Packing fabricated steel for export: erection order, labels and lists

Good export packing protects the coating, keeps containers safe and lets the erection crew find the right member first time. Here is what it involves.

· updated November 19, 2026 · 3 min read · World Steel USA engineering team

Steel that leaves the shop in perfect condition can still arrive scratched, bent or impossible to find in a pile. Export packing is what prevents that. It is a small part of the fabricator's work and a large part of the erector's success.

Pack in erection order

The erection crew works by sequence. Packing should follow the same order:

  • the first sequence's columns, beams and bracing ship together and first;
  • within a container or bundle, the pieces needed first sit on top;
  • small parts, bolts and connection plates travel with the members they belong to.

This takes planning when the shop drawings are approved, not when the steel is ready.

Label everything

Every member carries its piece mark from the shop drawings, painted or tagged where the erector will see it. Every bundle carries a label with:

  • project name and destination;
  • bundle number and erection sequence;
  • list of piece marks and quantities;
  • gross weight and lifting points.

Labels must survive weeks at sea and outdoor storage, so use durable tags and markings.

Protect the coating

  • Timber dunnage between layers so coated surfaces do not rub.
  • Soft slings or protected chains for lifting.
  • Edge protectors on flanges and plate edges.
  • Wrapping for galvanized or finished members that must look perfect.

Secure the load

Containers and flat racks are lashed and blocked so nothing shifts in heavy seas. Long members may ship on flat racks or as breakbulk. The fabricator should provide stowage plans and photos of each loaded unit.

Packing lists and photos

A packing list is more than an inventory. A good one lets the receiving crew check each bundle against the list in minutes and tells the erector where every piece is. World Steel shares packing lists, container reports and photos in PEB Studio, so the US contractor sees exactly what is coming before the ship arrives.

Small parts

Bolts, nuts, washers, anchor bolt templates and small plates are packed in labelled crates or bags by sequence. Missing bolts are one of the most common reasons erection stops; count them twice.

Handling at the port and on site

Packing must suit every lift between shop and site. Mark lifting points on long members and heavy bundles, use spreader bars where needed, and state the weight on every label. A bundle that can only be lifted with the right rigging should say so clearly.

Weather protection

Steel can spend weeks at sea and in port yards. Coated members tolerate weather, but bolts, small parts and some finished surfaces need cover. Crates and bags for small parts should be weatherproof and clearly labelled.

Containers and flat racks

When steel ships in containers, the packing plan should use the space well without overloading any container or placing heavy items high. Loading drawings that show which bundles go in which container, and in what order, make unloading at the site straightforward. For flat racks, lashing points and dunnage spacing must suit the member lengths and weights.

Inspection before closing

Agree that the contractor or its inspector can check packing before containers are sealed, either on site or by video. Once a container is sealed for export, opening it again means delays and paperwork. Photos of each container interior, taken just before closing, help settle any later question about damage in transit.

Documents in the container

Place a copy of the packing list inside each container or bundle, in a waterproof pouch, in addition to the electronic copy. Site crews often work from paper on the first day.

What to ask your fabricator

  1. Do you pack in erection order?
  2. What is on each bundle label?
  3. How do you protect coated surfaces?
  4. Will I get packing lists and photos per container before arrival?
  5. How are bolts and small parts packed and listed?

Packing well costs the fabricator a little more time; it saves the erector far more on site.

Quick answers

What does packing in erection order mean?

Members are grouped and loaded so that the steel for the first erection sequence arrives first and sits on top, followed by later sequences.

How are coated members protected?

With timber dunnage between layers, soft slings, edge protectors and wrapping for finished or galvanized surfaces where needed.

Can I see what is in each container before it arrives?

With World Steel, yes: packing lists, photos and container reports are shared online in PEB Studio.