Design step: proposal and pricing

A proposal that says what is in the price, and what is not

An estimator and an engineer write every World Steel proposal together. You receive proposal drawings, a scope letter that draws the line between our supply and the work that stays local, and a price on the Incoterm you chose. Nothing that matters is left to a footnote.

World Steel USAScope of supply

Issued for quotation
Project
Your project name and site address
Code basis
IBC edition and amendments your jurisdiction enforces
Drawings
Proposal drawings, revision for quotation
Delivery term
The Incoterm you chose, with the named place
Importer of record
Named in writing before you sign
Shop drawings
Included at no extra charge

Estimator and project engineer, World Steel

The scope letter

Supplied by World Steel, and supplied by others

The letter is the heart of every proposal. Each line says which side of the scope an item sits on, so your bid carries no gap and no double count.

Supplied by World Steel

Primary framing. Built-up and hot-rolled columns, rafters, beams and frames, with their connection plates and stiffeners.
Secondary framing. Cold-formed purlins, girts and eave struts, flange braces, sag rods and bridging.
Bracing. Rod, angle or portal bracing and wind columns, with every connection detailed.
Envelope, when in scope. Roof and wall sheeting, trims, gutters, downspouts and closures, with fasteners by zone.
Bolts and hardware. Structural bolts, nuts and washers for steel-to-steel connections, bagged and labeled by connection.
Coating. The surface preparation and paint system named in the letter, or galvanizing where specified.
Engineering. Design calculations, approval drawings and the Design Report for your Engineer of Record.
Detailing. Shop drawings, erection drawings and the Tekla IFC model, on every project at no extra charge.
Export packing. Bundles, cradles and containers packed in erection sequence, with packing lists by piece mark.

Typically by others

Foundations. Foundation design, embeds, setting the anchor rods and pouring concrete.
Erection. Erection, cranes, temporary bracing and site safety, by your erector.
Approval and seal. Review and approval of our drawings, the PE seal and the permit, by your Engineer of Record and you.
Special inspection. Field inspections the building official requires, and any third-party testing beyond our plant program.
US customs and trucking. Customs entry and inland freight, unless the Incoterm you chose puts them on our side.
Other trades. Doors and windows not listed, MEP, fire protection, slab and site work.

Every project can move a line from one column to the other. Anchor rods, doors and sheeting are the items that move most often, and the letter always says where they landed.

Proposal drawings

Drawings that show what the price buys

For projects World Steel designs, the proposal comes with drawings drawn for quotation: a general arrangement, the frame lines and typical cross-sections, sidewall and endwall elevations with the openings we allowed for, and clouds around anything we assumed.

They are not approval drawings. Their job is to let you, your architect and your estimator check that we priced the building you meant, before anyone signs. After the contract, they grow into the approval set and the Design Report.

See every drawing stage

How a steel price is built

Six things that move the number

We never publish prices, because no two jobs share them. What we do publish is how the price is put together, so you can compare proposals line for line.

Steel weight by member type

Built-up plate members, hot-rolled sections and cold-formed secondary members cost differently per kilogram, so the weight is broken out by type, not quoted as one lump.

Plate and coil at time of order

Steel is bought against the approved design. The proposal states when the material price is fixed and what would reopen it.

Fabrication content

Moment connections, cambered rafters, curved members, cutouts and many unique pieces add shop hours that a simple weight figure hides.

Surface preparation and coating

Blast standard, primer, intermediate and finish coats, or hot-dip galvanizing: the system the owner expects has to be the one that is priced.

Packing and container count

Long members, crated hardware and sheeting bundles decide how many containers or breakbulk lots the job ships in.

Delivery term and duties

Freight, insurance, US customs entry and duties land on one side or the other depending on the Incoterm, and on who acts as importer of record.

Proposal drawings, a real sample

Sample proposal drawings for a US steel structure

Free download: the proposal drawings World Steel sends with a quotation: general notes, plans, elevations and sections.

PDF · 12.1 MB · 15 pages · English

Alternates

Options worth asking for in the proposal

An alternate priced next to the base scope lets the owner decide with numbers in hand. Our engineers suggest the ones that suit your building; your Engineer of Record has the final word.

Bay spacing and frame lines

Moving frame lines a little can shorten purlin spans and remove a frame without changing how the building works.

Tapered versus straight members

Web-tapered rafters and columns put steel where the moment is. Straight members can suit cranes, mezzanines or simpler connections.

End wall framing

Post-and-beam end walls are lighter; a full frame at the end wall allows a future expansion without new steel.

Coating system

A different primer or a galvanized option for exposed members, priced side by side so the owner can choose.

Purlin depth and laps

Deeper purlins with longer laps can carry more load per kilogram and reduce the number of lines.

Shipping split

Packing and lot options that follow how your erector plans to build, so steel arrives in the order it is needed.

Who owns this step

Clear lines between our scope and yours

World Steel designs and fabricates the steel structure. Approval, the PE seal, the permit and the erection stay with the US contractor and the Engineer of Record they appoint.

World Steel

Designs, details and fabricates the steel in Vietnam

Prepares the proposal drawings and the scope letter, prices the steel, states every assumption and exclusion, and names the Incoterm and the importer of record.

Your Engineer of Record

Reviews, approves and seals for your permit

Checks that the design criteria in the letter match what the jurisdiction will accept and flags any load or code edition that must change before approval.

The US contractor, our customer

Submits, builds the foundations and erects

Compares the letter with the bid documents, chooses the Incoterm and alternates, and confirms who imports and who erects before signing.

Questions from US contractors

Questions about proposals and pricing

Why are there no prices on your website?

Every steel price depends on the design loads at your site, the member mix, the coating, the delivery term and the market for plate and coil when the steel is bought. A number on a web page would be wrong for almost every job, so each project gets its own written price.

Is the structural design included in the price?

Yes. For projects World Steel designs, the calculations, approval drawings and Design Report are part of the supply. Your Engineer of Record reviews and approves them, and the PE seal stays with your side.

Do shop drawings cost extra?

No. Shop drawings, erection drawings and the IFC model of the steel are included on every project at no extra charge, whether we design the steel or fabricate to your engineer’s design.

Can you quote delivered to our site, duties paid?

We can quote on the Incoterm you need, and the proposal states who acts as importer of record. If you prefer to import yourself, a term such as FOB or CIF leaves customs and duties with your broker.

Can the price be split by building or phase?

Yes. On campuses and phased jobs the proposal can price each building or phase on its own line, with the production and shipping lots to match.

What happens if the design changes after we sign?

The change is logged and its effect on drawings, schedule and price is sent to you in writing. Nothing is fabricated on a verbal instruction.

Keep reading

Where this step connects

Want a scope letter for your next bid?

Send the drawings and tell us the delivery term you work with. You will get proposal drawings and a letter that names every item we supply and every item that stays with your team.