Where defects get caught
Six places a problem is stopped before it reaches your site
At each station
The process tag needs three signatures: the worker, the foreman and QC. A missing one stops the member there.
On the shop floor
QC marks defects in yellow paint marker on the steel itself, and the punch list is closed with photos.
During welding
QC checks voltage, current and travel speed against the WPS at random, not only on the finished weld.
At final release
Only a member that cleared every earlier check gets the acceptance sticker that lets it be packed.
At the container door
QA/QC checks the packing before the container is closed, and raises an NCR if goods fail.
At audits and witness points
Findings from IAS audits and from your inspector go into the same log and are closed the same way.
One nonconformance report
From the hold sticker to the acceptance sticker
Hold
The member gets an on-hold sticker and is set aside so it cannot be packed by mistake.
Report
QC raises a nonconformance report: piece mark, what failed, against which requirement, with photos.
Cause
Production and QC find out why it happened, so the same defect is not repeated on the next member.
Repair
Repaired to an approved procedure, for example a weld repair under the WPS, then inspected again.
Remake
Scrapped and fabricated again from traceable material when repair is not the right answer.
Use as is
Only with your written acceptance through your Engineer of Record. We never decide this alone.
Re-inspected and photographed
The same check that failed is made again, and the result is photographed against the piece mark.
Closed and released
QC closes the NCR, the acceptance sticker goes on, and the member may be packed.
Every NCR on your job is visible in PEB Studio and closed NCRs go into your data book. How welds are inspected: weld inspection and NDT.
Hard lines
Four things that never happen at our plant
Questions
Questions about nonconformances
Will we be told about nonconformances on our job?
Yes. Every NCR on your job is logged in PEB Studio against its piece mark, with photos, the disposition and the re-inspection, and the closed NCRs go into your data book.
Who decides whether a defect can be accepted as is?
You do, through your Engineer of Record. World Steel can repair to procedure or remake on its own decision, but accepting a nonconforming member as is always needs your written acceptance.
Can a member with an open NCR be shipped?
No. PEB Studio will not let a member with an open inspection or NCR be scanned into a bundle or onto a packing list, and the acceptance sticker that releases it for packing comes only after the NCR is closed.
How are weld repairs made?
To an approved procedure under the job’s WPS, by a qualified welder, followed by the same inspection that found the defect, plus any NDT your specification requires.
What happens if steel arrives damaged on site?
Your crew photographs it when checking in by scanning the labels, and we work with you on the replacement or repair. Site work itself is the US contractor’s scope.
Ask how a defect on your job would be handled
Send your specification. We show you the hold points, the NCR route and what your Engineer of Record would see, from a plant that fabricates 2,500 metric tons a month.