photos and video taken at each stage of loading and stored with the shipment record
- Seal applied and its number recorded; serious defects stop the shipment under a nonconformance report
Manufacturing Data Record
What ships with your steel
The paper trail of every checkpoint, compiled per job and indexed so your inspector, your Engineer of Record or the building official can find any member’s history.
In PEB Studio you can follow the same releases in real time from the US: each member’s stages appear as QC releases them, with its quality history.
QC and QA
Who checks what at this checkpoint
US practice separates the fabricator’s quality control from the quality assurance carried out for the owner. World Steel runs the QC; your side decides how much QA it adds, and the Engineer of Record sets what is acceptable.
World Steel QC
Quality control: the fabricator
Performs the final inspection, checks every signature on the process control tag, closes or escalates open nonconformances, releases the member and compiles the records.
Your inspector
Quality assurance: owner, special or third-party inspector
Can hold final release of the whole job or of chosen members, inspect before packing in Vietnam or by video, and review the data record before shipment.
Your Engineer of Record
Sets the criteria, rules on what changes the design
Decides on any nonconformance that would change the design or accept steel outside the specification, before the member is released.
Inspectors can attend in Vietnam, join hold points live on Zoom or Microsoft Teams, or be given remote access to the records on request. The plant itself is audited twice a year under IAS AC472, with periodic plant inspections by Smith-Emery Laboratories.
Questions from US contractors and inspectors
Questions about final inspection and release
Ask us anything else about this checkpoint before you award, or during the job through your project manager.
Can a member skip a checkpoint if the schedule is tight?
No. A member with an unsigned line on its process control tag is put on hold. It cannot be worked on further, and it cannot be released for packing, until the missing step is done and signed.
Can we inspect before the steel is packed?
Yes. Final release can be a hold point in the ITP for the whole job or for selected members. Your inspector can attend in Vietnam or live over Zoom or Microsoft Teams.
What records do we receive?
A Manufacturing Data Record with the signed ITP, mill certificates, welding qualifications, inspection and NDT reports, dimension and coating records, nonconformance reports and packing lists.
How long do you keep inspection records?
Welding and dimension inspection reports are kept for at least three years under our procedures, and you receive your own copy with the shipment.
Can we see the status of each member before it ships?
Yes. In PEB Studio each member’s stages are shown as QC releases them, with its quality history, so you can follow release in real time from the US.
What if damage is found when the steel arrives?
Photograph it before the driver leaves and send it to your project manager. Because each member is tied to a bundle, a container and photos taken at loading, the cause can be traced and the fix agreed quickly.