QC checkpoint: dimensional check

Measured in the shop so it bolts up in the field

An erector with a crane on the hook has no time for a beam that is 10 mm short or a hole that misses its bolt. Before a member goes to blasting, QC measures its length, holes, end plates and straightness against the shop drawing and the tolerances your contract names, and writes the numbers down.

Quality inspector taking dimensions on a finished steel member
Measured againstthe shop drawing · AISC 303

What we measure

Six measurements between welding and blasting

Each one prevents a particular problem in the field. All six are checked against the shop drawing on every member, and the numbers go into the Dimension Inspection Report.

overall length, end-plate face to face end plate: squareness, flatness, hole group clip positions and piece mark sweep and camber

Overall length

Tape along the member between working points or end-plate faces, compared with the shop drawing.

A long or short member pushes every connection down the line out of place.

Hole location

Edge distance, pitch, gauge and group position measured from the working lines.

Holes that line up are the difference between bolting and reaming on site.

Hole size

Diameter checked for standard, oversized or slotted holes as detailed.

Hole type is part of the connection design, especially for slip-critical joints.

End and base plates

Squareness to the member axis, flatness at the contact face, and the plate’s position.

End plates that are out of square open gaps a bolt cannot close.

Camber and sweep

Straightness in both planes against a taut line or reference, and specified camber where drawn.

A swept column or rafter throws the frame out of plumb and line.

Section and attachments

Depth, flange width, stiffener and clip positions, and piece marks.

Purlin clips and brackets in the wrong place stop secondary steel from fitting.

Where the limits come from

Tolerances quoted from a source, never from habit

The tolerance standard your contract names is written into the ITP. These are the usual sources on US structural steel work; the most demanding applicable one governs.

AISC 303, Section 6.4

Length of fabricated members

For members with both ends finished for contact bearing, 0.8 mm (1/32 in). For other members, 1.6 mm (1/16 in) up to 9 m (30 ft) and 3.2 mm (1/8 in) over 9 m (30 ft).

ASTM A6/A6M

Rolled shapes and plate as delivered

Straightness, section size and thickness variations the mill must meet, which become the starting point for fabricated members.

AWS D1.1

Welded built-up members

Straightness, flange tilt, web flatness and depth of members made from plate, the main members of most metal buildings.

AISC 360 and RCSC

Bolt holes

Nominal sizes of standard, oversized and slotted holes, which set how far a hole may be from its bolt.

MBMA Metal Building Systems Manual

Metal building systems

Fabrication tolerances commonly applied to primary frames and secondary members of metal buildings.

Your specification and drawings

Anything tighter

Where your Engineer of Record specifies closer tolerances, for example for crane runways or exposed steel, they govern and are written into the ITP.

On your site

What a member that fits saves your erector

No reaming on the hook

Reaming holes in the field takes time, needs approval and can weaken a connection. Holes checked in the shop avoid it.

No cutting and rewelding

A short member or a misplaced clip found on site means torches, welders and a lost day. Found in the shop, it is a quick fix.

Erection stays on sequence

When pieces fit the first time, the crew follows the erection drawings in order and the crane keeps moving.

Hands-on check of a fabricated web plate on the shop floor
Hands-on check of a fabricated web plate on the shop floor. (IAS AC472 periodic audit, April 2022)
Painted beams with bolted end plates resting on stands below an overhead crane
Coated beams with end plates welded on, waiting for release in the Vietnam plant.

QC and QA

Who checks what at this checkpoint

US practice separates the fabricator’s quality control from the quality assurance carried out for the owner. World Steel runs the QC; your side decides how much QA it adds, and the Engineer of Record sets what is acceptable.

World Steel QC

Quality control: the fabricator

Measures every member against the shop drawing after welding and before blasting, records the Dimension Inspection Report and keeps it for three years.

Your inspector

Quality assurance: owner, special or third-party inspector

Can witness dimensional checks in the plant or by video, spot-check members against the drawings, and review the dimension reports.

Your Engineer of Record

Sets the criteria, rules on what changes the design

Names the tolerance standard in the specification and sets any tighter tolerances, for example for crane runways or architecturally exposed steel.

Inspectors can attend in Vietnam, join hold points live on Zoom or Microsoft Teams, or be given remote access to the records on request. The plant itself is audited twice a year under IAS AC472, with periodic plant inspections by Smith-Emery Laboratories.

Questions from US contractors and inspectors

Questions about dimensional inspection

Ask us anything else about this checkpoint before you award, or during the job through your project manager.

Which tolerances do you work to?

The ones your contract names: AISC 303 for fabricated members, ASTM A6 for mill material, AWS D1.1 for welded built-up members and MBMA practice for metal building systems, unless your Engineer of Record specifies tighter values.

Is every member measured?

Yes. Every member is checked against its shop drawing by QC before it goes to blasting, and the results are recorded in the Dimension Inspection Report.

Do you trial-assemble connections?

Where your specification asks for a shop trial assembly, for example of a complex truss or a splice, it is planned as a hold point in the ITP. Otherwise, holes and end plates are checked member by member against the drawings.

Can our inspector check dimensions remotely?

Yes. Dimensional checks can be witnessed live over Zoom or Microsoft Teams, and the dimension reports are available through remote access on request.

What happens when a member is out of tolerance?

It is held, corrected by straightening, re-drilling or remaking the part, and measured again before it moves on. The correction stays in its record.

Do you check secondary members too?

Yes. Purlins, girts, clips and brackets are checked for length, hole positions and piece marks, because they are what an erection crew handles most.