At the joint
Six things checked on every fitted joint
Each is measured against the welding procedure for that joint and the shop drawing, and the limit comes from a written source, not from the fitter’s eye.
Root opening
The gap at the root of a complete-joint-penetration groove weld is no more than 3 mm (1/8 in), or the opening the WPS states.
WPS and AWS D1.1 joint tolerances
Root face
The land left at the root suits the process and the backing, so the root fuses without burning through.
WPS joint detail
Groove angle
The bevel is cut to the angle in the WPS, giving the welder room to reach the root and fuse the sidewalls.
WPS joint detail
Alignment
Abutting parts line up, so loads pass through the weld as designed rather than around an offset.
AWS D1.1 alignment limits
Backing
Steel backing, where used, is continuous and tight to the parts, with no gap that could trap slag.
AWS D1.1 and the WPS
Cleanliness
Joint faces are free of loose mill scale, rust, oil, paint and moisture before welding.
AWS D1.1 surface preparation
AISC 360, Chapter N
The checklist the US code sets before welding
AISC 360 lists inspection tasks to perform before, during and after welding. These are the ones that fall before the arc is struck, and they are what our QC inspector works through at fit-up.
Photo
Prior to welding
- The WPS for the joint is available at the workstation
- Welding consumables carry their manufacturer’s certification and match the WPS
- Material identification is in place: type and grade
- The welder is qualified for the process and position
- Groove welds: joint preparation, root opening, root face and bevel within tolerance
- Groove welds: joint faces clean, tack welds sound, backing type and fit correct
- Fillet welds: parts brought into contact, with any gap within the code limit
- Weld access holes: shape and finish as detailed
Three signatures
Who signs the fitting station
Every member carries a process control tag. At fit-up, three people sign it before welding can start, each with a date.
Fitter
Lays out center lines and working points from the drawing, fits the parts, tacks them and checks the main dimensions and joint preparation.
Foreman
Rechecks the main dimensions and the joint preparation before letting welding begin, and signs the process control tag.
QC inspector
Checks the full dimensions, hole positions and diameters and the joint preparation against the drawing, signs the tag and records the Dimension Inspection Report.
Tack welds
Small welds, held to the same care
- Tack welds hold parts firmly in place and are made by qualified welders under the same procedure care as the final weld.
- No tack welds at the ends of a weld line or at corners, where they would interfere with the start and stop of the final weld.
- Slag is removed from every tack, and arc strikes on the parent metal are avoided.
- Where stitch welds are specified, the seam is marked before fitting so the tacks fall inside the final welds.
- For fillet welds, AWS D1.1 limits the gap between parts, and the leg size is increased by the gap when it exceeds 2 mm (1/16 in).
QC and QA
Who checks what at this checkpoint
US practice separates the fabricator’s quality control from the quality assurance carried out for the owner. World Steel runs the QC; your side decides how much QA it adds, and the Engineer of Record sets what is acceptable.
World Steel QC
Quality control: the fabricator
Checks every fitted assembly against the drawing and WPS before final welding, signs the process control tag and records the dimensions.
Your inspector
Quality assurance: owner, special or third-party inspector
Can set the first fit-up of each member type as a hold point in the ITP and inspect it in Vietnam or by live video.
Your Engineer of Record
Sets the criteria, rules on what changes the design
Approves the joint details on the drawings and any change of joint geometry the shop proposes.
Inspectors can attend in Vietnam, join hold points live on Zoom or Microsoft Teams, or be given remote access to the records on request. The plant itself is audited twice a year under IAS AC472, with periodic plant inspections by Smith-Emery Laboratories.
Questions from US contractors and inspectors
Questions about fit-up inspection
Ask us anything else about this checkpoint before you award, or during the job through your project manager.
Why inspect fit-up separately from the finished weld?
Because a finished weld hides its root. Once the joint is welded out, a wrong root opening or bevel can only be found by testing, and it can only be fixed by cutting the weld out. At fit-up it takes minutes to correct.
What root opening do you allow on full-penetration welds?
No more than 3 mm (1/8 in) on complete-joint-penetration fit-ups, or the opening the welding procedure states for that joint. Anything outside is corrected and re-inspected before welding.
Who signs off fit-up?
The fitter, the foreman and a QC inspector each sign the process control tag at the fitting station. A member with a missing signature cannot move to welding.
Can our inspector check the first assembly of each type?
Yes. Mark the first fit-up of each member type as a hold point in the ITP, and production waits for your inspector, in person or live by video, before welding out.
What happens when a fit-up is out of tolerance?
It is corrected straight away by the fitting team and called back for re-inspection. It does not proceed to welding until QC accepts it.
Do you check weld access holes?
Yes. Their shape and finish are checked against the detail before welding, as AISC 360 lists among the tasks to perform prior to welding.
Keep reading
Where this checkpoint connects
Building something with heavy joints?
Send the connection details for your job. Our engineers will match each joint to a qualified procedure and plan the fit-up checks your inspector can witness.