Transmittal and project data
Project address, occupancy and construction type, building area and height, code edition, and the list of documents in the package with their revisions.
US contractor, with our data
Tab by tab
This is the order we assemble the steel part of the package in. Plan reviewers find the design criteria before the calculations, and the calculations before the sheets that rely on them.
Project address, occupancy and construction type, building area and height, code edition, and the list of documents in the package with their revisions.
US contractor, with our data
The frozen design basis on one page: risk category, wind, snow, seismic, collateral and live loads, deflection limits and material grades.
World Steel, confirmed by your EOR
The Design Report with an index up front: load derivation, frame and bracing analysis, member checks, purlin and girt checks, connections, base plates and reactions.
World Steel, reviewed and sealed by your EOR
The approved set: general notes, anchor rod plan and reactions, framing plans, sections, elevations, bracing and typical details, all on one revision.
World Steel, reviewed and sealed by your EOR
Data sheets for roof and wall panels, fasteners, insulation and accessories in our supply, and evaluation reports where the product maker holds them and the reviewer asks for them.
World Steel and product makers
World Steel’s IAS AC472 accreditation certificate, the quality manual summary and the material certificate format, for the special inspection discussion with the building official.
World Steel
Where the metal building is a deferred submittal, the items deferred and how they will be reviewed by your Engineer of Record before they reach the building department.
Your EOR, with our input
Deferred submittals
On many US projects, the metal building or the structural steel is handled as a deferred submittal under IBC Section 107.3.4.1. The building official agrees that part of the design can be submitted after the main permit, and the Engineer of Record lists those items on the permit drawings.
Deferral moves the deadline, not the review. The deferred documents still go to your Engineer of Record first, who checks that they fit the building design, then on to the building department. We prepare them so they can move through both reviews without a second round of questions.
Shop inspection
IBC Chapter 17 requires special inspection of structural steel, and Section 1704.2.5 lets the building official rely on an approved fabricator program instead of sending inspectors into the shop. World Steel is accredited under IAS AC472, and its certificate and quality documents travel in the package.
Whether your jurisdiction accepts that program is the building official’s decision, not ours. The package gives your team what it needs to ask early, and witness inspections at our plant can be arranged in person or online if the answer is no.
IAS AC472 accreditationPlan check
Plan check comments come to the US contractor. The ones about the steel come to us, and we turn them around as a package your Engineer of Record can adopt.
For every structural comment on the steel, our engineer drafts a response your Engineer of Record can adopt, edit or reject.
Where a comment changes the design, the calculations and sheets are revised, clouded and reissued for your engineer to review and seal again.
Calculations, drawings and the comment response all carry the same revision, so the reviewer never compares mismatched documents.
Jurisdictions that ask for more
The core of the package is the same everywhere. These are the places where the code, the review path or the product rules add to it.
The California Building Code adds its own amendments, and state agencies review schools and hospitals separately from city building departments. Seismic detailing and AWS D1.8 welding records carry more weight.
California steel solutionsThe Florida Building Code applies statewide, and envelope products in the High-Velocity Hurricane Zone face product approval rules. We do not claim Florida product approvals or Miami-Dade NOAs.
Florida steel solutionsSome cities write or heavily amend their own building code. The edition and amendments are confirmed on the design basis before calculations are run.
Counties may publish their own ground snow loads and drift rules. The local value goes on the sheet with its source.
Before it goes in
A rejected submittal costs far more time than the few minutes these checks take. These are the checks we run on our part of the package before it leaves for your Engineer of Record.
Who owns this step
World Steel designs and fabricates the steel structure. Approval, the PE seal, the permit and the erection stay with the US contractor and the Engineer of Record they appoint.
Designs, details and fabricates the steel in Vietnam
Prepares the steel calculations, drawings, product data and fabricator documents, assembles them in reviewer order, and drafts answers to plan check comments on the steel.
Reviews, approves and seals for your permit
Reviews the calculations and drawings, approves them, applies the PE seal where the jurisdiction requires it, and owns the structural design for the permit.
Submits, builds the foundations and erects
Files the permit, pays the fees, coordinates the full set with the architect and other trades, and is the building department’s point of contact.
Questions from US contractors
No. The US contractor, our customer, files the permit and deals with the building department. We prepare the steel content of the package and support the answers to plan check comments.
No. World Steel designs and fabricates the steel structure. Your Engineer of Record reviews and approves our calculations and drawings and applies the PE seal where the jurisdiction requires one.
Under the IBC, a building official can allow parts of the design, often the metal building, to be submitted after the main permit. The Engineer of Record lists the deferred items on the permit drawings and reviews the deferred documents before they go to the building department.
The building official decides. World Steel is accredited under IAS AC472, and the IBC lets officials rely on approved fabricator programs for shop inspection. We give your team the documents to ask the question early, before production starts.
We provide the steel data those forms ask for: loads, material grades, product information and fabricator details. The forms themselves are signed by your team.
Send us the comments on the steel. Our engineer drafts a written response and revises calculations or sheets where needed, for your Engineer of Record to review and resubmit through you.