Every structural steel quote is an answer to the question "what exactly are you asking me to build?". When the bid package answers that clearly, fabricators compete on price and schedule. When it does not, they compete on how many exclusions they can write. This checklist is what World Steel's estimators look for first when a US general contractor sends a package.
Drawings and models
Send the latest structural set, even if it is not issued for construction, and mark which sheets are in the steel scope. If a model exists, send it: an IFC or Tekla model lets an estimator take off tonnage in hours rather than days and catches conflicts early.
Architectural drawings still matter. Roof slopes, wall openings, canopies, mezzanines and equipment platforms often carry steel that the structural set only hints at.
Specifications and the code basis
Include Division 05 (metals), Division 09 painting sections and any owner standards. The estimator needs to know:
- the building code and edition adopted where the project is built, for example IBC 2021 or 2024;
- the load standard, usually ASCE 7-22 for current codes;
- material grades for shapes, plate, HSS and bolts;
- whether the project is seismic and which members are part of the seismic force-resisting system.
Loads, if the fabricator designs anything
For a pre-engineered building, a design-build frame or delegated connection design, the fabricator needs the loads: wind speed and exposure, ground snow load, seismic site class and spectral values, collateral and equipment loads, crane data and any special deflection limits. A one-page design criteria sheet signed by the Engineer of Record avoids most RFIs.
Scope split
Write down who supplies what. The usual grey areas are:
- anchor bolts and embeds (who supplies, who sets);
- metal deck, joists and cold-formed framing;
- stairs, railings, ladders and miscellaneous metals;
- roof and wall panels, insulation, doors and trim on a metal building;
- fireproofing and final coats of paint;
- erection, which sits with the US contractor; World Steel designs, fabricates and supplies the steel only.
A scope matrix with one row per item and one column per party fits on a page and prevents most change orders.
Coating requirements
State the surface preparation, primer and finish system, or the exposure the steel will see if you want the fabricator to propose one. Say which members are galvanized, which are fire-protected and which are left bare for concrete encasement.
Schedule and delivery
Give the date steel must be on site, the sequence you plan to erect in and any phasing. For steel fabricated overseas, also give the port or jobsite address so the fabricator can plan ocean freight and the right Incoterms rule. A schedule lets the fabricator book shop capacity; without it the quote can only promise a lead time.
Submittal and inspection expectations
List the submittals you need (shop drawings, calculations, mill certificates, weld procedures, coating records) and how special inspection will work. If inspection must happen at the plant, say so: the fabricator will plan hold points and access.
Contract and commercial terms
State the delivery terms, using an Incoterms rule, and who arranges freight, insurance and customs. Give the payment structure and any retention in the commercial documents, not in the technical scope. Ask bidders to list their exclusions in one place, so you can compare like with like.
Bid form
A simple bid form, listing tonnage by area, shop drawings, coating, packing and delivery as separate lines, makes bids easier to level. It also shows which bidder left something out.
The one-page cover sheet
Put the essentials on one page at the front of the package: project name and address, scope summary, code basis, required-on-site date, quote due date and who to send questions to. Estimators read that page first; a good one shortens the whole bid cycle.
Quick answers
Can a fabricator quote from architectural drawings only?
Yes, as a budget. A firm quote needs structural drawings or, for a design-build package, the design criteria: code edition, loads, geometry and the scope split. Without them every fabricator adds allowances.
Should the bid package include connection design?
Say who designs the connections. If the fabricator does it under delegated design, state the AISC option and the reactions to use. If the Engineer of Record shows every connection, say so.
How much tonnage accuracy should I expect from a quote?
From complete structural drawings, a fabricator's takeoff is normally close to final tonnage. From criteria only, expect a range until the design is done.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US general contractorsHow we support GCs, steel erectors and developers
- Lower cost, lower riskWhere overseas fabrication saves on large jobs
- Section 232 steel importsDuties and paperwork on imported steel
- Landed cost calculatorFreight, duty and fees to your US jobsite
- Contractor partnershipLong-term supply for US contractors
- Solutions by stateState-by-state steel solutions