ASCE 7-22 design loads: what a steel fabricator needs from you

Most redesigns start with a missing or wrong load. This is the list of ASCE 7-22 inputs that lets a steel package be designed once.

· updated November 19, 2026 · 3 min read · World Steel USA engineering team

ASCE 7 is the load standard behind the International Building Code. When a fabricator designs a pre-engineered building, a delegated frame or connections, every member size depends on the loads it receives. Missing one is the most common reason a steel design has to be redone.

Start with the code edition and risk category

Confirm the building code and edition adopted where the project is built, and therefore the ASCE 7 edition. IBC 2024 references ASCE 7-22. Then state the risk category (I to IV). It scales wind speeds, snow and seismic importance, so a Risk Category IV emergency facility gets much heavier loads than a Category II warehouse of the same size.

Wind

The fabricator needs:

  • basic wind speed for the risk category, from the ASCE Hazard Tool;
  • exposure category (B, C or D) based on the surrounding terrain;
  • enclosure classification: enclosed, partially enclosed or open;
  • topographic effects if the site sits on a hill or escarpment;
  • for hurricane-prone regions, whether the envelope must resist wind-borne debris.

ASCE 7-22 also added tornado loads for Risk Category III and IV buildings in tornado-prone areas, which can govern some designs in the central and southeastern US.

Snow

Give the ground snow load. ASCE 7-22 changed how ground snow loads are mapped, using reliability-targeted values that differ by risk category, so values taken from an older drawing may be out of date. Also state roof slope, thermal condition, exposure, and any adjacent higher roofs or parapets that cause drifting.

Seismic

Provide the site class from the geotechnical report and the spectral values for the site. ASCE 7-22 introduced multi-period response spectra and changed site class definitions, so a current geotechnical report matters. The seismic design category that results drives the detailing rules of AISC 341.

Dead, collateral and live loads

  • Collateral loads: sprinklers, lighting, ductwork, ceilings and solar panels hung from the roof.
  • Live loads: roof live load, floor occupancy loads, mezzanine and storage loads.
  • Equipment loads: rooftop units, process equipment, hoists.

On metal buildings, under-estimated collateral loads are the most common reason a roof has to be strengthened later.

Cranes and special loads

For crane buildings, give the crane capacity, span, wheel loads, duty class and runway arrangement. Also list any vibration-sensitive equipment, special deflection limits and future expansion the frame must allow for.

Rain and ponding

Roof drainage design affects steel: secondary drainage depth sets rain load, and low-slope roofs need to be checked for ponding.

Load combinations and serviceability

Strength is only half of the design. Give the fabricator the serviceability limits the Engineer of Record expects, because they often govern member sizes in steel buildings:

  • Drift limits for frames under wind and seismic loads, especially where brick, glazing or cranes are attached.
  • Deflection limits for rafters, beams and girts, for example L/180 for a metal roof or L/240 to L/360 for members supporting ceilings or brittle finishes.
  • Vibration criteria for floors supporting sensitive equipment, offices or long spans.

ASCE 7 and the building code set the load combinations; the project may add stricter limits. Writing them on the criteria sheet avoids a design that is strong enough but still rejected at review.

Future loads

Owners often add rooftop solar, extra mechanical units or heavier racking years after handover. If that is likely, say so now and give an allowance. Designing for a future load costs little at the start and a great deal later, when strengthening means working above an occupied building.

Common mistakes

  1. Using wind speeds or snow loads from a previous project nearby, under an older ASCE 7 edition.
  2. Forgetting collateral loads from sprinklers and lighting.
  3. Leaving out snow drift at adjacent roofs, parapets and rooftop equipment screens.
  4. Assuming a site class instead of waiting for the geotechnical report.
  5. Leaving out tornado loads for Risk Category III and IV buildings where ASCE 7-22 requires them.

One page, signed

The best way to hand these to a fabricator is a one-page design criteria sheet from the Engineer of Record. World Steel uses it to design to the stated loads, and the calculations come back for the Engineer of Record's review with every input listed, so nothing is assumed.

Quick answers

Which edition of ASCE 7 applies?

The one referenced by the building code adopted where the project is built. IBC 2024 references ASCE 7-22; some jurisdictions still use IBC 2018 or 2021 with ASCE 7-16.

Where do I get the site values?

The ASCE Hazard Tool gives wind, snow, seismic, ice, rain, flood and tornado values for an address. Local amendments can raise them, so check with the building department.

Who signs the loads?

The US Engineer of Record sets the design criteria. The fabricator designs to them and submits calculations for review.